Facts of the Case
The petitioner, M/s J.B. Enterprise, was
issued various supply orders dated 10.07.2017 by the concerned Forest
Department authorities for supply of materials including plastic mesh wire
(Tuflex) of specified dimensions and binding G.I. wire.
The supply orders included:
- Supply Order No. SP/GGP/SUPPLY ORDER/90;
- Supply Order No. H/GGP/SUPPLY ORDER/38;
- Supply Order No. SP/03/Plantation/90(A)-90(c); and
- Supply Order No. SF/HR/68/GGP/45.
The petitioner claimed that the required materials
had been supplied in accordance with the supply orders. However, the
respondents allegedly failed to honour the bills submitted by the petitioner.
Aggrieved by the non-payment, the petitioner
instituted the writ petition seeking a direction for disbursement of the
contractor’s bill amounting to Rs. 21,87,357/-, together with interest
as may be applicable.
The respondents, through the Divisional Forest
Officer, Guwahati Social Forestry Division, filed an affidavit referring to a
committee report. According to the stand taken in the affidavit, the works had
been executed without obtaining technical sanction from the competent
authority. It was also stated that verification had been conducted almost one
year after execution and that there were instances of damage and theft, due to
which exact verification could not be undertaken.
Issues
Involved
The principal issues before the Court were:
- Whether the petitioner’s claim for unpaid contractor bills had been
admitted or denied by the respondent authorities.
- Whether absence of technical sanction from the competent authority could
constitute a valid reason for refusing payment where the supplies made
pursuant to the supply orders were not denied.
- Whether delayed verification by the departmental authorities,
conducted approximately one year later, could be used as a ground to refuse
payment.
- Whether allegations relating to theft, damage or misplacement could
justify non-payment when the actual supply orders concerned plastic mesh
wire and binding G.I. wire.
- Whether the petitioner was entitled to consideration and payment of
the admitted bill amount upon establishing issuance of the supply orders
and actual supply of the ordered materials.
Petitioner’s
Arguments
The petitioner contended that:
- Valid supply orders had been issued by the concerned Forest
Department authorities.
- The materials required under those supply orders had actually been
supplied.
- Despite completion of the supplies, the respondents failed to
honour the bills submitted by the petitioner.
- The petitioner was therefore entitled to payment of the outstanding
contractor’s bill amounting to Rs. 21,87,357/-, along with
applicable interest.
- The continued withholding of payment necessitated intervention by
the High Court.
Respondent’s
Arguments
The respondents relied upon the findings of a committee
and contended, in substance, that:
- The works had been executed without obtaining technical sanction
from the competent authority.
- Verification was carried out almost one year after execution.
- There had been instances of damage and theft.
- Due to the passage of time and the alleged damage or theft, exact
verification could not be undertaken.
- The committee had assessed expenditure and undertaken field
verification on the basis of available circumstances.
Court Order
/ Findings
The Gauhati High Court found that the respondents’
affidavit did not amount to a denial of the petitioner’s claim. Rather, the
respondents were refusing payment on the plea that technical sanction had not
been obtained from the competent authorities.
The Court observed that where the petitioner had
actually made supplies pursuant to the supply orders and verification was
undertaken by the departmental authorities only after one year, such delayed
verification was more in the nature of laches on the part of the department
and could not be used as a reason for refusing to honour the contractor’s
bills.
The Court further noticed that the respondents had
referred to theft of saplings. However, the supply orders forming the subject
matter of the petitioner’s claim related to plastic mesh wire of specified
dimensions and binding G.I. wire. The Court found that such a stand
appeared to be a misdirection by the authorities from the claim made by the
petitioner.
The Court emphasized that the core fact remained
that the supplies made by the petitioner were not denied by the respondents.
The Court held that the three grounds emerging from
the respondents’ stand—
- absence of technical sanction;
- verification after one year; and
- possible misplacement or theft of supplied articles—
were not acceptable reasons that could be construed
as a non-admission by the Forest Department authorities of the petitioner’s
contractor bill claim.
Final
Direction of the Court
The Court directed the petitioner to submit an
application before the Principal Chief Conservator, providing:
- complete details of the supply orders;
- details of the supplies made; and
- any supporting material capable of substantiating that the ordered
items had actually been supplied.
Upon receipt of such application, the Principal
Chief Conservator was directed to:
- provide the petitioner an opportunity of hearing;
- allow the petitioner to produce materials substantiating issuance
of the supply orders and actual supplies;
- examine whether the supply orders were in fact issued and whether supplies
were actually made; and
- if such facts were established, pass orders for payment of all
admitted bill amounts.
The Court directed that the required order be
passed within two months from the date of submission of the petitioner’s
application.
The writ petition was accordingly disposed of.
Important
Clarification
The judgment is significant for the following
clarification:
Where supplies pursuant to departmental supply
orders are not denied, the department cannot treat its own internal or
administrative deficiencies as an automatic justification for withholding
payment.
In particular:
- absence of technical sanction does not, by itself, constitute an
acceptable ground for treating an otherwise undisputed supply claim as
denied;
- delayed verification by the department may amount to departmental
laches and cannot automatically prejudice the supplier;
- grounds relating to theft, damage or misplacement must have a
rational and factual connection with the actual goods covered by the
supply orders;
- a departmental authority cannot misdirect itself by relying upon
facts concerning different materials or items unrelated to the
contractor’s actual claim; and
- where issuance of supply orders and actual supply are established,
orders for payment of admitted bill amounts are required to be considered
and passed.
Section /
Constitutional Provision Involved
Article 226 of the Constitution of India – Exercise of writ jurisdiction by the High Court in relation to
non-payment of contractor’s bills where the respondent authorities’ stand did
not amount to a genuine denial of the supply claim and the grounds advanced for
withholding payment were found unacceptable.
Case Law /
Precedent Position
No separate precedent or reported case law was
cited or discussed in the judgment. The
decision was rendered on the specific facts, pleadings, affidavit of the
respondents, the nature of the supply orders and the Court’s finding that the
supplies were not denied by the respondent authorities.
Accordingly, no unrelated judicial precedent has been added merely for SEO purposes, thereby preserving the accuracy and meaning of the judgment.
Link to download the order - https://www.mytaxexpert.co.in/uploads/1783318603_1202compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment