Facts of the Case
The Petitioner filed the writ petition challenging
the action of the Opposite Parties in not reimbursing the differential tax
amount arising from the change in the indirect tax regime from Value Added Tax
(VAT) to Goods and Services Tax (GST) with effect from 01.07.2017.
The dispute arose in the context of a works
contract where the introduction of GST created a tax burden that, according to
the Petitioner, had not been envisaged when the agreement was originally
entered into. The Court recorded that a batch of writ petitions had been filed
concerning the difficulties faced by contractors due to the change in the tax
regime applicable to works contracts under GST.
The Government of Odisha had subsequently issued
revised guidelines relating to works contracts under GST through Finance
Department Office Memorandum No. FIN-CT1-TAX-0045-2017/38535/F dated
10.12.2018, superseding the earlier guidelines dated 07.12.2017. These revised
guidelines addressed additional GST implications for works tendered before
01.07.2017 but executed wholly or partly thereafter.
Issues
Involved
The principal issues before the Court were:
- Whether the Petitioner was entitled to consideration of
reimbursement of the differential tax burden arising from the transition
from VAT and other pre-GST indirect taxes to GST with effect from
01.07.2017.
- Whether additional GST liability on works contracts, which had not
been envisaged at the time of entering into the original agreement, should
be dealt with under the revised guidelines issued by the Finance
Department, Government of Odisha, dated 10.12.2018.
- Whether the revised GST-inclusive value of balance work executed
after 30.06.2017 was required to be calculated under the prescribed
mechanism based on the Revised Schedule of Rates, 2014.
- Whether the Petitioner’s grievance was identical to the matter
dealt with in W.P.(C) No. 5933 of 2020 and could therefore be disposed of
in terms of the order dated 18.02.2020 passed in that case.
Petitioner’s
Arguments
The Petitioner submitted that the present writ
petition was identical to W.P.(C) No. 5933 of 2020 and requested that it be
disposed of in terms of the order dated 18.02.2020 passed in that writ
petition.
The Petitioner’s substantive grievance was that,
following the introduction of GST, tax became payable in a manner that had not
been envisaged when the works contract agreement was entered into. The
Petitioner challenged the failure of the Opposite Parties to reimburse the
differential tax amount resulting from the transition from VAT to GST.
Accordingly, the Petitioner sought consideration of
the additional tax burden under the revised guidelines governing works
contracts under GST.
Respondent’s
Arguments
The learned Additional Standing Counsel appearing
for the State-Opposite Parties did not dispute the Petitioner’s submission that
the present matter was identical to W.P.(C) No. 5933 of 2020.
The State’s position also brought on record the
revised guidelines issued by the Government of Odisha, Finance Department,
through Office Memorandum dated 10.12.2018 concerning works contracts under
GST.
These guidelines provided a mechanism for
determining the GST-inclusive work value of balance work in cases where tenders
had been invited before 01.07.2017 on the basis of SoR-2014 but payments for
balance work or full work were made after implementation of GST.
Court Order
/ Findings
The High Court took note of the revised guidelines
dated 10.12.2018 issued by the Finance Department, Government of Odisha.
The Court directed the Petitioner to make a comprehensive
representation before the appropriate authority within two weeks from the date
of the order, setting out the grievance concerning differential tax
reimbursement.
The Court further directed that, if such
representation was filed, the competent authority should consider and
dispose of the representation in light of the revised guidelines dated
10.12.2018, as expeditiously as possible and preferably by 02.01.2023.
The Court also expressly clarified that, if the
Petitioner remained aggrieved by the authority’s decision, it would be open to
the Petitioner to challenge that decision.
Accordingly, the writ petition was disposed of.
Important
Clarification
The judgment does not record a direct
unconditional award of differential GST reimbursement to the Petitioner.
Instead, it requires the Petitioner’s claim to be examined by the appropriate
authority under the revised Government of Odisha guidelines dated 10.12.2018.
The revised guidelines contemplate the following
mechanism for works tendered before 01.07.2017 but executed wholly or partly
thereafter:
- The item-wise quantity and value of balance work performed after
30.06.2017 must first be ascertained under the original agreement based on
the pre-revised SoR-2014.
- The revised estimated value of the balance work must then be
determined under the Revised SoR-2014.
- Where relevant goods or services are not covered by the Revised
SoR-2014, their tax-exclusive basic value is to be determined by removing
embedded incidences of VAT, Entry Tax, Excise Duty, Service Tax and
similar taxes.
- The revised estimated balance-work value must be enhanced or
reduced in the same proportion as the applicable tender premium or
discount.
- GST at the applicable rate of 5%, 12% or 18%, as the case may be,
must then be added to arrive at the GST-inclusive work value.
- If the revised GST-inclusive work value exceeds the original
agreement value for the balance work, the contractor is to be reimbursed
for the excess amount.
- If the revised GST-inclusive value is lower, the contractor’s
payment is to be reduced accordingly, and excess payment already made may
be recovered.
- The procedure applies to all works contracts, including EPC,
Turn-key and Lumpsum contracts.
- In F2 contracts, the competent authority is to determine the
taxable value under GST for each item of balance work by applying the
premium or discount offered by the contractor to the respective item.
Sections /
Legal Provisions and Government Guidelines Involved
Goods and Services Tax framework applicable from
01.07.2017 – The dispute concerns the transition from the
earlier indirect tax regime to GST and its financial impact on works contracts.
Works Contract under GST – The revised guidelines record that works contracts are treated as
composite supplies of services under GST and may attract GST at the applicable
rate of 18%, 12% or 5%, depending upon the nature of the works contract.
CGST and SGST Components – In the GST regime, the works contractor is required to raise a tax
invoice separately reflecting taxable work value and GST comprising CGST and
SGST.
Government of Odisha, Finance Department Office
Memorandum No. FIN-CT1-TAX-0045-2017/38535/F dated 10.12.2018 – Revised guidelines relating to works contracts under GST, issued in
supersession of the earlier Finance Department guidelines dated 07.12.2017.
Revised Schedule of Rates, 2014 (Revised SoR-2014) – Relevant for determining the revised estimated tax-exclusive value of balance work after 01.07.2017.
Link to download the order -https://www.mytaxexpert.co.in/uploads/1783313819_1001compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment