Facts of the Case
The petitioner, a registered civil contractor, was
awarded the work of construction of "Sampradayam Kala Gurukulam at
Kallepalli Village" through the e-tender process pursuant to Agreement
No. 01/JNTUK/ED/Sampradayam/Srikakulam/2016-17 dated 06.02.2017.
The estimated contract value was Rs.4,51,65,521/-,
whereas the petitioner's successful bid amounted to Rs.4,07,88,892/-,
being the lowest tender.
The petitioner completed the entire work within the
extended contractual period. The competent authorities inspected the work,
verified its quality, issued a completion certificate, and accepted the
completed project.
Although substantial payments were released, the
respondents failed to release the balance amount comprising:
- Final Bill
- Further Security Deposit (FSD)
- GST Component
The total unpaid amount came to Rs.1,19,12,476/-
(later processed as Rs.1,20,69,031/-).
Repeated representations made by the petitioner failed to yield payment, compelling him to invoke the writ jurisdiction of the High Court seeking release of the admitted dues together with interest.
Issues Involved
- Whether Government authorities can indefinitely withhold admitted
contractual dues merely because funds are unavailable.
- Whether non-payment of admitted bills after completion and
acceptance of contractual work violates Articles 14 and 21 of the
Constitution.
- Whether a contractor is entitled to interest on delayed payment of admitted bills.
Petitioner's Arguments
The petitioner contended that:
- The contractual work had been fully completed.
- The work was duly inspected, certified, and accepted by the
respondents.
- The completion certificate had already been issued.
- The respondents had already released major portions of the contract
amount, thereby admitting execution of the work.
- Only the final bill, FSD, and GST component remained unpaid.
- There existed no contractual dispute regarding execution or quality
of work.
- Non-payment despite repeated requests was arbitrary, illegal, and
contrary to the contractual terms.
- The petitioner was entitled to the balance amount along with interest at 24% per annum from the date of completion of work.
Respondents' Arguments
The respondents did not dispute:
- Award of the contract.
- Completion of the work.
- Acceptance of the completed construction.
- Submission of the sixth and final bill.
Their sole defence was that:
- The balance amount could not be released because the Project
Deposit (P.D.) Account maintained for the scheme had become nil.
- A proposal had already been forwarded to the Principal Secretary
requesting release of additional funds.
- Upon receipt of funds from the Government, payment would
immediately be released to the petitioner.
- Therefore, there was no deliberate or illegal withholding by the University authorities.
Court Findings
The Andhra Pradesh High Court observed that:
- Completion of the work was never disputed.
- The respondents themselves had verified and accepted the
construction.
- The pending amount represented an admitted liability.
- Mere non-availability of Government funds could not become a valid
defence for withholding admitted contractual dues.
- Failure to release payment despite acceptance of the work amounted
to arbitrary State action.
The Court further held that:
- Withholding admitted payments payable to contractors violates the
constitutional guarantee under Articles 14 and 21.
- A contractor cannot be deprived of legitimate dues because of
internal administrative or financial difficulties of the Government.
The Court relied upon several judicial precedents,
including:
- ABL International Ltd. v. Export Credit Guarantee Corporation of
India Ltd. (2004) 3 SCC 553
- Secretary, Irrigation Department, Government of Orissa v. G.C. Roy
(AIR 1992 SC 732)
- J. Devendar Reddy v. Kakatiya University (2015 (3) ALD 97)
- S. Srinivas v. State of Andhra Pradesh (2021) 5 ALT 267
These decisions consistently recognize that delayed payment of admitted contractual dues entitles the contractor to reasonable interest as compensation.
Court Order / Decision
The High Court disposed of the writ petition with
the following directions:
- The respondents shall release the admitted amount of Rs.1,20,69,031/-
to the petitioner.
- The petitioner shall also receive interest at 12% per annum.
- Interest shall be calculated from 26.11.2018, being the date
of submission of the sixth and final bill.
- The entire payment shall be completed within eight weeks from receipt of the Court's order.
Important Clarification
This judgment reiterates the settled legal
principle that:
- Government authorities cannot avoid payment of admitted contractual
dues merely on the ground of shortage or non-availability of funds.
- Once contractual work is completed, verified, and accepted, the
contractor acquires a legal right to timely payment.
- Administrative delays and financial constraints cannot defeat
constitutional protections against arbitrary State action.
- Delayed payment of admitted dues attracts reasonable interest as
compensation.
Sections /
Provisions Involved
- Article 226 of the Constitution of India
- Article 14 of the Constitution of India
- Article 21 of the Constitution of India
- Clauses 68 & 69 of Andhra Pradesh Standard Specifications
(APSS)
- Principles governing payment of contractual dues by Government authorities.
Important Case Laws Referred
- ABL International Ltd. & Another vs Export Credit Guarantee
Corporation of India Ltd. (2004) 3 SCC 553
- Secretary, Irrigation Department, Government of Orissa vs G.C. Roy,
AIR 1992 SC 732
- J. Devendar Reddy vs Kakatiya University & Others, 2015 (3) ALD
97
- S. Srinivas vs State of Andhra Pradesh & Others, (2021) 5 ALT
267
Link
to download the order -https://www.mytaxexpert.co.in/uploads/1783941333_934compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content.The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment