Facts of the Case
- The
Agreement: On January 24, 2013, Moongipa Realty Pvt.
Ltd. (formerly known as Axayraj Buildwell Pvt. Ltd. - Appellant/Promoter)
entered into seven registered Agreements for Sale with Shekhar Rajan
Prasad (Respondent/Allottee). The agreements concerned Shop Nos. G-37 to
G-43, admeasuring a total carpet area of 1,191 sq. ft. on the ground floor
of the commercial building "Moongipa Arcade" (formerly "Ark
Arcade") located in Andheri, Mumbai, for a total agreed consideration
of ₹2,83,84,000.
- Financial
Discrepancies: A dispute arose regarding the exact amount
of consideration paid by the allottee. The Appellant contended that the
Respondent had paid ₹1,12,33,600 (excluding taxes), leaving a balance of
₹1,71,50,400. Conversely, the Respondent claimed a total payment of
₹1,14,33,600 (including taxes), establishing a balance consideration of
₹1,69,50,400. The Respondent was also contractually liable to pay
₹7,92,188 toward other miscellaneous statutory charges along with
applicable Service Tax/VAT.
- Delay
and Regulatory Recourse: Due to construction delays
and the non-completion of the commercial project within the agreed
timelines, the Respondent filed two formal complaints (Complaint Nos.
CC006000000044128 of 2018 and CC006000000181957 of 2019) before the
Maharashtra Real Estate Regulatory Authority (MahaRERA).
- MahaRERA
Order: On January 28, 2021, MahaRERA issued a
common order directing the Appellant to pay interest at the rate of 9% per
annum on the total consideration paid by the Respondent. Crucially, the
authority restrained the Appellant from modifying the sanctioned plans of
the commercial layout without strictly complying with the statutory
procedure set forth under Section 14 of the RERA Act.
- Appellate
Tribunal Modification: Aggrieved by the regulatory order, the
Appellant approached the Maharashtra Real Estate Appellate Tribunal via
Appeal Nos. AT006000000053065 and AT006000000053066 of 2021. On March 23,
2022, the Appellate Tribunal partially modified MahaRERA's order, specifically
executing an injunction restraining the Appellant from making any
modifications to the sanctioned layout plans that related explicitly to
the commercial shops purchased by the Respondent without obtaining his
express prior consent.
- High
Court Appeal: The Appellant filed Second Appeal Nos. 549
and 550 of 2022 along with Interim Application Nos. 16754 and 16757 of
2022 before the Hon'ble Bombay High Court challenging the Appellate
Tribunal's ruling. Concurrently, the Respondent initiated Execution Application
Nos. 23 and 24 of 2022 before the Appellate Tribunal to enforce the
decree.
Issues Involved
- Whether
a promoter can modify or alter sanctioned construction layouts and change
allocated units without executing a legally valid substitution or
supplementary agreement that complies with Section 14 of the RERA Act.
- Whether
an allottee is entitled to receive continuous interest under RERA for
delayed possession when the parties transition into a revised arrangement
with a deferred possession date.
- Whether
the implementation of judicially recorded "Consent Terms" during
the pendency of a Second Appeal before a High Court effectively
extinguishes prior decrees passed by MahaRERA and the Real Estate
Appellate Tribunal.
Petitioner’s (Appellant's) Arguments
- Financial
Redressal and Compromise: The Appellant argued that
to resolve the long-standing dispute and terminate protracted litigation,
they were willing to formally acknowledge and accept the Respondent’s
calculation of the paid consideration as ₹1,14,33,600.
- Substitution
of Units: The Appellant proposed a mutual substitution
of the original units. In lieu of the originally booked Shop Nos. G-37 to
G-43 (1,191 sq. ft.), they offered "New Shops" (Shop Nos. G-33
to G-36 and G-41 to G-43) comprising a larger total carpet area of 1,228
sq. ft. on the ground floor of Phase III of the project. They undertook
not to demand any additional monetary compensation for the excess 37 sq.
ft. provided.
- Third-Party
Settlement: Regarding the fact that Shop Nos. G-33 to
G-36 were already allocated to a third party (Mr. Jitendra Dewoolkar), the
Appellant presented a formal undertaking via an affidavit from the third
party, expressing full compliance to execute cancellation or exchange
deeds to free up the units for the Respondent.
- Staged
Payments: The Appellant prayed that the balance
payment of ₹1,69,50,400 should be strictly synchronized with the physical
progress of construction verified by structural architect certificates.
Respondent’s Arguments
- Protection
of Financial Interests: The Respondent contended
that any extension of the project deadline or alteration of the physical
location of the commercial spaces must safeguard the finances already
invested.
- Enforcement
of Interest: The Respondent insisted on the complete
withdrawal of the accrued interest deposited by the builder with the
Appellate Tribunal (amounting to ₹80,77,000 for the period from April 1,
2014, to May 31, 2022).
- Compensatory
Indemnity: The Respondent demanded an ongoing interest
payout at 9% per annum from June 1, 2022, until the final physical
possession of the new commercial spaces is delivered along with a valid
Occupation Certificate (OC).
- Mutual
Execution: The Respondent agreed to execute all
supplementary contracts, rectification deeds, and formal adjustments
through his constituted attorney, provided the stamp duty, registration
fees, and incidental costs were borne entirely by the builder.
Court Order / Findings
- Acceptance
of Consent Terms: The Hon’ble High Court, presided over
by Justice Madhav J. Jamdar, took the comprehensive "Consent
Terms" on record, marked as 'X', duly executed by the authorized
signatories and advocates of both parties.
- Substitution
of Lower Decrees: The High Court ordered that upon the
Appellant fulfilling its specific structural obligations—specifically
executing the cancellation/rectification deeds with the third party within
45 days—the impugned orders of MahaRERA (dated January 28, 2021) and the
Maharashtra Real Estate Appellate Tribunal (dated March 23, 2022) would
stand entirely substituted by the judicial order passed in terms of these
Consent Terms.
- Acceptance
of Third-Party Undertaking: The Court formally accepted
the affidavit-cum-undertaking (marked 'X1') of the third-party allottee,
binding him to execute the required cancellation and exchange deeds to
facilitate the clean title transfer of the new units to the Respondent.
- Disposal
of Appeals: Consequently, the High Court disposed of
Second Appeal Nos. 549 and 550 of 2022 in strict alignment with the
Consent Terms. All connected Interim Applications were disposed of as they
did not survive independently, and the Respondent was directed to withdraw
his Execution Applications from the Appellate Tribunal.
Important Clarification
- Strict
Adherence to Section 14: The court-sanctioned
agreement establishes that any modification or reallocation of real estate
property units under Section 14 requires a clear, registered supplementary
mechanism (Rectification Deeds/Supplementary Agreements) where the
promoter bears the absolute financial burden of stamp duty and
registration.
- Architect's
Certification for Milestone Payments: Demands for balance
consideration amounts cannot be raised arbitrarily by a promoter. Every
demand milestone (e.g., Plinth, Slab, Brickwork, Flooring) must be
accompanied by an official certificate issued by the Project Architect
proving construction stage completion.
- Set-off
Mechanism for Interest Default: In the event the promoter
defaults on paying the monthly 9% p.a. interest on the paid consideration,
a clear contractual right is established for the allottee to unilaterally
deduct/set off the outstanding interest amount from the subsequent
construction-linked milestones payable to the promoter.
Section Involved
- Section
14 of the Real Estate (Regulation and Development) Act, 2016 (RERA):
Adherence to sanctioned plans and project specifications, restricting the
promoter from making structural modifications or alterations without the
prior written consent of the allottee.
- Section
18 of the Real Estate (Regulation and Development) Act, 2016 (RERA):
Liability of the promoter to pay interest or compensation for failure to
give possession of the apartment, plot, or building in accordance with the
terms of the agreement for sale.
Link to download the order -https://mytaxexpert.co.in/uploads/1782895891_44compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment