Facts of the Case
The petitioner, Sanjeev Kumar, filed a petition
under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking
appointment of an Arbitrator in terms of Clause 27 of the Agreement executed in
April 2018.
The agreement related to a licence to occupy land
for the purpose of a Comprehensive Parking Contract at Ludhiana Railway
Station. Open tenders had been floated by respondent No. 2 on 27 December 2017
for comprehensive parking arrangements for a period of three years at Ludhiana
Railway Station, covering the Main Side and the Civil Lines Side.
For the Ludhiana Main Side, the reserve price was
₹66,72,840 for one year and ₹2,00,18,520 for three years. The designated area
was 4745.90 square metres for private vehicles, together with the existing area
earmarked in the circulating area for commercial vehicles. The tender cost was
₹10,000 plus 18% GST, and the earnest money deposit was ₹20,01,852.
For the Ludhiana Civil Lines Side, the reserve
price was ₹20,72,712 for one year and ₹62,18,136 for three years. The
designated area was 1516.15 square metres for private vehicles. The tender cost
was ₹5,000 plus 18% GST, and the earnest money deposit was ₹6,21,814.
The petitioner emerged as the successful bidder and
was allotted the comprehensive parking contract at Railway Station Main for
three years on 19 March 2018. He was also allotted the comprehensive parking
contract at the Railway Station Civil Lines Side for three years.
The petitioner was required to deposit ₹27,06,000
towards quarterly licence fee plus 18% GST with the Station Superintendent,
Ludhiana, for the Railway Station Main Side and ₹9,90,000 plus 18% GST for the
Railway Station Civil Lines Side.
According to the petitioner, all necessary
formalities were completed. After execution of the agreement, respondent No. 2
was required to hand over the work site free from all obstructions. The site
was stated to be required to be handed over within one week from 25 March 2018,
but it was allegedly not handed over until 19 June 2018.
The petitioner asserted that the non-availability
of the work site caused financial loss. Numerous representations were submitted
to respondent No. 2 seeking handover of the work site in accordance with the
agreement, but without success. The petitioner relied upon representations
dated 21 June 2018, 28 June 2018, 30 June 2018, 2 July 2018, 7 August 2018, and
20 August 2018.
The petitioner also invoked the arbitration clause
seeking appointment of an Arbitrator, but according to him, the respondents did
not reply. Instead, respondent No. 2 terminated the comprehensive parking
contract on 10 September 2018 on the ground that the petitioner had failed to
deposit the licence fee for the second quarter. The competent authority
consequently decided to terminate the contract with forfeiture of the security
amount and performance guarantee.
The petitioner thereafter issued a notice dated 15
January 2019 to respondent No. 2 seeking appointment of an Arbitrator. It was
also asserted that a sum of approximately ₹1.03 crore had already been
deposited with respondent No. 2 and had not been refunded along with interest.
Issues
Involved
- Whether a bona fide and arbitrable dispute existed between the
petitioner and the respondents warranting appointment of an Arbitrator
under Section 11(6) of the Arbitration and Conciliation Act, 1996.
- Whether the petitioner’s notice invoking arbitration satisfied the
requirements of Clause 27.1(c) of the contract agreement.
- Whether specification of the “subject of dispute” in the invocation
notice was sufficient for compliance with the contractual arbitration
mechanism.
- Whether the respondents’ objection concerning waiver under Section
12(5) of the Arbitration and Conciliation Act, 1996 could defeat the
request for appointment of an Arbitrator.
- Whether the alleged waiver document relied upon by the respondents
could be accepted when its material columns were blank and its execution
remained debatable.
- Whether the respondent could rely upon Clause 15 of the agreement
regarding suo motu termination when such a ground had not been pleaded in
the written reply and the reply was silent regarding compliance with the
contractual notice requirement.
Petitioner’s
Arguments
The petitioner contended that he had completed all
necessary contractual formalities after being declared the successful bidder.
It was argued that respondent No. 2 was contractually
required to hand over the work site free from all obstructions within the
stipulated period, but the site was not handed over until 19 June 2018. This
delay allegedly caused substantial financial loss.
The petitioner relied upon several representations
made to the respondent authorities seeking proper handover of the work site in
accordance with the agreement.
It was further contended that the arbitration
clause had been duly invoked, but the respondents failed to respond and did not
appoint an Arbitrator.
The petitioner challenged the termination of the
parking contract dated 10 September 2018, which was based on the alleged
non-payment of the second-quarter licence fee and resulted in forfeiture of the
security amount and performance guarantee.
The petitioner further relied upon the notice dated
15 January 2019 seeking appointment of an Arbitrator and asserted that
approximately ₹1.03 crore deposited with respondent No. 2 remained unrefunded
along with interest.
Respondents’
Arguments
The respondents raised two principal objections in
their reply.
First, they relied upon Clause 27.1(c) of the
contract agreement and contended that a demand for arbitration was required to
specify the matters in question or forming the subject of the dispute or
difference, as well as the amount of the claim item-wise, if any. According to
the contractual clause, only those disputes or differences in respect of which
a demand had been made, together with any counterclaim or set-off raised by the
Railway, could be referred to arbitration.
Second, the respondents raised an objection
concerning waiver under Section 12(5) of the Arbitration and Conciliation Act,
1996 and relied upon Annexure R-1.
During oral submissions, learned counsel for the
respondent further referred to Clause 15 of the agreement and argued that the
Railway Administration could, if required, terminate the contract suo motu by
giving one month’s notice to the licensee.
Court Order
/ Findings
The High Court examined Clause 27.1(c) of the contract
agreement and observed that the word “or” appeared in the relevant options
contained in the clause.
The Court found that, through the notice of
invocation dated 15 January 2019, the petitioner had elaborated the “subject of
the dispute.” The respondents had not filed any reply to that invocation
notice.
The Court held that recital of the “subject of
dispute” in the notice invoking arbitration was sufficient to satisfy the
requirement of Clause 27.1(c) of the contract agreement, which was ultimately to
be treated as an arbitration clause.
Regarding the second objection based on waiver
under Section 12(5) of the Act, the Court examined Annexure R-1. It observed
that the vernacular proforma contained blank necessary columns and only the
alleged signature of the tenderer appeared at the tail end of the paper.
The Court further noted that the document was
neither signed by the respondent authority nor filled in with reference to any
particulars of the petitioner, except for alleged short signatures appearing
across the first three lines. The Court held that the matter relating to such a
document would remain debatable.
As regards the oral submission based on Clause 15
of the agreement, the Court observed that no such ground had been taken in the
respondents’ reply. The written reply was conspicuously silent regarding the
requirement arising from the said termination clause.
Upon considering the pleadings of the parties, the
High Court concluded that a bona fide dispute existed between them and that the
matter was required to be referred to a sole Arbitrator for adjudication.
The tentative value of the claim was recorded as
₹1.03 crore plus interest till date and compensation, if any.
Accordingly, the High Court appointed Hon’ble Mr.
Justice Rameshwar Singh Malik (Retd.) as the sole Arbitrator to resolve the
disputes and differences between the parties.
The appointment was made subject to the declaration
required under Section 12 of the Arbitration and Conciliation Act, 1996
concerning the Arbitrator’s independence and impartiality.
The Court further directed that the arbitral
proceedings be completed within the specified period in terms of Section 29-A
of the Act.
The Arbitrator’s fee was directed to be governed by
the Fourth Schedule to the Arbitration and Conciliation Act, 1996, as amended
from time to time, and was to be shared equally by the parties.
The venue of arbitration proceedings was fixed at
Ludhiana, subject to the convenience of the Arbitrator.
Important
Clarification
The decision provides an important clarification
regarding compliance with a contractual arbitration invocation clause. Where
Clause 27.1(c) required the arbitration demand to identify the relevant matters
or the subject of the dispute or difference, the High Court treated a clear recital
and elaboration of the “subject of dispute” in the invocation notice as
sufficient compliance.
The judgment also indicates that an objection based
on an alleged waiver under Section 12(5) cannot be mechanically accepted where
the relied-upon document itself contains blank material particulars, lacks
execution by the respondent authority, and raises a debatable issue regarding
its authenticity or completeness.
Further, a party cannot effectively rely upon an
additional contractual ground at the stage of oral submissions when that ground
was not taken in its written reply, particularly where the pleading remains
silent regarding compliance with the relevant contractual requirement.
Sections and
Contractual Provisions Involved
Section 11(6), Arbitration and Conciliation Act,
1996: Governs recourse to the Court for appointment of
an Arbitrator where the agreed appointment procedure fails in circumstances
covered by the provision.
Section 12, Arbitration and Conciliation Act, 1996: Relates to disclosure requirements and circumstances concerning the
independence and impartiality of an Arbitrator.
Section 12(5), Arbitration and Conciliation Act,
1996: Concerns statutory ineligibility for appointment
as Arbitrator in specified circumstances and the legally prescribed framework
concerning waiver.
Section 29-A, Arbitration and Conciliation Act,
1996: Relates to the time limit for making an arbitral
award.
Fourth Schedule, Arbitration and Conciliation Act,
1996: Provides the statutory framework relevant to the
fee structure of Arbitrators.
Clause 27 of the Agreement: Arbitration clause forming the contractual basis for seeking
appointment of an Arbitrator.
Clause 27.1(c) of the Agreement: Concerned the contents and scope of the demand for arbitration,
including specification of the matters or subject of dispute or difference and
claim details, if any.
Clause 15 of the Agreement: Relied upon orally by the respondent in relation to the Railway Administration’s power to terminate the contract suo motu with one month’s notice to the licensee.
Link to Download the Order-https://mytaxexpert.co.in/uploads/1783402093_1336compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment