Facts of the Case
- The
petitioner’s proprietary concern, "M/s. Straight Line Engineering
Works," was awarded a contract by Steel Industries Kerala Ltd
(SILK—Respondent No. 2 & 3) on May 2, 2019.
- The
scope of the contract involved the unloading, leading, erection, welding,
painting, and testing of a 1600-ton Sulfuric Acid Storage Tank within the
premises of Travancore Titanium Products Ltd (TTPL).
- The
stipulated timeline for completing the entire project was three months
from the date of the award.
- The
petitioner claimed that work started promptly but faced delays due to the
non-cooperative and recalcitrant attitude of Respondents 2 and 3 regarding
material supplies and operational support.
- As a
result of these mutual delays, the contract timeline was extended.
However, at the final leg of execution, SILK unilaterally terminated the
contract on January 24, 2020.
- Out
of the total contract value of ₹15,63,050/-, the petitioner received
₹10,24,787/-. The petitioner claimed a balance of ₹5,38,263/- along with
an additional claim of ₹6,30,300/- for alleged extra works executed,
totaling an unpaid demand of ₹11,68,563/-.
- Aggrieved
by the non-payment and termination, the petitioner filed a Writ Petition
under Article 226 seeking a Writ of Mandamus to direct the 1st Respondent
to reconsider his statement and clear the dues.
Issues Involved
- Whether
a Writ Petition under Article 226 of the Constitution of India is
maintainable for adjudication when the underlying dispute arises strictly
from a breach of contract involving deeply contested financial and factual
claims.
- Whether
the actions of the State instrumentalities (SILK) in terminating the
contract and withholding alleged dues were arbitrary, unjust, or violated
public interest so as to bypass the availability of an alternative remedy
in a civil court.
Petitioner’s Arguments
- Performance
and Delay: The petitioner’s team performed the work
efficiently and promptly. The delay in execution was entirely attributable
to the irresponsible and unsupportive behavior of Respondents 2 and 3 in
supplying necessary materials.
- Illegal
Termination: Because the delay was caused by the
respondents, the unilateral termination of the contract on January 24,
2020, was highly illegal, unfair, and high-handed.
- Entitlement
to Dues: The respondents are bound under law to pay
for the quantum of works already executed, including the extra works
established via various email communications.
- Maintainability
of Writ: Relying on Zonal Manager, Central Bank of
India v. Devi Ispat Ltd. and Harbanslal Sahnia v. Indian Oil
Corporation Ltd., the petitioner argued that the rule of alternative
remedy is merely a rule of discretion and not a rule of law. A writ is
maintainable if the State acts unfairly, unjustly, unreasonably, or in
violation of Article 14 of the Constitution.
Respondent’s Arguments
- Preliminary
Objection on Maintainability: The respondents raised a
robust preliminary objection that the dispute is purely contractual in
nature and devoid of any public law element. Hence, it cannot be decided
in a summary proceeding under Article 226. They cited landmark Supreme
Court rulings: KSEB v. Kurien E. Kalathil, State of Bihar v.
Jain Plastics and Chemicals Ltd., and State of Kerala v. M.K. Jose.
- Abandonment
and Laches: On merits, the respondents argued that the
petitioner failed to meet the initial deadline of August 2, 2019, and
abandoned the project mid-way. Despite clear lapses, SILK accommodated the
petitioner by extending the contract period twice (up to October 31, 2019,
and December 12, 2019).
- Financial
Counter-Claims: Due to the petitioner's systematic breach,
the relationship between SILK and the principal company (TTPL) turned
sour. TTPL recovered Liquidation Damages (LD) worth ₹6,11,283/- from SILK.
SILK had to step in, complete the remaining work independently by February
15, 2020, and hand it over to TTPL.
- Dues
from Petitioner: According to SILK’s books, the total
payments made plus damages and incomplete work values calculated to
₹22,04,337/- against a gross contract value of ₹18,44,399/- (inclusive of
GST). Thus, instead of paying the petitioner, an amount of ₹3,59,938/- is
actually recoverable from the petitioner.
Court Orders & Findings
- Nature
of Dispute: The Hon'ble High Court observed that the
matter showcases an intense factual dispute regarding who committed the
breach of contract and what exact monetary quantum is payable or
recoverable.
- Settled
Legal Position: The Court reaffirmed the settled principle
of law that for disputes arising entirely out of an agreement executed
between parties, the proper legal remedy is to approach a competent Civil
Court or a contractually designated forum, rather than filing a writ
petition.
- Application
of Precedent: The Court heavily relied on the Supreme
Court judgment in State of Bihar v. Jain Plastics and Chemicals Ltd.,
noting that seriously disputed questions or rival claims concerning
contractual breaches must be investigated and determined based on oral and
documentary evidence led in a properly instituted civil suit.
- Absence
of Public Law Element: The Court rejected the petitioner's
argument to bypass the alternative remedy, stating that a writ could only
be entertained if the State's action was patently against public good,
public interest, discriminatory, or in blatant violation of natural justice.
In this case, no such material or exceptional grounds were established.
- Final
Decision: Finding no merit under the extraordinary
jurisdiction of Article 226, the High Court dismissed the writ petition,
relegating the petitioner to seek remedies before a competent Civil Court.
Important Clarification
- Writ
vs. Civil Suit in Contracts: The ruling clarifies that a
simple allegation of an unfair contract termination or non-payment by a
State body does not automatically open the doors to Article 226. Unless an
element of public law interest or egregious violation of natural justice
is clearly demonstrated, complex calculations of contractual accounts,
damages, and claims for extra work must strictly be litigated through a
traditional civil suit where evidence can be properly tested.
Section Involved
- Article
226 of the Constitution of India: Constitutional provision
invoked by the petitioner seeking an extraordinary remedy through a Writ
of Mandamus against State instrumentalities in a contractual dispute.
- Article 14 of the Constitution of India: Pleaded by the petitioner to argue against arbitrary, unjust, and unfair actions by a State instrumentality within a contract.
Link to download the order - https://mytaxexpert.co.in/uploads/1783148755_578compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content.The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment