Facts of the Case
The petitioner was awarded a contract for execution
of work under the “Neeru-Chettu” Programme for removal of weed growth in
the Amalapuram Main Canal from Nadipudi Lock to Chintalapudi Lock in D.C.,
Amalapuram, East Godavari District, under Agreement No. 93/2018-19 dated
26.07.2018.
After completion of the work, a final bill
amounting to Rs. 1,87,276/- plus 9% GST was prepared and submitted to
the concerned authorities for payment. However, the respondents did not release
the payment. Consequently, the petitioner approached the High Court by filing
the writ petition seeking judicial intervention against the continued
non-payment of the contractual dues.
Issues
Involved
The principal issues arising for consideration
were:
- Whether the continued non-payment of contractual dues, despite the
petitioner’s asserted entitlement to payment, was arbitrary and warranted
interference by the High Court.
- Whether the respondents could indefinitely defer payment on the
ground that verification of the petitioner’s claim was still in progress.
- What time-bound directions should be issued for completion of
verification and payment of the amount found due.
- Whether the petitioner could separately pursue a claim for interest
on delayed payment before an appropriate forum.
Petitioner’s
Arguments
The petitioner contended that the respondents had
admitted the petitioner’s entitlement to the amounts in question, yet payment
was not being made.
It was argued that such withholding and non-payment
of money was arbitrary and high-handed, thereby requiring interference
by the High Court. The petitioner’s grievance was founded on the fact that the
contracted work had already been executed and the final bill had been prepared
and submitted, but the payment remained outstanding.
Respondents’
Arguments
The learned Government Pleader submitted that the
respondent authorities were in the process of verifying the petitioner’s
claims.
According to the respondents, payment could be made
only after completion of such verification. Thus, the respondents sought to
justify the delay on the ground that the verification process had not yet
concluded.
Court Order
/ Findings
The High Court referred to its earlier orders,
including the judgment of a learned Single Judge dated 05.10.2021 in W.P.
No. 10038 of 2021 and batch, wherein the Court had taken the view that such
non-payment of dues was arbitrary and that the dues were required to be cleared
by the respondents at the earliest.
After considering the submissions of the
petitioner’s counsel and the learned Government Pleader for Irrigation, the
Court disposed of the writ petition with the following directions:
- The respondents were directed to complete the verification
process within three weeks from the date of receipt of a copy of the
order.
- Thereafter, the respondents were directed to pay the amount due
to the petitioner, depending upon the outcome of verification, within six
weeks.
- If the verification process was not completed within the
stipulated three-week period, the respondents were required to pay
the amount due to the petitioner without insisting upon any further time
for verification.
- The petitioner was granted liberty to agitate the claim for interest,
if any payable by the respondents, before an appropriate forum.
- There was no order as to costs.
- Pending miscellaneous petitions, if any, were ordered to stand
closed.
Important
Clarification
The most significant clarification issued by the
Court was that the respondents could not use an incomplete verification process
as a basis for indefinite delay. If verification was not completed within the
prescribed period of three weeks, the respondents were directed to pay
the amount due without insisting upon any further time for verification.
The Court further clarified that the order did not
finally determine any claim for interest. The petitioner remained free to
pursue such a claim, if otherwise payable, before an appropriate forum.
Legal
Principle Emerging from the Case
The order reinforces the principle that State authorities
should not indefinitely withhold legitimate contractual dues after execution of
work merely by keeping the verification process pending. Where claims require
verification, such verification must be completed within a reasonable and
judicially fixed timeframe. Failure to complete verification within that period
cannot become a continuing justification for withholding payment.
The Court’s reliance on the judgment dated 05.10.2021 in W.P. No. 10038 of 2021 and batch further supports the proposition that arbitrary non-payment of dues by public authorities warrants judicial intervention and that outstanding dues should be cleared at the earliest.
Link to
download the order - https://www.mytaxexpert.co.in/uploads/1783318651_1252compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment