Facts of the Case
The petitioner, M/s Ratna Khanij Udyog, was awarded
contracts by the respondents for construction and widening of roads. These
contracts were awarded before the introduction of the GST regime, when no
service tax was payable on the concerned works.
After implementation of GST with effect from
01.07.2017, the petitioner became liable to pay GST on the execution of the
remaining contractual work. Since the contract price had been quoted under the
earlier tax regime without considering GST liability, the petitioner contended
that the additional GST burden should be reimbursed by the Government.
Accordingly, the petitioner approached the High
Court seeking reimbursement of GST paid on services rendered under Categories
C1, C2 and C3 of the contract.
Issues Involved
- Whether a contractor executing contracts awarded before the
implementation of GST is entitled to reimbursement of the additional GST
liability incurred after 01.07.2017.
- Whether reimbursement can be granted without the contractor
furnishing complete documentary evidence showing the additional tax
burden.
- Whether the Government authorities are required to examine and
process such reimbursement claims upon submission of supporting documents.
Petitioner’s Arguments
- The contracts were awarded under the pre-GST tax regime where the
quoted prices did not include GST or service tax.
- Introduction of GST resulted in an unforeseen additional tax
liability during execution of the contracts.
- Since this additional liability arose solely because of the change
in the tax regime, the Government should reimburse the additional GST
paid.
- The petitioner also submitted that relevant supporting documents
had already been filed and expressed willingness to submit a fresh claim
with additional documents, if required.
Respondent’s Arguments
- The State did not dispute the legal entitlement of contractors to
reimbursement of GST relating to contracts finalized before 01.07.2017 but
executed thereafter.
- The respondents stated that reimbursement could be considered only
after the contractor furnished complete details regarding:
- Taxes paid prior to 01.07.2017;
- GST paid after 01.07.2017; and
- The exact difference representing the additional tax burden.
- The State further submitted that the petitioner had approached the
High Court without first submitting a properly documented claim before the
competent departmental authorities.
- Upon receipt of complete documentary evidence, the Government was
willing to examine and process the reimbursement claim in accordance with
the applicable policy.
Court Order / Findings
The High Court observed that the respondents had
categorically accepted the principle that GST reimbursement could be granted in
respect of contracts finalized before 01.07.2017, subject to verification of
the additional tax liability actually suffered by the contractor.
The Court held that the petitioner should submit a
fresh claim before the competent authority along with cogent documentary
evidence demonstrating the additional GST liability incurred during execution
of the contract.
The Court directed the respondent authorities to:
- Receive and examine the fresh claim;
- Verify the supporting documents;
- Scrutinize the claim in accordance with the applicable Government
policy; and
- Pass an appropriate decision within 90 days from the date of
receipt of the fresh claim.
Accordingly, the writ petition was disposed of with
the above directions.
Important Clarification
- Contractors executing pre-GST contracts are not automatically
entitled to reimbursement merely because GST became applicable.
- Reimbursement is available where Government policy permits and
where the contractor establishes the actual additional tax burden through
proper documentary evidence.
- The Government itself acknowledged that reimbursement claims
relating to contracts finalized before 01.07.2017 may be considered after
verification.
- Proper documentation regarding pre-GST taxes, GST paid, and the
differential tax liability is essential for processing such claims.
- The competent authority must decide such reimbursement claims
within the time stipulated by the Court after receipt of a complete
application.
Key Takeaway
The Chhattisgarh High Court reaffirmed that
contractors executing contracts awarded before the introduction of GST may seek
reimbursement of the additional GST burden arising due to the new tax regime.
However, such reimbursement is subject to submission of complete documentary
proof and verification by the competent Government authorities under the
applicable reimbursement policy.
Sections Involved
- Goods and Services Tax (GST) Regime (Effective from 01.07.2017)
- Principles relating to reimbursement of additional tax burden
arising due to introduction of GST
- Government Policy governing reimbursement of GST on contracts
awarded under the pre-GST regime
- Article 226 of the Constitution of India (Writ Jurisdiction)
Link to download the order - https://mytaxexpert.co.in/uploads/1782968233_224compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment