Facts of the Case
The petitioner, City Steels, was issued multiple
supply orders dated 10 July 2017 by the concerned Forest Department authorities
for supply of specified materials. The supply orders included items such as
tub-raised plants, plastic mesh wire (Tuflex), and binding G.I. wire at the
rates and quantities stipulated in the respective orders.
The petitioner claimed that the required materials
had been supplied in accordance with the supply orders. However, the respondent
authorities did not honour the bills submitted by the petitioner.
Aggrieved by the non-payment, the petitioner
instituted the writ petition seeking a direction for disbursement of its
contractor’s bill amounting to Rs. 48,61,246/-, along with applicable
interest.
The respondent authorities, through the Divisional
Forest Officer, Guwahati Social Forestry Division, filed an affidavit referring
to a committee report. According to the stand taken, the works had been
executed without obtaining technical sanction from the competent authority. It
was further stated that verification had taken place almost one year after
execution and that cases of damage and theft had occurred, due to which the
committee could not ascertain the exact number of certain plantation items. The
committee nevertheless assessed expenditure and ascertained certain quantities
on the basis of field verification.
Issues
Involved
- Whether the respondent authorities could refuse payment of the
petitioner’s contractor/supply bills merely on the ground that technical
sanction had not been obtained from the competent authority.
- Whether delayed departmental verification, conducted approximately
one year after execution or supply, could constitute a valid ground for
withholding payment.
- Whether subsequent damage, misplacement, or theft of supplied
articles could justify refusal to honour the petitioner’s bills when the
fact of supply was not specifically denied.
- Whether the respondents’ affidavit amounted to a denial of the
petitioner’s claim or merely disclosed reasons for refusing payment.
- Whether the High Court, in exercise of writ jurisdiction under
Article 226 of the Constitution of India, could direct the competent
authority to examine the supporting materials and pass appropriate orders
for payment of admitted bill amounts.
Petitioner’s
Arguments
The petitioner contended that:
- Valid supply orders had been issued by the departmental authority
on 10 July 2017.
- The materials required under those supply orders had actually been
supplied.
- Despite completion of the supplies, the respondents failed to
honour the submitted bills.
- The outstanding contractor’s bill amounted to Rs. 48,61,246/-.
- The petitioner was therefore entitled to a direction for
disbursement of the outstanding amount along with applicable interest.
The petitioner’s grievance was fundamentally based
on the failure of the departmental authorities to make payment despite supplies
having been made pursuant to official supply orders.
Respondent’s
Arguments
The respondents relied upon the committee report
and contended, in substance, that:
- The works had been executed without obtaining technical sanction
from the competent authority.
- Verification was carried out almost one year after execution.
- There had been cases of damage and theft.
- Due to the lapse of time and intervening circumstances, the
committee could not ascertain the exact number of certain plantation
items.
- The committee nevertheless assessed expenditure for individual
plantation items, RCC flower tubs, and plastic tubs and ascertained
quantities on the basis of field verification.
Court’s
Findings
The Gauhati High Court examined whether the
respondents had actually admitted or denied the petitioner’s claim for unpaid
contractor bills.
The Court found that the affidavit filed by the
respondents did not amount to a denial of the petitioner’s claim. Rather, the
respondents were refusing payment principally on the ground that technical
sanction had not been obtained from the competent authorities.
The Court further observed that if the petitioner
had actually made supplies pursuant to the supply orders and departmental
verification was conducted only after one year, such delayed verification was
more in the nature of laches on the part of the department. The
department could not rely upon its own delayed verification as a reason for not
honouring the contractor’s bills.
The Court also considered the stand concerning
theft or misplacement of supplied articles during the intervening period. It
found that the core fact remained that the supplies made by the petitioner were
not denied by the respondents.
Accordingly, the Court held that the following
grounds were not acceptable reasons capable of being construed as non-admission
of the petitioner’s contractor bill claim:
- absence of technical sanction;
- verification conducted after one year; and
- possible misplacement or theft of supplied articles during the
intervening period.
Court Order
/ Final Directions
The High Court directed the petitioner to submit an
application before the Principal Chief Conservator, providing:
- complete details of the supply orders;
- particulars of the supplies made; and
- all supporting material capable of substantiating that the ordered
items had actually been supplied.
Upon receipt of the application, the Principal
Chief Conservator was directed to:
- provide the petitioner an opportunity of hearing;
- permit the petitioner to produce materials substantiating issuance
of the supply orders and actual supplies;
- examine whether the supply orders were in fact issued and whether
supplies were actually made; and
- if such facts were established, pass orders for payment of all
admitted bill amounts.
The Court directed that the required order be
passed within two months from the date of submission of the petitioner’s
application.
The writ petition was disposed of accordingly.
Important Clarification
This judgment does not lay down that every disputed
contractor bill must automatically be paid through writ proceedings. The
significant factual and legal feature of the case was that the respondent
authorities did not deny the core fact of supplies in a manner sufficient to
constitute a genuine non-admission of the claim.
The Court distinguished between:
- a genuine denial of the underlying supply or liability; and
- a refusal to make payment based on departmental or administrative
grounds such as absence of technical sanction, delayed verification, and
subsequent theft or misplacement.
The judgment is particularly important for the
principle that departmental delay in verification cannot ordinarily be used
by the department itself as a justification to defeat an otherwise admitted
contractor or supplier claim.
It further clarifies that where supply orders and
actual supplies are established, the competent authority must consider and pass
orders for payment of admitted bill amounts rather than reject the claim solely
on internal administrative deficiencies.
Sections /
Legal Provisions Involved
Article 226 of the Constitution of India – Writ jurisdiction of the High Court.
The dispute also concerned administrative and
contractual payment obligations arising from departmental supply orders and the
treatment of admitted contractor/supplier bills.
Concerned
Case-Law Principle
City Steels vs State of Assam & Ors. establishes that where supplies pursuant to departmental supply orders
are not denied, the Government department cannot treat the claim as genuinely
disputed merely by relying upon:
- absence of technical sanction;
- verification conducted after a substantial delay attributable to
the department; or
- subsequent theft, damage, or misplacement of supplied articles.
The decision further recognises that departmental laches in conducting timely verification should not become a ground to refuse payment of an otherwise admitted contractor or supplier bill.
Link to Download the Order
https://www.mytaxexpert.co.in/uploads/1783319095_1203compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment