Facts of the Case
The dispute arose from a tender invited through
notice dated 22.04.2022 for construction of an R.C.C. minor bridge, approach
and protection work at Shahbad, Rampur–Bazpur Road (SH-144), Km. 75, District
Rampur. The estimated cost of the work was ₹540 lakh, excluding GST.
Two technical bids were admitted: one submitted by
the petitioners and the other by M/s A.M. Builders. On 25.09.2022, the
petitioners’ financial bid was opened and found to be the lowest. The
petitioners had quoted a rate 2.50% above the departmental estimate,
whereas the other bidder had quoted 8.94% above the estimate.
On 26.09.2022, the petitioners received a
communication from the office of the fourth respondent requiring them to
intimate, by 30.09.2022, how much they could reduce their quoted price. In
response, by communication dated 27.09.2022, the petitioners reduced their bid
from 2.50% above the departmental estimate to 2% above the departmental
estimate.
According to the petitioners, the website upload
reflected that their bid had been declared successful. However, on 29.09.2022,
they received a communication dated 26.09.2022 stating that the tender
proceedings had been scrapped because the bids were at rates higher than the
departmental estimates.
The petitioners challenged the communication/order
dated 26.09.2022 and sought quashing of the same, along with acceptance of
their lowest bid for the concerned work project.
Issues
Involved
The principal issues before the Court were whether
the tendering authority could scrap the tender process even though the
petitioners’ financial bid was the lowest; whether cancellation of the tender
process was arbitrary when, on the same date, the petitioners had been granted
time up to 30.09.2022 to submit a revised lower rate; whether being the lowest
bidder created an enforceable right in favour of the petitioners to obtain
acceptance of their bid; and whether the High Court, in exercise of writ
jurisdiction under Article 226, could compel the department to accept the
petitioners’ bid merely because it was the lowest.
Petitioners’
Arguments
The petitioners contended that there was no
justification for passing the order dated 26.09.2022 scrapping the tender
proceedings when, through another communication of the same date, they had been
granted an opportunity to submit a revised lower rate by 30.09.2022.
It was argued that the procedure adopted by the
respondents was arbitrary on the face of the record because the tender process
had allegedly been scrapped even before expiry of the period granted for
submission of a revised proposal.
The petitioners further contended that the order
dated 26.09.2022 reflected non-application of mind to the contemporaneous
communication inviting them to reduce their bid. They relied upon the fact that
their financial bid was the lowest and that they had further reduced it from
2.50% above the departmental estimate to 2% above the estimate.
Respondents’
Arguments
The judgment does not record a detailed separate
set of submissions on behalf of the respondents. However, the position emerging
from the impugned communication and the record was that the tender proceedings
had been scrapped because the bids were higher than the departmental estimates.
The Court also noted that there was no document on
record demonstrating that the petitioners’ lowest bid had actually been
accepted by the department. Thus, although the petitioners’ technical bid was
responsive and their financial bid was the lowest, the bid remained above the
departmental estimate.
Court Order
/ Findings
The Allahabad High Court declined to entertain the
writ petition and dismissed it.
The Court recorded the following material findings:
- No document established acceptance of the petitioners’ bid. The Court found nothing on record to suggest that the petitioners’
bid had been accepted merely because it was the lowest.
- Lowest bid remained above the departmental estimate. Although the petitioners’ technical bid was responsive and their
financial bid was the lowest, it was 2.50% above the departmental
estimate. Even after revision, according to the petitioners’ own case, the
bid remained 2% above the departmental estimate.
- The department cannot be forced to accept the lowest tender. The Court expressly held that it is well settled that the
department cannot be compelled to accept a tender merely because it is the
lowest.
- Premature scrapping argument did not justify compelling acceptance. The Court observed that the argument concerning scrapping of the
tender process before the date fixed for receipt of the revised proposal
might appear attractive. However, the decisive consideration was that even
the revised bid remained above the departmental estimate.
- Writ jurisdiction cannot be used to compel award of the tender
merely on L-1 status. The Court held that it
could not, by issuance of a writ, force the department to accept the
petitioners’ bid merely because it was the lowest.
Accordingly, the writ petition was dismissed without
prejudice to the petitioners’ right to participate in the fresh tender process
as and when floated.
Important
Clarification
The judgment makes an important distinction between
being the lowest bidder (L-1) and having an accepted bid. A
bidder does not acquire an enforceable right to award of a government contract
merely because its bid is the lowest.
Further, where the lowest bid itself exceeds the
departmental estimate, the tendering authority cannot be compelled through writ
proceedings to accept such bid. Even a technically responsive bid and L-1
status do not, by themselves, establish acceptance of the tender or create an
absolute right to the contract.
The Court’s order also clarifies that dismissal of
the writ petition did not bar the petitioners from participating in any fresh
tender process subsequently floated for the work.
Section /
Constitutional Provision Involved
Article 226 of the Constitution of India – The petition invoked the writ jurisdiction of the High Court to
challenge the communication/order scrapping the tender process and to seek
acceptance of the petitioners’ lowest bid.
The case concerns judicial review in public tender matters, particularly the limits of writ jurisdiction where a bidder seeks to compel a government department to accept an L-1 bid that remains above the departmental estimate.
Link to download the order -
https://www.mytaxexpert.co.in/uploads/1783318920_1253compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment