Facts of the Case
Army Welfare Housing Organisation (AWHO) awarded a
construction contract to Shapoorji Pallonji and Company Private Limited for a
residential project at Greater Noida. The respondent subsequently awarded the
electrical works to Brilltech Engineers Private Limited under a Work Order
dated 19.12.2011.
The petitioner completed the electrical works and raised
running account bills. It claimed that substantial amounts towards pending
bills, security deposit, and interest remained unpaid despite completion of the
project. Demand notices were issued and proceedings were initiated before MSME
Samadhaan and later before the NCLT under Section 9 of the Insolvency and
Bankruptcy Code.
As the disputes remained unresolved, the petitioner invoked
the arbitration clause and filed a petition under Section 11(6) of the
Arbitration and Conciliation Act, 1996 seeking appointment of an arbitrator. A
connected petition under Section 9 of the Act sought interim protection by
directing the respondent to maintain funds sufficient to secure the claim.
Issues Involved
- Whether
arbitrable disputes existed between the parties despite the petitioner
having earlier initiated proceedings before the NCLT.
- Whether
filing proceedings under the Insolvency and Bankruptcy Code amounted to
forum shopping.
- Whether
the arbitration petition was maintainable without a separate notice under
Section 21 of the Arbitration and Conciliation Act.
- Whether
the disputes were liable to be referred to arbitration under Clause 13 of
the Work Order.
- Whether
interim protection under Section 9 of the Arbitration and Conciliation Act
should be granted.
Petitioner's Arguments
- The
petitioner contended that the respondent had failed to release legitimate
payments for completed work despite certification and completion of the
project.
- Clause
13 of the Work Order contained a valid arbitration agreement requiring
disputes to be referred to arbitration.
- Genuine
disputes had arisen regarding unpaid bills, security deposit, and
interest.
- The
respondent had wrongfully withheld payments despite receiving
corresponding payments from AWHO.
- The
demand notice and subsequent correspondence sufficiently conveyed the
intention to invoke legal remedies including arbitration.
- Interim
protection was necessary to safeguard the claim amount pending
arbitration.
Respondent's Arguments
- The
respondent argued that by approaching the NCLT under Section 9 of the
Insolvency and Bankruptcy Code, the petitioner had admitted that there
were no arbitrable disputes.
- It
contended that the petitioner had failed to comply with the dispute
resolution procedure prescribed in Clause 13 before invoking arbitration.
- No
valid notice under Section 21 of the Arbitration and Conciliation Act had
been served prior to filing the petition under Section 11.
- The
petitioner had raised inconsistent claims before different forums,
amounting to forum shopping.
- According
to the respondent, all payments due under the contract had already been
made after permissible deductions and no amount remained payable.
Court Findings / Order
The Delhi High Court held that:
- The
existence of proceedings before the NCLT did not eliminate the existence
of arbitrable disputes. The respondent had consistently disputed the
petitioner's claims, thereby establishing the presence of genuine disputes.
- Mere
initiation of proceedings under the Insolvency and Bankruptcy Code did not
amount to forum shopping since proceedings under the IBC and arbitration
serve different legal purposes.
- Although
a separate notice under Section 21 was disputed, the demand notice,
subsequent correspondence, and the respondent's conduct sufficiently
demonstrated awareness of the disputes and the intention to resort to
arbitration. The requirement of Section 21 stood substantially complied
with.
- The
arbitration clause contained in Clause 13 of the Work Order was valid and
enforceable.
- The
disputes were referable to arbitration.
- Ms.
R. Kiran Nath (Retired District & Sessions Judge) was appointed as the
Sole Arbitrator under Section 11 of the Arbitration and Conciliation Act,
1996.
- The
respondent was directed to maintain a balance of ₹99,87,760/- until
adjudication of the disputes, subject to modification by the Arbitrator.
Both the petitions under Sections 11 and 9 of the Arbitration and
Conciliation Act were allowed.
Important Clarification
- Filing
proceedings under the Insolvency and Bankruptcy Code does not
automatically bar arbitration where genuine disputes exist.
- Different
statutory remedies with distinct objectives can be pursued without
attracting the doctrine of forum shopping.
- A
separate formal notice under Section 21 may not always be fatal where the
intention to invoke arbitration has been clearly communicated and the
opposite party has fully understood the dispute.
- Courts
will adopt a practical approach while examining compliance with Section 21
where parties have already engaged in extensive dispute resolution
proceedings.
- The
judgment reinforces the pro-arbitration approach adopted by Indian courts
while interpreting procedural requirements under the Arbitration and
Conciliation Act, 1996.
Sections Involved
- Section
9, Arbitration and Conciliation Act, 1996
- Section
11(6), Arbitration and Conciliation Act, 1996
- Section
21, Arbitration and Conciliation Act, 1996
- Section
12(1) & Section 12(5), Arbitration and Conciliation Act, 1996
- Section
9, Insolvency and Bankruptcy Code, 2016
- Clause 13 of the Work Order (Arbitration Clause)
Link to download the order -
https://mytaxexpert.co.in/uploads/1782970139_177compressed.pdf
Disclaimer
This content is shared strictly for general information and
knowledge purposes only. Readers should independently verify the information
from reliable sources. It is not intended to provide legal, professional, or
advisory guidance. The author and the organisation disclaim all liability
arising from the use of this content. The material has been prepared with the
assistance of AI tools.
0 Comments
Leave a Comment