Facts of the Case
The petitioner, M/s Jaypee Projects Limited,
was awarded a contract by the Public Works Department (Roads & Buildings),
Government of Tripura, for the construction of the Composite Tripura
Legislative Assembly Building and the New Secretariat Complex at Agartala. Upon
successful completion of the project, the work was duly certified and handed
over to the Government authorities without any dispute regarding the quality or
execution of the work.
Subsequently, the petitioner claimed payment of
outstanding dues amounting to Rs. 27,46,96,122.55, including escalation
charges, GST reimbursement, VAT reimbursement and other pending contractual
payments together with interest at 18% per annum. Despite repeated
representations and reminder letters, the alleged outstanding amounts remained
unpaid.
Aggrieved by the prolonged non-payment, the
petitioner invoked the writ jurisdiction of the High Court under Article 226
of the Constitution of India, alleging violation of Articles 14, 19(1)(g),
21 and 300A and seeking directions for immediate release of the dues with
interest.
Issues Involved
- Whether a writ petition under Article 226 of the Constitution of
India is maintainable for recovery of disputed contractual dues.
- Whether the High Court should entertain a writ petition when
disputed questions of fact require adjudication.
- Whether the existence of an arbitration clause and alternative
dispute resolution mechanism bars exercise of writ jurisdiction in
contractual disputes.
- Whether alleged non-payment of contractual dues constitutes violation
of constitutional rights under Articles 14, 19(1)(g), 21 and 300A.
Petitioner’s Arguments
The petitioner contended that:
- The entire contractual work had been completed to the satisfaction
of the respondents, and completion certificates had already been issued.
- Under the contractual clauses governing escalation, taxes and
reimbursement, the petitioner was legally entitled to receive the pending
escalation amount, GST reimbursement and other contractual payments.
- The respondents had substantially admitted their liability and
merely postponed payment on the ground of non-availability of Government
funds.
- Indefinite withholding of legitimate contractual dues was arbitrary
and violative of Articles 14, 19(1)(g), 21 and 300A of the Constitution.
- Although the agreement contained an arbitration clause, the
respondents' admitted liability made the writ petition maintainable for
enforcement of undisputed contractual obligations.
- The Court should direct immediate payment along with interest at
18% from the date the amounts became due.
Respondent’s Arguments
The respondents submitted that:
- The writ petition involved several disputed questions of fact
regarding the quantum and admissibility of the claims.
- The escalation claim was not maintainable under Clause 47 of
the contract because the stipulated completion period attracted the
contractual restriction on escalation.
- GST reimbursement was also subject to contractual conditions and
determination of delay attributable to the contractor.
- Certain payments had already been released, while the remaining
amounts were dependent upon availability of funds, approval of time
extension and finalization of deviations.
- The agreement itself provided an effective alternative dispute
resolution mechanism through arbitration, which the petitioner had already
invoked by seeking appointment of an arbitrator.
- Since disputed contractual rights were involved, the writ petition
was not maintainable under Article 226.
Court Order / Findings
The High Court dismissed the writ petition and held
that:
- The dispute involved complex and disputed questions of fact
relating to contractual payments, escalation, GST reimbursement and
computation of dues.
- The petitioner itself had raised varying claims at different
stages, making factual adjudication necessary.
- Such disputed contractual issues cannot ordinarily be decided in
writ jurisdiction under Article 226.
- Where an effective alternative remedy, including arbitration,
exists under the contract, the High Court should ordinarily decline to
exercise its extraordinary writ jurisdiction.
- The Court relied upon the Supreme Court judgment in Bhaven
Construction v. Executive Engineer, Sardar Sarovar Narmada Nigam Ltd.
& Another, (2022) 1 SCC 75, reiterating that writ jurisdiction
should be exercised only in exceptional circumstances where statutory
remedies are ineffective.
- Since arbitration proceedings had already been sought by the
petitioner and contractual remedies remained available, the writ petition
was held to be not maintainable and was accordingly dismissed.
Important Clarification
The judgment reiterates that:
- Recovery of disputed contractual dues generally cannot be pursued
through a writ petition under Article 226.
- Courts ordinarily refuse to adjudicate disputed questions of fact
involving contractual rights in writ jurisdiction.
- Existence of an arbitration clause or contractual dispute
resolution mechanism is a significant factor against entertaining a writ
petition.
- Mere allegation of non-payment by a Government authority does not automatically
justify invocation of constitutional writ jurisdiction where disputed
facts exist.
- Constitutional remedies are exceptional and do not replace agreed
contractual dispute resolution mechanisms.
Sections / Constitutional Provisions / Contractual Clauses Involved
- Article 226 – Constitution of India
- Article 14 – Constitution of India
- Article 19(1)(g) –
Constitution of India
- Article 21 – Constitution of India
- Article 300A – Constitution of India
- Clause 24 – Alternative Dispute Resolution
- Clause 25 – Arbitration Procedure
- Clause 26 – Contractual Dispute Resolution
- Clause 31.1 – Final Completion
Certificate
- Clause 34 – Defect Liability Period
- Clause 37.2 – Taxes, GST and
Reimbursement
- Clause 47 – Price Escalation
Link to
download the order -
https://www.mytaxexpert.co.in/uploads/1782969989_89compressed.pdf
Disclaimer
This content is shared strictly for general
information and knowledge purposes only. Readers should independently verify
the information from reliable sources. It is not intended to provide legal,
professional, or advisory guidance. The author and the organisation disclaim
all liability arising from the use of this content. The material has been
prepared with the assistance of AI tools.
0 Comments
Leave a Comment