Facts of the Case
KNK Construction Private Limited was originally incorporated
on 12 April 2006 under the name “KNK Nexgen Construction Private Limited.”
On 24 August 2015, the company was enlisted as a Class I contractor with
the Central Public Works Department (CPWD), and its subsisting licence was
extended up to 31 March 2018.
On 18 May 2017, the company changed its name from “KNK
Nexgen Construction Private Limited” to “KNK Construction Private
Limited,” essentially removing the word “Nexgen.” According to the
petitioners, this change of name was intimated to the Special Director General,
CPWD, on 2 November 2017.
Subsequently, during March 2021, the company submitted an
online application through the CEMS portal concerning the change in name,
together with relevant documents, including the Memorandum and Articles of
Association, prescribed annexures, certificate of incorporation recording the
name change, PAN and GST documents.
The CPWD authorities took the view that the company had
changed its name without obtaining prior in-principle approval of the
Enlistment Authority and had intimated the change only after a lapse of
approximately 3.5 years. Treating this as a violation of Rule 9.6 of the
CPWD Enlistment Rules, 2020, disciplinary proceedings were initiated.
By order dated 28 February 2022, the contractor’s
enlistment was suspended for two years, thereby preventing participation
in the CPWD tendering process. Aggrieved by the suspension, the petitioners
approached the High Court under Articles 226 and 227 of the Constitution of
India.
Issues Involved
The principal issues before the High Court were whether the
suspension of the petitioner-company from participating in CPWD tenders was
legally sustainable when the disciplinary procedure prescribed under Rule
13.2 of the CPWD Enlistment Rules, 2020 had allegedly not been followed;
whether the Empowered Committee itself was required to consider the documents,
facts and circumstances, issue the show cause notice, permit a personal hearing
if necessary, and thereafter make its recommendation to the Enlistment
Authority; whether a show cause notice issued by an authority other than the
Empowered Committee could satisfy the mandatory procedure under Rule 13.2; and
whether the conclusion that the change of name was intimated only after 3.5
years was sustainable in view of the petitioners’ documents showing intimation
dated 2 November 2017 and subsequent CPWD dealings with the company under its
changed name.
Petitioners’ Arguments
The petitioners contended that the suspension order dated 28
February 2022 came unexpectedly because they were not properly made aware of or
associated with the proceedings that culminated in the impugned action.
It was argued that the company’s name had been changed in 2017
and that documentary records demonstrated that the change was intimated to the
competent CPWD authority on 2 November 2017 itself. Therefore, the
allegation that the company had communicated the change only after 3.5 years
was contrary to the record.
The petitioners further submitted that the change merely
involved deletion of the word “Nexgen” from the corporate name and did
not amount to any alteration in the constitution of the company warranting
disciplinary action of the nature imposed.
It was also emphasized that subsequent contracts had been
awarded to the petitioner-company in the changed name, namely KNK
Construction Private Limited, demonstrating that the department had
knowledge of and had acted upon the changed name.
The petitioners accordingly challenged the decision-making
process as contrary to the prescribed procedure and principles of fair hearing.
Respondents’ Arguments
The respondents contended that the applicable CPWD Enlistment
Rules required prior approval for any change in the name or status of an
enlisted company.
According to the respondents, the requisite intimation had not
been received by the competent authority in accordance with the prescribed
procedure. Since the petitioner-company had changed its name without first
obtaining approval from the Enlistment Authority, the respondents argued that
the action taken under the Enlistment Rules was justified.
The respondents therefore maintained that the suspension order
could not be faulted and sought dismissal of the writ petition.
Court’s Findings
The High Court closely examined Rule 9.6 of the CPWD
Enlistment Rules, 2020, which provides that a change in the name of an
entity is permissible with prior approval of the Enlistment Authority and
requires the contractor to intimate the change not later than one month from
such change, along with acknowledgements from the relevant Bank, Income Tax and
GST authorities. Failure to comply may result in cancellation of enlistment.
However, the decisive issue before the Court concerned
compliance with Rule 13.2, which regulates disciplinary action against
an enlisted contractor.
The Court found that Rule 13.2 requires the Empowered
Committee to consider the disciplinary case on the basis of documents,
facts and circumstances; issue a show cause notice to the contractor; allow a
personal hearing if necessary; and thereafter forward its recommendations to
the Enlistment Authority. The Enlistment Authority is then required to take a
decision based on the recommendations of the Empowered Committee.
In the present case, the High Court found that the show cause
notice had been issued by the respondent authority and not by the Empowered
Committee in the manner contemplated under Rule 13.2.
The Court further examined the proceedings of the Empowered
Committee and observed that they did not indicate that the petitioner-company
had been properly notified before the Committee reached its conclusions. The
Empowered Committee scrutinised the material placed before it, concluded that
the change of name had been intimated after 3.5 years, and recommended
disciplinary action.
The High Court found a “blatant violation of Rule 13.2”
because, before recommending suspension, the Empowered Committee had neither
properly scrutinised the petitioners’ documents nor sought relevant documents
from the enlisted contractor through the procedure mandated by the Rule.
Significantly, the Court noted that the petitioners had
produced documents showing the change of name and its intimation to the
competent authority on 2 November 2017. The Court also took note of
subsequent developments indicating departmental knowledge, including the award
of certain contracts after 2017 in the name of KNK Construction Private
Limited, rather than the former name.
The Court held that the Empowered Committee ought to have
considered all such documents. For that purpose, it was required to issue a
show cause notice to the petitioners, enabling them to produce the relevant
material and facilitating a lawful recommendation.
Court Order / Final Decision
The High Court allowed the writ petition in part.
The order dated 28 February 2022, bearing No. 007-2022
in File No. E-288/2011/ADG(SR)/383-84(H), passed by the Special Director
General, CPWD, was quashed.
The matter was remitted back to the Empowered Committee
with directions to:
- issue
a show cause notice in terms of Rule 13.2 of the CPWD Enlistment Rules,
2020;
- afford
an opportunity of personal hearing, if necessary;
- consider
the petitioners’ reply; and
- thereafter
pass appropriate orders in accordance with law.
Thus, the Court did not finally decide that the company’s
change of name was fully compliant with Rule 9.6. Instead, it invalidated the
suspension because the mandatory disciplinary procedure under Rule 13.2 had not
been followed and directed fresh consideration in accordance with law.
Important Clarification
This judgment is particularly important because it
distinguishes between an alleged substantive breach of enlistment conditions
and the mandatory procedural safeguards governing disciplinary action.
The High Court did not hold that an enlisted CPWD
contractor may freely change its corporate name without complying with Rule
9.6. Rule 9.6 expressly contemplates prior approval of the Enlistment Authority
and timely intimation of the change.
The crucial finding was that even where a contractor is
alleged to have violated Rule 9.6 or other enlistment obligations, disciplinary
action must still conform to the procedure prescribed under Rule 13.2.
The Empowered Committee cannot make unilateral adverse observations or
recommendations without following the prescribed process of consideration,
notice, opportunity to respond, and personal hearing where necessary.
The judgment further demonstrates that where the contractor
produces evidence of earlier intimation and the department’s subsequent conduct
indicates knowledge of the changed name, such material must be meaningfully
considered before imposing a serious consequence such as a two-year suspension
from CPWD tender participation.
Sections / Rules / Constitutional Provisions
Involved
Articles 226 and 227 of the Constitution of India – Writ
and supervisory jurisdiction of the High Court.
Rule 9.6, CPWD Enlistment Rules, 2020 – Change
in name of an enlisted entity; prior approval of the Enlistment Authority;
prescribed application procedure; intimation within one month; consequences of
failure.
Rule 12(c), CPWD Enlistment Rules, 2020 –
Contractor’s obligations, as referred to in the disciplinary proceedings and
recommendation.
Rule 13.2, CPWD Enlistment Rules, 2020 –
Procedure for disciplinary action; consideration by Empowered Committee;
issuance of show cause notice; personal hearing if necessary; recommendation to
Enlistment Authority.
Rule 13.3, CPWD Enlistment Rules, 2020 –
Uploading disciplinary orders on the CPWD website.
Rules 13.7(c) and 13.7(g), CPWD Enlistment Rules,
2020
– Provisions referred to in relation to proposed disciplinary action/removal
from the approved list of contractors.
Rules 15.0 and 22.0 of the Enlistment Rules, 2005,
as updated to the 2020/2021 framework – Provisions relied upon in the
impugned suspension order concerning enlistment consequences.
Clauses 4 and 5 of the Enlistment Office Order dated 24 August 2015 – Conditions invoked by the authority while ordering suspension.
Link to download the order -https://mytaxexpert.co.in/uploads/1783494340_1515compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment