Facts of the Case
The Petitioner, BPT Infra Projects Pvt. Ltd., filed a
petition under Section 11(6) of the Arbitration and Conciliation Act, 1996
seeking appointment of an arbitrator for adjudication of disputes with the
Respondent, Indraprastha Ice and Cold Storage Pvt. Ltd.
A Letter of Intent dated 19.01.2022 was issued by the
Respondent in favour of the Petitioner for construction of a factory and
setting up of a CA (Control Atmosphere Storage) Plant at Village Bayal,
Tehsil Nirmand, District Kullu, Himachal Pradesh. The Petitioner was a private
company engaged in construction business. An Agreement dated 01.02.2022
was executed between the parties, and the construction was to be completed and
handed over by the end of April 2022. The tentative value of the work was
approximately ₹10 crore.
After commencement of work, the Petitioner claimed that the
layout plan supplied by the Respondent did not conform to actual site
conditions. According to the Petitioner, the Respondent was informed and, on
its instructions, a feasibility survey was conducted. A revised layout plan was
issued on 27.01.2022, further revised on 05.02.2022, when the
construction area increased from approximately 5,500 square metres to 7,500
square metres, and revised again on 24.02.2022.
The Petitioner sought requisite drawings and requested
provision of electricity through communication dated 26.02.2022.
According to the Petitioner, the Respondent retaliated by issuing a letter
dated 26.02.2022 under the guise of a show-cause notice, alleging poor quality
construction, requiring submission of an up-to-date bill and directing
clearance of the site within seven days.
The Petitioner replied on 28.02.2022, refuting the
allegations. However, the Respondent terminated the contract by letter dated 03.03.2022.
The Petitioner alleged that the Respondent unilaterally prepared a Memorandum
of Understanding and Settlement and sought the Petitioner’s signature.
Representatives and engineers of both parties jointly prepared a list of
material lying at the site on 04.03.2022. By communication dated 05.03.2022,
the Petitioner objected to both the termination and the proposed Memorandum of
Understanding and Settlement.
The Petitioner asserted claims including:
- approximately
₹46,30,744 for work executed;
- approximately
₹55,08,653 for material lying at the site; and
- approximately
₹10,25,000 toward expenses incurred.
These claims were communicated to the Respondent on 08.03.2022.
The Petitioner alleged that, through communication dated 11.03.2022, the
Respondent unilaterally approved only certain amounts and made arbitrary and
illegal deductions.
The Petitioner further claimed that it was called to the
Respondent’s office on 16.03.2022 and made to sign certain papers under
the impression that they related to acknowledgement of release of the
Performance Guarantee. According to the Petitioner, upon receiving
communication dated 17.03.2022, it discovered an attachment suggesting
that it had accepted an abstract of final payment.
The Petitioner asserted that it was compelled to submit a bill
by e-mail dated 17.03.2022, following which approximately ₹46 lakh
was transferred to its account. It maintained that the bills submitted were
under duress and compulsion and subsequently raised objections.
Disputes continued. By communication dated 18.04.2022,
the Petitioner requested settlement of disputes, but the Respondent declined.
The Petitioner thereafter invoked arbitration under Clause 11 of the
Agreement by notice dated 14.06.2022. The Respondent rejected the
request by letter dated 20.06.2022, leading to the Section 11(6)
petition.
Issues Involved
The principal issues before the Delhi High Court were:
- Whether
an independent arbitrator should be appointed under Section 11(6) of
the Arbitration and Conciliation Act, 1996.
- Whether
the disputes between the parties had already been fully and finally
settled, leaving no subsisting arbitrable dispute.
- Whether
acceptance of approximately ₹46.81 lakh and release of the
Performance Bank Guarantee amounted to complete satisfaction of all
contractual claims.
- Whether
the Petitioner’s alleged execution or acceptance of a final bill prevented
invocation of arbitration.
- Whether
the alleged full and final settlement was obtained under economic
pressure, duress or compulsion.
- Whether
the approximately ₹46.81 lakh payment represented settlement only of
material supplied by vendors or settlement of the Petitioner’s entire
contractual claims.
- Whether
the Petitioner’s claims of approximately ₹1.83 crore, including
claims for other work, expenses and damages arising from alleged illegal
termination, remained unresolved.
- Whether
questions concerning the nature and effect of the alleged settlement
required evidence and should therefore be determined by the Arbitral
Tribunal rather than conclusively decided in Section 11 proceedings.
- Whether
prima facie arbitrable disputes existed despite the Respondent’s plea of
accord and satisfaction.
Petitioner’s Arguments
The Petitioner contended that genuine and unresolved disputes
continued to exist and required adjudication through arbitration.
The principal submissions were:
- The
Respondent repeatedly revised the layout plan after commencement of the
project, including increasing the construction area from approximately
5,500 square metres to 7,500 square metres.
- The
Petitioner requested requisite drawings and electricity supply for
execution of work, but the Respondent issued a show-cause notice alleging
poor quality and thereafter terminated the contract.
- The
termination was disputed and protested by the Petitioner.
- The
Petitioner objected to the Memorandum of Understanding and Settlement
allegedly prepared unilaterally by the Respondent.
- The
Petitioner had claims for work executed, material lying at site, expenses
incurred and damages arising from alleged illegal termination.
- The
Petitioner alleged that the Respondent made unilateral and illegal
deductions from its claims.
- The
Petitioner claimed that papers were signed under the impression that they
related to release of the Performance Guarantee and that it later
discovered an attachment suggesting acceptance of the final-payment
abstract.
- The
bills were allegedly submitted under duress and compulsion.
- The
amount of approximately ₹46.81 lakh represented payment relating to
materials supplied by vendors and did not constitute settlement of the
Petitioner’s entire claims.
- The
Petitioner’s overall claims were approximately ₹1.83 crore, of
which only approximately ₹46.81 lakh had been paid.
- The
Petitioner asserted that it was a contractor and not merely a supplier,
and it had been compelled to submit a bill concerning supply of material.
- The
payment received was accepted without prejudice to the right to
claim remaining amounts.
- Immediately
after receipt of the amount and release of the Performance Bank Guarantee,
the Petitioner asserted its remaining claims.
- The
question whether the alleged final bill constituted full and final
settlement required evidence and could not be conclusively determined in a
Section 11 petition.
Respondent’s Arguments
The Respondent raised a preliminary objection that all
disputes had already been resolved, and therefore no arbitrable dispute
survived.
Its principal contentions were:
- Arbitration
could be initiated only if unresolved disputes remained.
- According
to the Respondent, the Petitioner’s own admissions demonstrated that no
disputes remained.
- The
Petitioner had allegedly acknowledged settlement through its e-mail dated 16.03.2022.
- The
Performance Bank Guarantee dated 24.01.2022 had been released on 16.03.2022
after payment of all dues.
- The
Petitioner had allegedly accepted the final payment.
- The
final bill followed a joint inspection/survey conducted by representatives
of both parties.
- Once
full and final payment had been accepted, nothing remained for
arbitration.
- Referring
to Supreme Court precedents, the Respondent argued that a Section 11 Court
could screen out ex facie meritless, frivolous or non-existing disputes.
- The
Respondent contended that the Court’s Section 11 jurisdiction was not
confined merely to mechanically identifying the existence of an
arbitration agreement.
- Since
no subsisting arbitrable dispute remained, the petition should be
dismissed.
Court Order / Findings
The Delhi High Court allowed the petition and appointed an
independent arbitrator. Its material findings were as follows:
1. Correspondence Demonstrated Continuing Disputes
The Court examined the correspondence exchanged between the
parties. It noted that the Petitioner had protested the termination and had
expressly stated that the proposed Memorandum of Settlement was unacceptable.
The Petitioner had also asserted financial loss from alleged
illegal termination and reserved its right to claim damages.
2. Joint Survey and Final Bill Did Not
Conclusively End the Controversy
The Court noted that a joint survey was conducted by
representatives of both parties and that details of work and material were
prepared.
It further recorded that the Petitioner submitted an invoice
of approximately ₹47.66 lakh for material along with applicable GST,
with diesel reimbursement stated separately, while excavation and
foundation-related work was estimated at approximately ₹23,23,159. A
final payment abstract of approximately ₹46.81 lakh carried an
endorsement of acceptance by the vendor.
However, the Petitioner explained that this final bill related
to work/material concerning vendors, while its independent claims remained
unresolved.
3. Petitioner Claimed Approximately ₹1.83 Crore
The Court recorded the Petitioner’s explanation that its total
claim was approximately ₹1.83 crore, whereas only approximately ₹46.81
lakh had been paid.
The Petitioner maintained that the amount paid represented
vendor-related material payments and not full settlement of all claims.
4. Immediate Protest Supported Existence of
Dispute
The Court referred to the Petitioner’s letter dated 19.03.2022,
in which it explained that it was a contractor rather than a supplier and
claimed that it had been compelled to submit the bill for supply of material.
The Petitioner also challenged unilateral deductions and
asserted that the approximately ₹46 lakh payment had been received without
prejudice to its entitlement to claim other amounts.
5. Claims Extended Beyond Material Supplied
The Court found that, from the beginning, the Petitioner had
claimed not only amounts for material supplied by vendors but also:
- amounts
for other work done;
- expenses
incurred; and
- damages
for alleged illegal termination of the contract.
The Petitioner’s case was that ₹46.81 lakh represented only
payment toward vendor-supplied material.
6. Full and Final Settlement Question Required
Evidence
This was a central finding of the judgment.
The Court held that whether the alleged final bill constituted
full and final settlement of all claims, or whether the Petitioner
remained entitled to other claimed amounts, could not be determined without
recording evidence.
Consequently, that issue was beyond the scope of the Section
11 petition for appointment of an arbitrator.
7. Respondent Could Prove Settlement Defence
Before Arbitrator
The Court clarified that the Respondent remained at liberty to
prove before the Arbitrator its defence that all contractual claims had already
been satisfied.
Thus, appointment of the Arbitrator did not reject the
Respondent’s settlement defence on merits; it left that defence open for
adjudication before the Arbitral Tribunal.
8. Prima Facie Disputes Existed
The High Court held that prima facie disputes had arisen
between the parties.
The correspondence showed that the Petitioner had claimed
damages for alleged illegal termination and other incidental expenses. The
Court viewed the payment concerning supplied material as settlement of only a
partial claim on the Petitioner’s case, while other claims were asserted to
remain outstanding.
9. Economic Pressure and Duress Were Arbitrable
Questions
The Court noted the Petitioner’s case that it had accepted the
amount and release of the Performance Bank Guarantee due to economic
pressure and duress, and that this did not constitute full and final
settlement.
The Court held that the Petitioner still had the right to have
its approximately ₹1.83 crore claims arbitrated and decided by the learned
Arbitrator.
10. Independent Arbitrator Appointed
The High Court appointed Mr. K.S. Khurana, Additional
District Judge (Retd.), as the independent Arbitrator to adjudicate
disputes between the parties.
11. Parties Free to Raise Objections Before
Arbitrator
The Court expressly granted liberty to both parties to raise
their respective objections before the Arbitrator.
12. Arbitrator’s Fee
The Arbitrator’s fee was directed to be fixed in accordance
with the Fourth Schedule to the Arbitration and Conciliation Act, 1996.
13. Disclosure and Eligibility Requirements
The appointment was made subject to:
- necessary
disclosure under Section 12(1) of the Arbitration and Conciliation
Act, 1996; and
- the
Arbitrator not being ineligible under Section 12(5) of the Act.
The parties’ counsel were directed to contact the Arbitrator
within one week of communication of the order. The petition was accordingly
allowed.
Important Clarification
This judgment does not finally hold that the
Petitioner’s allegations of duress, coercion, illegal deductions or outstanding
claims are proved.
The High Court’s essential conclusion was that:
- prima
facie disputes existed;
- the
correspondence indicated continuing claims;
- the
alleged full and final settlement was seriously disputed;
- determining
whether all claims had actually been settled required evidence;
- such
disputed factual questions were beyond the limited scope of the Section 11
proceeding; and
- the
Respondent could establish its full-and-final-settlement defence before
the Arbitrator.
Therefore, the case is significant for the proposition that a
disputed discharge, final bill or alleged accord and satisfaction does not
automatically bar arbitration where the claimant raises a genuine and factually
debatable case of economic duress, compulsion, partial settlement or unresolved
claims.
Sections Involved
·
Section 11(6), Arbitration and Conciliation
Act, 1996 – Invoked for appointment of an arbitrator where the agreed
appointment mechanism had not resulted in constitution of the Arbitral
Tribunal.
·
Section 11(6A), Arbitration and Conciliation
Act, 1996 – Discussed in the context of the scope of judicial inquiry
at the referral stage through the cited precedent in Indian Oil Corporation
Limited v. NCC Limited.
·
Section 12(1), Arbitration and Conciliation
Act, 1996 – Requires necessary disclosure by the proposed arbitrator
concerning circumstances relevant to independence and impartiality.
·
Section 12(5), Arbitration and Conciliation
Act, 1996 – Concerns ineligibility of an arbitrator falling within
specified categories.
·
Fourth Schedule, Arbitration and Conciliation
Act, 1996 – Applied for fixation of the learned Arbitrator’s fees.
· Clause 11 of the Agreement – Arbitration clause invoked by the Petitioner through notice dated 14.06.2022.
Link to download the order -
Download
the Order – BPT Infra Projects Pvt. Ltd. vs Indraprastha Ice and Cold Storage
Pvt. Ltd.
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment