Facts of the Case
Mukut House Developers Private
Limited, the petitioner, entered into a Collaboration Agreement dated 7
September 2011 with the respondents. Under the Agreement, the respondents were
required, inter alia, to place at the petitioner’s disposal the project land comprising
Building No. 3 bearing Corporation No. 362/XII-min., together with the
underlying land measuring 6,675 square yards bearing Khasra Nos. 1312 and 1315,
situated at The Mall, Amritsar, Punjab, for construction and development of a
commercial complex consisting of a shopping mall and two basements.
The petitioner’s principal
obligations included payment of amounts and refundable sums/deposits as
consideration for development and construction of the complex. According to the
petitioner, it paid a total amount of ₹10.25 crore under the Agreement,
comprising ₹6.75 crore as an interest-free refundable deposit to the
respondents and ₹3.50 crore directly to Parsvnath towards execution of the Sale
Deed/Conveyance Deed for the petitioner’s undivided share in the project land.
The petitioner stated that the
refundable deposit of ₹6.75 crore and direct payments of ₹3.50 crore were to be
refunded by the respondents at the time of handing over possession of the
respondents’ share in the built-up spaces of the complex. Clauses 7.5 and 7.6
of the Agreement allegedly provided remedies and modes for recovery of damages
if the respondents failed or were unable to refund the gross amount of ₹10.25
crore along with other expenses. The petitioner also asserted a right of lien
over the exclusive area reserved for the respondents and rights to recover
outstanding payments by selling reserved units or leasing the respondents’
areas and receiving rentals.
By notice dated 18 July 2018, the
petitioner informed the respondents that it had applied for an Occupation
Certificate and called upon them to pay the amounts due under the Agreement.
The petitioner subsequently received the Occupation Certificate on 7 May 2019
and communicated this fact through a letter dated 31 July 2019, again demanding
clearance of the outstanding amount with interest at 14% per annum from 20
December 2018.
According to the petitioner, the
respondents began making some payments only after October 2019 but failed to
clear the entire outstanding amount. The petitioner claimed that an aggregate
amount of ₹4,98,20,250 remained outstanding at that stage. By letter dated 7
July 2020, the petitioner demanded specified dues, including refundable deposit
amounts, interest at 14% per annum, and outstanding marketing costs.
Thereafter, by legal notice dated
4 November 2020, the petitioner called upon the respondents to pay ₹8,97,03,475
along with interest at 14% per annum. Upon alleged failure to clear the dues,
disputes arose between the parties. The petitioner invoked Clause 19 of the
Agreement by an Arbitration Notice dated 11 December 2020 and proposed names of
former judges for appointment as Sole Arbitrator. As no mutually agreed
appointment followed, the petitioner approached the Delhi High Court under
Section 11(5) of the Arbitration and Conciliation Act, 1996.
Issues
Involved
The principal issues before the
Delhi High Court were:
Whether a Sole Arbitrator should
be appointed under Section 11(5) of the Arbitration and Conciliation Act, 1996
where the parties had admittedly executed a Collaboration Agreement containing
an arbitration clause and the respondents had not agreed to the proposed
appointment.
Whether the petition for
appointment of an arbitrator was maintainable when the respondents contended
that the Collaboration Agreement containing the arbitration clause was not duly
stamped.
Whether, in view of Sections 35
and 38 of the Indian Stamp Act, 1899, the Court was required first to impound
the Agreement and ensure payment of stamp duty and penalty before acting upon
the arbitration clause.
Whether the pending Larger Bench
consideration of the legal position concerning unstamped agreements required
the Section 11 proceedings to remain stalled.
Whether the approach adopted by
the Supreme Court in Intercontinental Hotels Group (India) Pvt. Ltd. &
Ors. vs Waterline Hotels Pvt. Ltd. justified allowing arbitration to
proceed at the pre-appointment stage unless the dispute was patently
“deadwood”.
Whether respondent No. 2 could be
taken on record as the legal heir representing the estate of deceased
respondent No. 1.
Petitioner’s
Arguments
The petitioner contended that the
Collaboration Agreement contained a valid and express arbitration clause in
Clause 19.1. The clause provided that disputes arising between the parties
concerning the Agreement, interpretation of its terms, performance or execution
were to be settled by arbitration under the Arbitration and Conciliation Act,
1996.
The petitioner submitted that
disputes had crystallised due to the respondents’ alleged failure to clear
outstanding payments. It had issued communications dated 31 July 2019, a legal
notice dated 4 November 2020 and an arbitration invocation notice dated 11
December 2020.
It was argued that, despite
service of the arbitration notice and proposal of names of retired judges for
appointment as Sole Arbitrator, the respondents did not respond and no mutual
appointment could be achieved. Consequently, Court intervention under Section
11(5) was warranted.
On the stamping objection, the
petitioner relied upon the Supreme Court decision in Intercontinental Hotels
Group (India) Pvt. Ltd. & Ors. vs Waterline Hotels Pvt. Ltd.,
contending that although the broader jurisprudential issue had been referred
for Larger Bench consideration, pre-appointment arbitration matters should not
remain indefinitely pending and arbitration should proceed unless the matter
patently represented “deadwood”.
The petitioner therefore urged
the Court to move the arbitral process forward and appoint a neutral Sole
Arbitrator.
Respondents’
Arguments
The respondents challenged the
maintainability of the petition primarily on the ground that the Collaboration
Agreement containing the arbitration clause was not duly stamped.
Relying on Section 35 of the
Indian Stamp Act, 1899, the respondents argued that an instrument not duly
stamped was inadmissible in evidence and could not be acted upon unless the
stamp defect was cured. They further contended that the document was required
to be impounded and dealt with under Section 38 of the Indian Stamp Act, 1899.
The respondents relied upon the
following case law:
SMS Tea
Estates Private Limited vs Chandmari Tea Company Private Limited, (2011) 14 SCC
66 – relied upon to support the proposition concerning
the legal consequences of an unstamped instrument containing an arbitration
clause.
Garware Wall
Ropes Ltd. vs Coastal Marine Constructions and Engineering Limited, (2019) 9
SCC 209 – relied upon for the contention
that where a Court dealing with an application under Sections 11(4) to 11(6)
encounters an unstamped arbitration agreement or conveyance, it must first
impound the instrument and ensure payment of stamp duty and penalty before the
agreement can be acted upon.
N.N. Global
Mercantile Private Limited vs Indo Unique Flame Limited & Ors., (2021) 4
SCC 379 – discussed in relation to the
proposition that non-payment of stamp duty on the commercial contract should
not invalidate the arbitration agreement or render it non-existent and
unenforceable, while noting that the issue had been referred for consideration
by a Larger Bench.
Vidya Drolia
& Ors. vs Durga Trading Corporation, (2021) 2 SCC 1 – relied upon in the broader jurisprudential
discussion concerning the effect of stamping objections and the legal position
then holding the field.
State of
Maharashtra & Anr. vs Sarva Shramik Sangh, Sangli & Ors., (2013) 16 SCC
16 – relied upon to argue that mere reference of an
issue to a Larger Bench does not, by itself, render the existing precedent
non-binding until the reference is answered.
Accordingly, the respondents
urged that the petition should be dismissed and that the Court should not
appoint an arbitrator on the basis of the allegedly insufficiently stamped
Agreement.
Court Order
/ Findings
The Delhi High Court noted that
there was no dispute regarding execution of the Collaboration Agreement dated 7
September 2011 between the petitioner and the respondents.
The Court further recorded that
the Agreement contained Clause 19, an arbitration clause, under which disputes
relating to the Agreement, interpretation of its terms, performance or
execution were to be referred to arbitration. The clause contemplated
appointment of a Sole Arbitrator mutually by the parties and, failing mutual
agreement, appointment by the Court in accordance with the Arbitration and
Conciliation Act, 1996. New Delhi was stipulated as the venue of arbitration.
The Court noted the petitioner’s
case that communications and notices had been issued demanding payment and that
the arbitration clause had been invoked through notice dated 11 December 2020.
The petitioner had also proposed names of three retired judges, but no response
was received from the respondents.
The Court particularly relied
upon the Supreme Court’s approach in Intercontinental Hotels Group (India)
Pvt. Ltd. & Ors. vs Waterline Hotels Pvt. Ltd. and held that the
arbitration process needed to be taken forward as an alternate dispute
resolution mechanism under Clause 19 of the Agreement.
Accordingly, the Court allowed
the petition and appointed Justice Badar Durrez Ahmed, former Chief Justice
of the Jammu & Kashmir High Court, as the Sole Arbitrator to adjudicate
the disputes between the parties through claims and counterclaims, if any.
The Court directed that the
Arbitrator’s fee would be regulated in terms of the Fourth Schedule to the
Arbitration and Conciliation Act, 1996 and that the Arbitrator would furnish disclosure
under Section 12 of the Act.
The petition was accordingly
disposed of.
Important
Clarification
The judgment is significant
because the Delhi High Court did not permit the stamping objection to
indefinitely halt the arbitral process at the pre-appointment stage. Applying
the then-relevant Supreme Court approach in Intercontinental Hotels Group
(India) Pvt. Ltd. & Ors. vs Waterline Hotels Pvt. Ltd., the Court
proceeded with appointment of the arbitrator while the larger jurisprudential
issue concerning the interplay between arbitration proceedings and unstamped
agreements awaited authoritative settlement.
The Court’s reasoning was rooted
in the need to ensure that arbitration matters at the pre-appointment stage
were not left hanging merely because a related legal issue was pending before a
Larger Bench, particularly where the dispute did not patently indicate
“deadwood”.
A further procedural
clarification concerns I.A. 12501/2021. Respondent No. 1 had died on 31
December 2020. The petitioner sought impleadment of respondent No. 2, Harpratap
Singh, as the legal heir of the deceased respondent No. 1. The Court allowed
the application and directed that the deceased respondent No. 1 be represented
through respondent No. 2, with an amended memo of parties to be filed within
ten days.
Sections and
Legal Provisions Involved
Section
11(5), Arbitration and Conciliation Act, 1996 – Appointment of arbitrator where parties fail to agree on the
arbitrator in an arbitration with a sole arbitrator.
Sections
11(4) to 11(6), Arbitration and Conciliation Act, 1996 – Statutory framework governing Court intervention
in appointment of arbitrators in specified circumstances.
Section 12,
Arbitration and Conciliation Act, 1996 –
Disclosure obligations concerning independence and impartiality of the
arbitrator.
Section 16,
Arbitration and Conciliation Act, 1996 –
Competence of the arbitral tribunal to rule on its own jurisdiction.
Fourth
Schedule, Arbitration and Conciliation Act, 1996 – Relevant framework for regulation of arbitral
fees.
Section 35,
Indian Stamp Act, 1899 –
Inadmissibility of instruments not duly stamped, subject to statutory
conditions.
Section 38,
Indian Stamp Act, 1899 – Procedure
concerning instruments impounded under the Stamp Act.
Order I Rule
10, Code of Civil Procedure, 1908 – Addition,
deletion and substitution of parties.
Order XXII
Rule 4, Code of Civil Procedure, 1908 – Procedure
concerning legal representatives upon death of a defendant/respondent.
Clause 19 of the Collaboration Agreement – Arbitration clause providing for reference of disputes to a Sole Arbitrator and stipulating New Delhi as the venue of
Link to download the order -https://www.mytaxexpert.co.in/uploads/1783321248_1258compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment