Facts of the Case
The petitioner, Gayatri Ventures, was awarded a work
contract by the Water Resources Department of the State of Chhattisgarh through
a work order dated 06.05.2022. At the time of issuance of the work order, GST
on the contract was applicable at the rate of 12%.
Subsequently, with effect from 18.07.2022, the GST rate
applicable to the contract increased from 12% to 18%, resulting in an
additional tax burden upon the petitioner.
Thereafter, the Water Resources Department issued an order
dated 30.09.2022 amending Clause 2.17.1 of the contract. The amended clause
provided that if any new tax, levy, cess, royalty, or any increase in GST
became applicable after submission of the tender, the contractor, upon payment
of such statutory liability, would be entitled to reimbursement from the department
after producing proof of payment.
The petitioner submitted a detailed representation dated
07.11.2022 seeking reimbursement of the additional GST liability. Since no
decision was taken by the authorities, the petitioner approached the High Court
seeking appropriate relief.
Issues Involved
- Whether
the petitioner was entitled to reimbursement of the additional GST
liability arising from the increase in GST rate from 12% to 18%.
- Whether
the amended Clause 2.17.1 obligated the State Government to reimburse the
contractor for the enhanced GST liability.
- Whether
the High Court should direct the respondent authorities to decide the
pending representation seeking reimbursement.
Petitioner's Arguments
- The
petitioner submitted that when the work order was issued, GST was payable
at 12%, whereas the subsequent increase to 18% imposed an unforeseen
statutory burden.
- It
was argued that the State Government itself amended Clause 2.17.1 on
30.09.2022, clearly providing that any new tax, levy, cess, royalty, or increase
in GST imposed after submission of the tender would be reimbursed by the
department upon production of proof of payment.
- The
petitioner further contended that the amended clause also required
contractors to refund any benefit arising from reduction in tax rates to
the Government. Therefore, on the same principle, the Government was
equally bound to reimburse contractors when tax rates increased.
- The
petitioner informed the Court that a detailed representation dated
07.11.2022 had already been submitted before the competent authority,
which remained undecided, and therefore requested the Court to direct the
respondents to consider and dispose of the representation.
Respondents' Arguments
- The
State did not oppose the limited prayer made by the petitioner.
- It
was submitted that the petitioner's representation would be examined and
decided strictly in accordance with the applicable law and the contractual
provisions governing the parties.
Court Order / Findings
The High Court disposed of the writ petition with the
following directions:
- The
respondent authorities were directed to consider and decide the
petitioner's representation dated 07.11.2022 as expeditiously as possible,
preferably within 90 days.
- While
deciding the representation, the authorities were specifically directed to
consider the amendment dated 30.09.2022 incorporating Clause 2.17.1
relating to reimbursement of additional statutory tax liability.
- The
petitioner was granted liberty to submit a fresh representation along with
documentary proof demonstrating the additional GST liability incurred.
- The
Court further observed that if the representation was decided in favour of
the petitioner, the respondents should take immediate steps for
reimbursement of the admissible amount.
Accordingly, the writ petition was disposed of.
Important Clarification
- Increase
in GST after submission of the tender may entitle a contractor to
reimbursement where the contract specifically provides for such
reimbursement.
- An
amended contractual clause governing statutory tax variations must be
considered while deciding reimbursement claims.
- The
High Court did not adjudicate the reimbursement claim on merits but
directed the competent authority to decide the representation in
accordance with law and the amended contractual provisions.
- Contractors
claiming reimbursement should submit documentary proof of payment of the
additional GST liability to facilitate consideration of their claim.
Sections / Clauses Involved
- Clause
2.17.1 of the Contract (as amended on 30.09.2022)
- Goods
and Services Tax (GST) provisions relating to change in tax rates
- Contractual
reimbursement of additional statutory tax liability
- Article 226 of the Constitution of India (Writ Jurisdiction)
Link to download the order -
https://mytaxexpert.co.in/uploads/1782972041_184compressed.pdf
Disclaimer
This content is shared strictly for general information and
knowledge purposes only. Readers should independently verify the information
from reliable sources. It is not intended to provide legal, professional, or
advisory guidance. The author and the organisation disclaim all liability arising
from the use of this content. The material has been prepared with the
assistance of AI tools.
0 Comments
Leave a Comment