Facts of the Case
- Tender
Issuance: The Animal Husbandry and Veterinary
Department, Government of Assam, issued a public tender under the Rural
Infrastructure Development Fund (RIDF-XXVII) for the construction of Assam
Type Sub-Centre Buildings, which included electrification, water supply,
and sanitary installations in the Nalbari district.
- Financial
Scope: The estimated cost allocated for the public
infrastructure project stood at ₹33,71,000/- with a strict contractual
completion deadline of 180 days.
- Procurement
Process: The department implemented a competitive
two-bid procurement system comprising independent technical and financial
evaluation stages.
- Bidding
Outcome: Registered contractors Diganta Borah,
Hemanta Kumar Borah, and Bobita Borah participated and emerged as the
lowest (L-1) bidders by quoting rates that were more than 15% below the
prevailing Detailed Schedule Rate (DSR).
- Departmental
Compliance: In alignment with Clause 2.A.(g) of the
tender criteria, the L-1 bidders provided rate analyses and structural
documentation to justify their financial quotes. The Bid Process
Management Committee ordered physical verifications, which were executed
by a departmental engineer who certified the feasibility of the bids.
- Tender
Award: Following the verification, the Committee
recommended awarding the project to the L-1 bidders, contingent upon the
submission of a 12% Additional Performance Guarantee and a timely
execution undertaking. Formal work orders were issued on January 6, 2024.
- Litigation
Trigger: Balen Roy Medhi, an unsuccessful bidder who
submitted a substantially higher quote, challenged the allotment by filing
a series of writ petitions before the Gauhati High Court. A Single Judge
subsequently set aside the work orders, prompting the private contractors
and the State of Assam to file structural Writ Appeals.
Issues Involved
- Whether
the Single Judge erred by overstepping the established boundaries of
judicial review under Article 226 by performing an appellate evaluation of
an expert technical committee's decision-making process in a public
tender.
- Whether
minor procedural discrepancies, such as non-geo-tagged site photographs or
the formatting of third-party material supplier quotes (GSTIN validation),
are sufficient grounds to invalidate an active public work contract.
- Whether
it is legally justifiable to halt or redirect public infrastructure works
at the behest of an unsuccessful higher bidder after significant execution
progress has already been achieved.
Petitioner’s Arguments (Appellants - Contractors
& State of Assam)
- Adherence
to Tender Protocols: The appellants argued that they fully
complied with Clause 2.A.(g) of the bid parameters by presenting
comprehensive rate justifications and supporting evidentiary portfolios
along with their low-rate bids.
- Expert
Valuation Finality: The evaluation and validation of the
low financial quotes were meticulously processed by the Bid Process
Management Committee, a body consisting of domain-specific technical
experts whose decisions should not be lightly substituted by a court.
- Irrationality
of Supplier Objections: The legal team asserted
that the technical focus remained on the main bidder’s legal eligibility.
The status of a material supplier’s internal GSTIN registry or the
plain-paper formatting of their quotes did not impact the primary
contractor's compliance, as the supplier's rate and material availability
were the only relevant criteria.
- Prejudicial
Contractual Disruption: The appellants underscored
that substantial infrastructural milestones had been reached on-site.
Halting active operations based on generalized allegations from a
defeated, higher-quoting bidder directly undermined public economic
interests and halted project momentum.
- Disregard
of Supreme Court Precedents: The state and the
contractors maintained that the Single Judge's intervention fundamentally
conflicted with landmark Apex Court rulings governing judicial restraint
in commercial tenders, specifically Afcon Infrastructure Limited v.
Nagpur Metro Rail Corporation Limited and Bharat Coking Coal
Limited v. A.R.M. Dev Prabha.
Respondent’s Arguments (Private Opponent - Balen
Roy Medhi)
- Allegations
of State Collusion: The respondent contended that the
acceptance of unfeasibly low rates was a direct byproduct of systemic
institutional collusion and administrative bias favoring the select group
of contractors.
- Fraudulent
Verification Evidence: The respondent presented evidence
indicating that the field inspection photographs submitted by the
departmental engineer to validate multiple distinct project sites were
completely identical and lacked mandated geo-tagging verifications.
- Documentary
Deficiencies: Attention was drawn to structural flaws in
the bid filings, demonstrating that one of the appellant's sub-contracted
quotes carried an invalid GSTIN that did not match the entity, and that
clarification letters from suppliers lacked official corporate letterheads
or legal seals.
- Contestation
of Work Progress: The respondent disputed the state's
factual assertions regarding the percentage of work completed and payments
disbursed, claiming that substantial phases remained incomplete and that
the rapid progress claims lacked valid corroboration inside official departmental
measurement books.
Court Order / Findings
- Reversal
of the Single Judge Order: The Division Bench
consisting of Chief Justice Ashutosh Kumar and Justice Arun Dev Choudhury
set aside the Single Judge's judgment, declaring the judicial cancellation
of the work orders wholly unjustified.
- Limitation
of Judicial Intervention: The Court re-emphasized
that judicial review must target the legality of the decision-making
process rather than the merit of the decision itself. Courts must
exercise extreme restraint unless the administrative actions are
demonstrably plagued by deep-seated mala fides, perversity, or
irrationality.
- Validation
of Expert Agency Discretion: The Division Bench observed
that the technical viability of the low rates had been verified via a
multi-layered process by the Bid Processing Management Committee. The
Bench ruled that an unsuccessful higher bidder’s systemic complaints
should not easily override expert assessments once construction has
initiated.
- Protection
of Public Interest: The Court expressed concern over the
judicial halt of public infrastructure works. Recognizing the extended
timelines authorized by the department, the Division Bench directed the
appellants to complete the entire contractual construction framework within
the officially extended deadline of June 30, 2026.
Important Clarification
- Supplier
vs. Bidder Compliance Matrix: The judgment establishes
that in public procurement, the statutory tax compliance (such as valid
GSTIN data) of a third-party raw material supplier cannot be weaponized to
disqualify the primary bidder, provided the primary bidder holds valid tax
registrations and the supplier's material rates are commercially
executable.
- Status
of Family Businesses: The Court clarified that multiple
bidders belonging to the same family participating or winning separate
packages within a public tender does not automatically imply collusion or
corporate malpractice, and cannot serve as a baseline for judicial disqualification.
Section Involved
- Article
226 of the Constitution of India: Constitutional provision
governing the scope and limitations of judicial review by High Courts
concerning administrative actions and public tender allocations.
- Clause 2.A.(g) of the Tender Bid Document: The specific regulatory terms mandating detailed justification, rate analysis, and structural proof for bids quoted beyond 15% below the Detailed Schedule Rate (DSR).
Link to download the order - https://mytaxexpert.co.in/uploads/1783060787_327compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment