Facts of the Case
L&T Hydrocarbon Engineering Limited, a wholly
owned subsidiary of Larsen & Toubro Limited, approached the Delhi High
Court under Sections 11(5), 11(6) and 11(8) of the Arbitration and Conciliation
Act, 1996 seeking appointment of an independent and impartial sole arbitrator
for adjudication of disputes with Indian Oil Corporation Limited (“IOCL”). The
petition arose from a contract concerning the Salaya Mathura Pipeline
De-bottlenecking Pipeline Project.
IOCL had issued a Letter of Award dated 11 June
2012 for mainline works, including small HDD works, civil works, mechanical
works, TCP and electrical works, OFC laying works and instrumentation works. A
formal contract was executed on 11 July 2012. The contract price was initially
fixed at approximately ₹104.5 crore and was subsequently reduced to
approximately ₹103.62 crore.
The work involved laying pipelines over substantial
stretches in Rajasthan and Haryana. The scheduled completion date was 10
September 2013; however, according to the petitioner, the works were delayed
for reasons not attributable to it and were ultimately completed on 24 February
2016. The petitioner submitted its revised final bill on 25 April 2018 and
claimed that approximately ₹72.58 crore, excluding GST, remained due and
payable by IOCL.
The petitioner had also furnished a performance
bank guarantee of approximately ₹10.45 crore. Following a dispute concerning
its possible invocation, proceedings under Section 9 of the Arbitration and
Conciliation Act, 1996 were initiated, in which directions were issued
concerning extension of the bank guarantee, invocation of the contractual
dispute-resolution mechanism, and prior notice before any proposed invocation
or encashment.
The GCC contained a structured arbitration
mechanism. Clause 9.0.1.0 provided for arbitration of disputes arising from a
contractor’s Notified Claims included in the Final Bill, subject to the
contractual conditions. Clause 9.0.1.1 contemplated selection of a sole
arbitrator by the contractor from a panel of three persons nominated by the
owner. Clause 9.0.2.0 treated specified questions—including whether a claim was
a Notified Claim and whether a Notified Claim was included in the Final Bill—as
excluded matters to be decided by the General Manager before the arbitrator proceeded.
On 20 April 2019, the petitioner invoked
arbitration in respect of claims of approximately ₹72.58 crore and stated that
it did not wish to opt for the alternative dispute-resolution machinery under
the GCC. The petitioner also questioned the General Manager’s authority to
conclusively decide matters under Clause 9.0.2.0, but nevertheless called upon
IOCL to refer the relevant questions to the General Manager and stipulated two
weeks for a decision.
After no decision was received within that period,
the petitioner, by communication dated 8 May 2019, challenged the validity of
the contractual procedure requiring selection of the sole arbitrator from a
three-member panel nominated by IOCL and suggested two retired judges for
appointment. IOCL did not accept those names and instead forwarded a panel of
three persons from which the petitioner was asked to select the sole
arbitrator.
Issues
Involved
The Delhi High Court identified two principal
issues for consideration: first, the legal effect of the contractual
requirement that claims must be notified and the role of the General Manager
under Clause 9.0.2.0; and second, the validity of the procedure requiring the
petitioner to select a sole arbitrator from a restrictive panel of three names
forwarded by IOCL.
More specifically, the questions were whether
claims not declared or treated as Notified Claims could be referred to
arbitration; whether IOCL’s failure for more than three years to refer the
claims to the General Manager amounted to waiver or a subsequent agreement
permitting the arbitrator to determine the issue; whether the arbitrator could
decide the status of the claims under Section 16 of the 1996 Act; and whether a
three-name panel nominated at the discretion of one contracting party satisfied
the standards of independence, impartiality and meaningful choice under
arbitration law.
Petitioner’s
Arguments
The petitioner argued that the General Manager
could not conclusively determine questions affecting arbitral jurisdiction and
that such questions should properly be decided by the arbitrator. It submitted
that, notwithstanding this position, it had expressly called upon IOCL on 20
April 2019 to refer the claims to the General Manager under Clause 9.0.2.0.
The petitioner contended that IOCL’s failure to
make such a reference for more than three years amounted to waiver of the
contractual precondition. It argued that IOCL could not take advantage of its
own omission and subsequently contend that the claims were non-arbitrable
because the General Manager had not notified them. It further relied on Section
46 of the Indian Contract Act, 1872 to submit that, where no time was
prescribed, the relevant act was required to be performed within a reasonable
time.
It was further argued that IOCL’s conduct demonstrated
waiver or a subsequent understanding because IOCL had itself responded to the
arbitration invocation by forwarding a panel of three proposed arbitrators
instead of insisting at that stage that the claims first be determined by the
General Manager. The petitioner also submitted that an arbitral tribunal could
determine its jurisdiction under Section 16 of the Arbitration and Conciliation
Act, 1996.
On appointment procedure, the petitioner challenged
Clause 9.0.1.1 insofar as it restricted its choice to only three persons
nominated by IOCL. It relied principally on Voestalpine Schienen GmbH vs
Delhi Metro Rail Corporation Limited, TRF Ltd. vs Energo Engineering
Projects Ltd. and Perkins Eastman Architects DPC vs HSCC (India) Ltd.
to argue that one interested party should not control the constitution of the
tribunal and that any panel-based procedure must provide a broad, diverse and
meaningful choice.
The petitioner further argued that Central
Organisation for Railway Electrification vs ECI-SPIC-SMO-MCML (JV) should
not govern the case because its correctness had been doubted in Union of
India vs Tantia Constructions Ltd. and because earlier authorities such as TRF,
Perkins Eastman and Voestalpine supported independence and
neutrality in the appointment process.
Respondent’s
Arguments
IOCL contended that the petitioner could not seek,
in proceedings under Section 11, to invalidate or rewrite the agreed
contractual arbitration mechanism. According to IOCL, only a contractor’s
Notified Claims included in the Final Bill in accordance with the GCC could be
referred to arbitration.
IOCL argued that Clause 9.0.1.1 expressly required
the contractor to select the sole arbitrator from a panel of three persons
nominated by the owner. If the contractor failed to select within thirty days,
the owner could select the sole arbitrator from that panel. According to IOCL,
this was a mutually agreed procedure and had to be respected.
The respondent further submitted that the
petitioner’s letter dated 20 April 2019 improperly imposed a unilateral
two-week deadline upon the General Manager, although the GCC prescribed no such
period. It also argued that the petitioner had not properly asserted that its
claims were Notified Claims under Clause 6.6.1.0 and included in the Final Bill
under Clause 6.6.3.0; therefore, there was no occasion for the General Manager
to decide the issue under Clause 9.0.2.0.
IOCL maintained that the three-member panel
procedure was valid and did not contravene Sections 12(1) or 12(5), or the
Fourth and Seventh Schedules to the Arbitration and Conciliation Act, 1996. It
relied upon authorities including IOT Infrastructure & Energy Services
Ltd. vs Indian Oil Corporation Ltd., Institute of Geoinformatics (P)
Ltd. vs Indian Oil Corporation Ltd., Srico Projects Pvt. Ltd. vs Indian
Oil Foundation, Union of India vs Parmar Construction and Kadimi
International Pvt. Ltd. vs Emaar MGF Land Ltd.
The respondent also relied on USAE Equipment vs
Krishna Shankar Tripathi, Bhayana Builders Pvt. Ltd. vs Oriental Structural
Pvt. Ltd., Sriram Electrical Works vs Power Grid Corporation of India
and Kadimi International Pvt. Ltd. vs Emaar MGF Land Ltd. to support the
proposition that contractual appointment procedures could remain valid where
the proposed arbitrators were not ineligible under Section 12(5) and the
Seventh Schedule.
Court Order
/ Findings
The Delhi High Court delivered a two-part ruling.
First, on Notified Claims and arbitrability, the Court followed the Supreme Court’s decision in Indian Oil
Corporation Limited vs NCC Limited. It held that the contractual language
was clear: only claims notified by the General Manager were arbitrable, while
claims not so notified constituted excepted matters and could not be referred
to arbitration. The arbitrator acquired jurisdiction only in respect of claims
satisfying the contractual notification requirement.
The Court specifically held that IOCL’s failure to
refer the petitioner’s claims to the General Manager did not mean that
all claims automatically became arbitrable. Nor did such omission create a
subsequent agreement authorising the arbitrator to determine whether the claims
were notified. The contractual mechanism required consideration by the General
Manager, and the Supreme Court’s ruling made clear that, absent the required
determination, the arbitral tribunal could not assume jurisdiction over such
disputes.
Second, on the arbitrator-selection procedure, the Court held that the restrictive panel mechanism could not be
sustained in its existing form. The Court relied on Voestalpine Schienen
GmbH vs Delhi Metro Rail Corporation Limited and observed that a procedure
requiring one party to choose from a narrowly selected panel forwarded by the
other party deprived the choosing party of a meaningful and free choice and
could create an apprehension that preferred persons had been selected.
The Court noted that IOCL had forwarded only three
names, comprising retired officers of organisations such as ONGC, SAIL and
GAIL. The Court did not question their integrity or impartiality; however, it
held that the absence of free choice from a broad and diversified panel,
coupled with IOCL’s discretion to forward any three names, could generate an
apprehension regarding impartiality. Even an apprehension of bias was
sufficient to undermine the purpose of a neutral arbitral process.
Accordingly, the Court declared that any procedure
for appointment of an arbitrator must necessarily conform to the principles
laid down by the Supreme Court in Voestalpine Schienen GmbH. The
concerned General Manager was directed to consider the petitioner’s claims and
decide whether they were to be notified within eight weeks from the date
of judgment. Thereafter, the parties were directed to proceed in accordance
with law. The petition was disposed of with no order as to costs.
Important
Clarification
This judgment draws a crucial distinction between arbitrability
of claims and validity of the arbitrator-selection procedure.
The Court did not hold that every
contractual claim raised by the contractor became arbitrable merely because
IOCL failed to promptly refer the matter to the General Manager. The Court
expressly rejected that proposition. Under the contractual framework, the
status of a claim as a Notified Claim remained a jurisdictional gateway to
arbitration.
At the same time, the Court did not approve
a restrictive appointment mechanism merely because the three proposed persons
were retired officers from independent public-sector organisations. The
decisive concern was the lack of meaningful choice from a broad and diversified
panel and the unilateral discretion of IOCL to forward only three selected
names.
Therefore, the legal position emerging from the
judgment is that contractual preconditions governing arbitrability may remain
enforceable, but the procedure for constituting the arbitral tribunal must
independently satisfy standards of neutrality, independence, impartiality and
meaningful choice.
Sections
Involved
The principal statutory provisions involved were Sections 11(5), 11(6), 11(8), 12(1), 12(5), 16 and 29A of the Arbitration and Conciliation Act, 1996; the Fourth and Seventh Schedules to the Act; and Section 46 of the Indian Contract Act, 1872.
Link to download the order -https://www.mytaxexpert.co.in/uploads/1783326186_1264compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment