Facts of the Case
The petitioner, M/s Bhanjadeo Constructions,
approached the High Court challenging the action of the State authorities in
not reimbursing the differential tax amount arising from the change in the tax
regime from VAT to GST with effect from 01.07.2017.
The principal grievance was that the introduction
of GST created an additional tax burden that had not been envisaged when the
relevant works contract agreement was originally entered into.
The Court noted that a batch of writ petitions had
been filed on the same issue concerning difficulties faced by contractors due
to the changed tax treatment of works contracts under GST.
At the Bar, it was submitted that the present writ
petition was identical to W.P.(C) No. 38490 of 2021 and could be
disposed of in terms of the order dated 14.12.2021 passed in that
matter.
The Court further considered the revised guidelines
relating to works contracts under GST issued by the Government of Odisha,
Finance Department, through Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F
dated 10.12.2018, which superseded the earlier guidelines dated 07.12.2017.
Issues
Involved
The principal issues involved were:
- Whether a works contractor could seek reimbursement or adjustment
of the differential tax burden arising from the transition from VAT to GST
with effect from 01.07.2017.
- How the amount payable should be determined where the tender was
invited before 01.07.2017 on the basis of the pre-revised SoR-2014, but
the balance work or full work was executed or paid for after implementation
of GST.
- Whether the petitioner’s grievance was required to be considered
under the revised guidelines dated 10.12.2018 issued by the Finance
Department, Government of Odisha.
- Whether the petitioner should first approach the competent
authority through a comprehensive representation for determination of the
GST-inclusive value of the balance work.
- Whether protection against coercive action should continue until
the competent authority decided the petitioner’s representation.
- Whether the present petition should be disposed of consistently
with the order dated 14.12.2021 in W.P.(C) No. 38490 of 2021, the
matter stated to be identical to the present case.
Petitioner’s
Arguments
The petitioner contended that the authorities had
failed to reimburse the differential tax amount resulting from the
change in the tax regime from VAT to GST.
The petitioner’s essential grievance was that, due
to introduction of GST, it was required to bear a tax liability that had not
been envisaged at the time of entering into the original agreement.
The petitioner relied upon the practical difficulty
faced by works contractors whose tenders and contractual rates had been
determined under the earlier tax regime but whose works continued or were paid
for after GST came into force on 01.07.2017.
It was also submitted at the Bar that the case was
identical to W.P.(C) No. 38490 of 2021, and therefore should be disposed
of in terms of the order dated 14.12.2021 passed in that matter.
Respondents’
Arguments
The State authorities placed reliance on the
revised framework issued by the Government of Odisha for dealing with works
contracts affected by the GST transition.
The Court recorded that the Government had issued
revised guidelines through the Finance Department’s Office Memorandum dated 10.12.2018,
in supersession of the earlier guidelines dated 07.12.2017.
The revised guidelines had been framed after
consideration of representations from contractors claiming additional amounts
towards GST in respect of works put to tender before 01.07.2017 but executed
partly or wholly after 01.07.2017.
The order does not separately record an elaborate
oral argument by the State beyond the revised guidelines and the submission
regarding disposal of the petition in line with the identical matter.
Therefore, no additional stand should be attributed to the respondents beyond
what is expressly reflected in the order.
Court Order
/ Findings
The High Court disposed of the writ petition with
specific directions.
The Court held that the petitioner should make a comprehensive
representation before the appropriate authority within four weeks from the
date of the order, setting out its grievance.
If such representation was filed, the competent
authority was directed to:
- consider the petitioner’s grievance in light of the revised
guidelines dated 10.12.2018 issued by the Finance Department,
Government of Odisha;
- dispose of the representation as expeditiously as possible;
- preferably decide it within three months from the date of
receipt of the certified copy of the order.
The Court further clarified that if the petitioner
remained aggrieved by the authority’s decision, it would be open to the petitioner
to challenge that decision in accordance with law.
Importantly, the High Court directed that no
coercive action should be taken against the petitioner until the authority
takes a decision.
Accordingly, the writ petition was disposed of
without the Court itself quantifying the differential tax reimbursement.
Important
Clarification
The judgment does not grant automatic
reimbursement of the entire GST differential amount merely because the
contract was entered into before 01.07.2017.
Instead, the Court directed that the petitioner’s
claim be examined under the specific computational and procedural mechanism
contained in the Odisha Government’s revised guidelines dated 10.12.2018.
This distinction is important because the revised
guidelines contemplate both possible outcomes:
- where the revised GST-inclusive value of the balance work exceeds
the original agreement value for that balance work, the contractor may be
reimbursed for the excess amount; and
- where the revised GST-inclusive value is lower than the original
agreement value, payment may be reduced, and excess payment already made
may be recovered.
Therefore, the revised mechanism is not merely a
blanket contractor-benefit scheme; it is a structured recalculation mechanism
intended to determine the appropriate contractual value after transition to
GST.
Detailed
Revised Guidelines for Works Contracts Under GST
The Court reproduced the revised guidelines dated
10.12.2018 in substantial detail. Their key features are as follows:
1. GST treatment of works contracts: GST came into force with effect from 01.07.2017 by subsuming indirect
taxes including Excise Duty, VAT, CST, Entry Tax and Service Tax. Works
contracts are treated as a composite supply of service under GST and may
be taxable at 18%, 12% or 5%, depending upon the nature of the works
contract.
2. Revision of Schedule of Rates: The State Government revised SoR-2014 with effect from
01.07.2017. Whereas the earlier SoR-2014 item rates included various embedded
taxes, the revised SoR excluded such taxes. Accordingly, estimates for
post-01.07.2017 work were to determine GST-exclusive work value first and
thereafter add GST at the applicable rate.
3. Tax invoice requirement: A works contractor under GST is required to issue a tax invoice
separately showing:
- taxable work value; and
- GST comprising CGST and SGST.
4. Pre-GST tenders with post-GST execution/payment: Where the tender was invited before 01.07.2017 on the basis of SoR-2014
but payment for balance work or full work arose after GST implementation, the
prescribed procedure was to be followed.
5. Identification of balance work: Item-wise quantities of work completed after 30.06.2017 were required
to be identified, and their value under the original agreement based on
pre-revised SoR-2014 had to be ascertained.
6. Revised estimated work value: The revised estimated value of the balance work was to be determined
according to Revised SoR-2014.
7. Items not covered by Revised SoR-2014: Where rates of goods or services were not covered, the tax-exclusive basic
value had to be determined by removing embedded incidences of VAT, Entry Tax,
Excise Duty, Service Tax and other relevant taxes from the estimated or quoted
price.
8. Tender premium or discount: The revised estimated value of the balance work was to be enhanced or
reduced in the same proportion as the applicable tender premium or discount.
9. Addition of GST: Applicable GST at 5%, 12% or 18%, as the case may be, was then
to be added to determine the GST-inclusive work value of the balance work.
10. Supplementary agreement: A supplementary agreement was required to be signed with the contractor
for the revised GST-inclusive value of the balance work.
11. Reimbursement where revised value is higher: If the revised GST-inclusive value exceeded the original agreement
value of the balance work, the contractor was to be reimbursed for the excess.
12. Reduction or recovery where revised value is
lower: If the revised GST-inclusive value was lower than
the original agreement value, payment was to be reduced accordingly. Where
excess payment had already been made, the excess amount was liable to be
recovered.
13. Applicability to different contract modes: The procedure was made applicable to all works contracts, including EPC,
Turn-key and Lumpsum contracts.
14. F2 contracts: For F2
contracts, the taxable value under GST for each item of balance work was to be
determined by the competent authority after applying the premium or discount
offered by the contractor on the respective item.
Sections /
Statutory and Administrative Provisions Involved
The order primarily concerns the following legal
and administrative framework:
- Goods and Services Tax regime effective from 01.07.2017
- Works contract treated as composite supply of service under GST
- Applicable GST rates of 5%, 12% or 18%, depending upon the nature
of the works contract
- Odisha Finance Department Guidelines dated 07.12.2017
- Revised Guidelines dated 10.12.2018
- Office Memorandum No. FIN-CTI-TAX-0045-2017/38535/F dated
10.12.2018
- Revised Schedule of Rates-2014
- Works Department OM No. 13827/WD dated 16.09.2017, effective from
01.07.2017
- Pre-GST works contracts executed partly or wholly after 01.07.2017
- Mechanism for determination of GST-inclusive balance work value
- Supplementary agreement requirement
- Reimbursement, reduction and recovery mechanism under the revised guidelines
Link to download the order - https://mytaxexpert.co.in/uploads/1783329611_1121compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment