Facts of the Case
D.B.S. Constructions Pvt. Ltd., a registered contractor,
claimed to have carried out maintenance work under the “Operation and Minor
Maintenance Work of Shirkhinda SHP (2 × 350 KW)” pursuant to an agreement dated
21 August 2012 entered into between the Chief Engineer, Bihar State
Hydroelectric Power Corporation Ltd. and the petitioner.
The petitioner approached the Patna High Court seeking refund
of ₹8,50,800, allegedly deducted beyond and contrary to the terms of the
agreement from three bills, namely:
- Bill
No. 19 dated 31 May 2016;
- Bill
No. 23 dated 7 October 2021; and
- Bill
No. 25 dated 7 October 2021.
The petitioner further sought refund of ₹11,05,232,
allegedly deducted from its Running Account Bills during the period from 5
May 2014 to 5 October 2018 under the heads of EPF and VAT/GST,
pursuant to closure of the agreement by the respondent authorities.
The petitioner also sought release of the amount allegedly due
under the 27th Final Bill in connection with the operation and
maintenance work of the Srikhinda State Hydel Project.
According to the petitioner, despite representations dated 28
October 2021 and 9 June 2022, including its calculated claim of
₹11,05,232, the amount was not released. The Court recorded that there was no
response to the petitioner’s request, the dispute continued to survive, and the
request for clearance of dues remained pending.
Issues Involved
- Whether
the petitioner’s claim for refund of ₹8,50,800, allegedly deducted
beyond and contrary to the agreement from the specified bills, required
consideration and decision by the competent authority.
- Whether
the petitioner’s claim for refund of ₹11,05,232, allegedly deducted
from Running Account Bills under the heads of EPF and VAT/GST,
required adjudication by the competent authority.
- Whether
the amount claimed under the 27th Final Bill for operation and
maintenance work was liable to be released.
- Whether
the respondent authorities could leave the petitioner’s representations
unanswered and the monetary claims pending without timely consideration.
- Whether
the dispute could and should be addressed through the mechanism
contemplated under the Bihar State Litigation Policy, 2011.
- Whether
recourse to Section 89 of the Code of Civil Procedure, 1908 and
appropriate dispute-resolution mechanisms could reduce avoidable and
prolonged litigation.
- Whether
the State authorities were required to establish an effective grievance
redressal mechanism on a digital platform for consideration of such
claims.
Petitioner’s Arguments
The petitioner submitted that it was a registered contractor
and had carried out maintenance work under the operation and minor maintenance
arrangement for the Shirkhinda SHP (2 × 350 KW) pursuant to the agreement dated
21 August 2012.
It contended that an amount of ₹8,50,800 had been
deducted beyond and contrary to the terms of the agreement from Bill No. 19
dated 31 May 2016, Bill No. 23 dated 7 October 2021 and Bill No. 25 dated 7
October 2021 and therefore sought refund of the said amount.
The petitioner further claimed refund of ₹11,05,232
deducted from its Running Account Bills between 5 May 2014 and 5 October 2018
under the heads of EPF and VAT/GST.
It also sought release of the amount allegedly due under the 27th
Final Bill relating to the operation and maintenance work of the State
Hydel Project.
The petitioner relied upon its representations dated 28
October 2021 and 9 June 2022 and asserted that its claims had not been
resolved.
Learned counsel for the petitioner specifically prayed that
the writ petition be disposed of in the same terms as the judgment dated 14
September 2022 passed in M/s. Raghoji House of Distribution vs The State
of Bihar & Ors., CWJC No. 13024 of 2022.
Respondent’s Arguments
The respondents raised no objection to the petitioner’s
prayer that the writ petition be disposed of in the same terms as the judgment
in M/s. Raghoji House of Distribution vs The State of Bihar & Ors.
The Court therefore proceeded on the mutually agreed basis
that the directions contained in the said judgment would govern the present
matter mutatis mutandis, to the extent possible.
Court Order / Findings
The Patna High Court observed that the petitioner’s dispute
remained alive and its request for clearance of dues continued to remain
pending. The Court further recorded that there was no response to the
petitioner’s request.
Without entering into the merits of the monetary claims, the
Court held that the dispute could have been resolved in terms of the Bihar
State Litigation Policy, 2011.
The Court referred to its earlier decision in M/s. Raghoji
House of Distribution vs The State of Bihar & Ors., where it had
observed that even in cases governed by contractual or statutory
dispute-resolution mechanisms, parties are often forced to litigate endlessly
before different legal forums and statutory tribunals.
The Court questioned why the State was not taking recourse to
its own Bihar State Litigation Policy, 2011 and why it was not resorting
to Section 89 of the Code of Civil Procedure, 1908.
The Court disposed of the present writ petition in terms of
the judgment in M/s. Raghoji House of Distribution vs The State of Bihar
& Ors., directing that the directions contained therein would govern
the present case mutatis mutandis, to the extent possible.
Specifically, the Court issued the following directions:
- The Managing
Director, Bihar State Hydroelectric Power Corporation, Government of Bihar,
was directed to examine the petitioner’s case and ensure an early decision
and disbursement of the petitioner’s legitimate dues payable, if any,
under the work order, along with consideration of all claims.
- The
entire exercise was directed to be completed positively within two
months from the date of the judgment.
- In
case of failure to comply within the stipulated period, costs of ₹5,000
were directed to be paid to the petitioner and recovered from the personal
salary of the officer concerned.
- The Principal
Secretary, Department of Energy-cum-Chairman, Bihar State Hydroelectric
Power Corporation, Government of Bihar, was directed to establish an
effective mechanism for grievance redressal.
- The
grievance redressal mechanism was specifically required to be made
available on a digital platform, and the general public was
required to be informed about its availability and functioning.
- Failure
to comply could result in initiation of proceedings for deliberate
violation of the Court’s order and consequential action involving stoppage
of salary of the concerned officer.
- The
Principal Secretary was directed to file an affidavit of compliance
within three months from the date of judgment. In case of failure, the
Registry was directed to place the file on the judicial side.
The writ petition and pending interlocutory application(s), if
any, were accordingly disposed of.
Important Clarification
The Patna High Court did not adjudicate the petitioner’s
monetary claims on merits.
The Court expressly left all issues on merits, facts and
law open for determination by the competent decision-making authority.
The competent authority was required to decide the matter in
compliance with all principles of natural justice.
The direction for early decision and disbursement was confined
to the petitioner’s legitimate dues payable, if any, under the work
order and consideration of all claims. Therefore, the judgment should not be
interpreted as a final determination that ₹8,50,800, ₹11,05,232 or the amount
under the 27th Final Bill was conclusively payable to the petitioner.
The parties were also granted liberty to initiate fresh proceedings should the need arise.
Sections / Legal Provisions Involved
- Section
89 of the Code of Civil Procedure, 1908 – Relating to
settlement of disputes outside the Court through alternative
dispute-resolution mechanisms.
- Article
39-A of the Constitution of India – Referred to in the
related precedent in connection with equal justice and the State’s
Litigation Policy.
- Bihar
State Litigation Policy, 2011 – Clause 1.1(b) –
Concept of the State as a responsible litigant and the principle that
litigation should not be resorted to merely for the sake of litigating.
- Bihar
State Litigation Policy, 2011 – Clause 1.2 –
Recognition of the Government’s responsibility to protect citizens’ rights
and respect fundamental rights.
- Bihar
State Litigation Policy, 2011 – Clause 1.3 –
Objective of reducing pressure on the overloaded judiciary and expediting
dispensation of justice.
- Bihar
State Litigation Policy, 2011 – Clause 4.A –
Setting up an effective grievance redressal system to prevent and control
avoidable litigation.
- Bihar
State Litigation Policy, 2011 – Clause 4.A(1) to 4.A(5) –
Grievance Redressal Committees, time-bound decision-making and review of
genuine grievances.
- Bihar
State Litigation Policy, 2011 – Clause 4.B and 4.B(1) –
Quick action on representations and legal notices and expeditious
decisions through detailed speaking orders.
- Principles
of Natural Justice – Expressly required by the Court to
govern the competent authority’s decision on merits, facts and law.
Link to Download the Order https://mytaxexpert.co.in/uploads/1783317252_1051compressed.pdf
Disclaimer
This content is shared strictly for general information and
knowledge purposes only. Readers should independently verify the information
from reliable sources. It is not intended to provide legal, professional, or
advisory guidance. The author and the organisation disclaim all liability
arising from the use of this content. The material has been prepared with the
assistance of AI tools.
0 Comments
Leave a Comment