Facts of the Case
Ram Kripal Singh Construction Pvt. Ltd., the
petitioner, filed a petition under Section 11 of the Arbitration and
Conciliation Act, 1996 seeking appointment of an arbitrator for
adjudication of disputes arising from a Letter of Award dated 17 December
2010 concerning the setting-up of a township for NTPC’s Super Thermal Power
Project at Barh, Bihar. The Letter of Award culminated in a Contract
Agreement dated 1 February 2011 between the parties.
The contractual relationship was governed by the
General Conditions of Contract. Clause 56 contained the arbitration
agreement and contemplated reference of disputes to the sole arbitration of the
General Manager of NTPC; if the General Manager was unable or unwilling to act,
arbitration was to be conducted by another person appointed by the Chairman and
Managing Director of NTPC. The clause further stipulated that no person other
than a person appointed by the CMD, NTPC should act as arbitrator and that, if
such appointment was not possible, the matter would not be referred to
arbitration at all.
The petitioner contended that after insertion of Section
12(5) through the Arbitration and Conciliation (Amendment) Act, 2015, the
contractual procedure permitting NTPC’s own officer or its CMD to control the
appointment of the arbitrator had become legally invalid and unenforceable.
Earlier disputes had been invoked through a notice
dated 27 January 2014, and those arbitral proceedings were terminated by
the sole arbitrator on 22 June 2016. The petitioner stated that the
project remained ongoing and further disputes subsequently arose. Accordingly,
a second invocation notice dated 29 September 2020 was issued concerning
later claims, including non-handing over of work fronts, non-supply of approved
working drawings, changes in specifications, claims arising from changes in law
including introduction of GST and labour-law changes, and alleged breaches of
contractual provisions.
The petitioner therefore approached the Delhi High
Court for appointment of a neutral and independent arbitrator.
Issues
Involved
The principal issues before the Court were:
- Whether the arbitration agreement itself became invalid or
inoperative because the agreed procedure for appointment of the arbitrator
became legally unenforceable after insertion of Section 12(5) of the
Arbitration and Conciliation Act, 1996.
- Whether the invalid appointment mechanism could be severed from the
substantive agreement between the parties to refer disputes to
arbitration.
- Whether a clause stipulating that disputes would not be referred to
arbitration if the CMD, NTPC could not appoint the arbitrator prevented
the Court from appointing an independent arbitrator under Section 11(6).
- Whether the petitioner’s claims were ex facie time-barred and
therefore incapable of reference to arbitration.
- Whether the second notice invoking arbitration dated 29 September
2020 constituted a valid invocation despite the respondent’s objection
that it did not quantify and detail the claims.
- Whether questions of limitation, involving disputed facts and
subsequent claims arising during an ongoing project, should be determined
by the arbitral tribunal rather than finally adjudicated at the Section 11
stage.
Petitioner’s
Arguments
The petitioner argued that Clause 56 constituted
a valid arbitration agreement, but the portion authorising the General
Manager of NTPC or another person appointed by the CMD, NTPC to act as sole
arbitrator had become inoperative and invalid in view of Section 12(5)
of the Act.
It was submitted that a person who was legally
ineligible to act as arbitrator could not nominate another arbitrator. The
petitioner placed particular reliance on the principles laid down in:
- TRF Ltd. vs Energo Engineering Projects Ltd.
- Bharat Broadband Network Ltd. vs United Telecoms Ltd.
- Perkins Eastman Architects DPC & Anr. vs HSCC (India) Ltd.
The petitioner argued that the contractual
stipulation stating that no person other than an appointee of the CMD, NTPC
could act as arbitrator, and that there would be no arbitration if such appointment
became impossible, was also illegal and incapable of defeating the substantive
agreement to arbitrate.
Reliance was also placed on T.K. Engineering
Consortium Pvt. Ltd. vs Director (Project), RITES Ltd. & Anr. and ARSS
Infrastructure Pvt. Ltd. vs IRCON International Ltd. & Anr., where
independent arbitrators were appointed after the contractual appointment
mechanism became legally impermissible.
On limitation, the petitioner submitted that the
second invocation notice dated 29 September 2020 concerned subsequent
disputes and claims arising after the earlier invocation dated 27 January 2014.
Since the project was still ongoing, later causes of action had arisen, even
where certain claims fell under similar broad heads.
The petitioner therefore sought appointment of a
neutral arbitrator by the Court under Section 11(6).
Respondent’s
Arguments
NTPC opposed the petition and argued that
arbitration is fundamentally based upon party consent. According to
NTPC, Clause 56 specifically provided that only:
- the General Manager of NTPC; or
- another person appointed by the CMD, NTPC
could act as arbitrator.
The respondent emphasised the contractual
stipulation that no person other than an appointee of the CMD, NTPC could
act as arbitrator, and if such appointment was not possible, the matter
was not to be referred to arbitration at all.
NTPC argued that, following Section 12(5) and the
decisions in TRF Ltd. and Perkins Eastman, if the agreed
appointees became ineligible, the appointment procedure became impossible to perform
and the arbitration agreement itself could not survive.
The respondent further contended that the Court
could not sever the appointment procedure from the remainder of Clause 56
because the agreement to arbitrate and the agreed identity or method of
appointment of the arbitrator formed part of the same consensual arrangement.
A further objection was raised that the claims were
ex facie time-barred, allegedly relating to 2014 while arbitration was
invoked through the notice dated 29 September 2020. Reliance was placed on Bharat
Sanchar Nigam Ltd. & Anr. vs Nortel Networks India Pvt. Ltd.
NTPC also argued that the second invocation notice
did not specify the exact quantum of disputes and claims and therefore did not
satisfy the contractual requirements for valid invocation.
Court Order
/ Findings
The Delhi High Court allowed the petition
and held that a valid and subsisting arbitration agreement continued to
exist between the parties, notwithstanding the invalidity of the
contractual procedure for appointment of the arbitrator.
1. Invalid
Appointment Procedure Does Not Destroy the Arbitration Agreement
The Court held that merely because the agreed
appointment mechanism had become invalid or unenforceable due to:
- insertion of Section 12(5); and
- the Supreme Court decisions in TRF Ltd. and Perkins
Eastman,
the entire arbitration clause did not become
invalid or void.
The Court observed that similar clauses had already
been considered by Coordinate Benches of the Delhi High Court, which
consistently held that invalidity of the appointment procedure does not
extinguish the substantive agreement to arbitrate.
2.
Appointment Mechanism Is Distinct and Severable from Core Consent to Arbitrate
A major finding of the judgment is that an
arbitration clause may contain several separate elements, including:
- procedure for appointment of arbitrators;
- seat or venue of arbitration;
- substantive and procedural law;
- excepted matters;
- allocation of costs; and
- other procedural features.
The Court held that these are different strands of
the agreed arbitral mechanism and are distinct from the core arbitration
agreement, namely, the primary consent of parties to refer their disputes
to arbitration.
Accordingly, the procedure for appointment of an
arbitrator is distinct and separable from the agreement to arbitrate,
even when both are contained in the same clause.
3. “My Way
or the Highway” Approach Rejected
The Court expressly rejected the proposition that
if NTPC’s own contractual appointment mechanism could not operate, there could
be no arbitration at all.
The Court characterised such an approach as a “my
way or the highway” approach and held it untenable in law.
Where a portion of the arbitration agreement
becomes invalid, void or unenforceable because of changes in law or binding
judicial interpretation, that defective portion must be severed or excised,
while preserving the valid remainder of the arbitration agreement.
4. CMD, NTPC
Appointment Procedure Severed
The Court concluded that the arbitration agreement
remained valid and subsisting, but the procedure permitting appointment of the
arbitrator at the hands of the CMD, NTPC was no longer valid and
therefore had to be severed from the remaining arbitration clause.
5.
Limitation Objection Left to Arbitrator
On NTPC’s plea that the claims were time-barred,
the Court examined the second invocation notice dated 29 September 2020 and
noted the petitioner’s case that further disputes had arisen after the earlier
invocation while the work remained ongoing.
The Court applied the principle that unless claims
are ex facie time-barred, courts should lean in favour of reference to
arbitration — the principle described as “when in doubt, do refer.”
Accordingly, the limitation objection did not prevent
appointment of an arbitrator. The issue of limitation was left open for
determination by the arbitrator as a mixed question of fact and law.
6. Sole
Arbitrator Appointed
The Court appointed a former Judge of the Supreme
Court of India as the learned Sole Arbitrator to adjudicate the disputes
between the parties.
The appointment was made subject to requisite
disclosures under Section 12 of the Arbitration and Conciliation Act, 1996.
The Court further directed that:
- the arbitrator’s fee would be governed by the Fourth Schedule
or as otherwise agreed;
- the parties would share the arbitrator’s fee and arbitral costs
equally;
- all rights and contentions concerning claims and counterclaims
would remain open;
- disputes would be decided on their own merits in accordance with
law; and
- the parties were to approach the appointed arbitrator within 10
days.
The petition was accordingly disposed of.
Important
Clarification
The most important legal clarification emerging
from this judgment is:
The invalidity of a unilateral or legally
impermissible arbitrator-appointment mechanism does not automatically
invalidate the parties’ substantive agreement to arbitrate.
The Court drew a clear legal distinction between:
(a) Core consent to arbitration — the parties’ agreement that disputes will be resolved through
arbitration; and
(b) Appointment procedure — the contractual machinery identifying who will appoint or act as
arbitrator.
If the appointment mechanism becomes invalid due to
Section 12(5) or binding judicial decisions, the invalid portion can be
severed while preserving the substantive arbitration agreement.
The judgment also clarifies that a contractual
clause cannot necessarily defeat arbitration merely by declaring that if one
party’s chosen appointment mechanism fails, there shall be “no arbitration
at all.” Where the core agreement to arbitrate remains ascertainable and
valid, the Court may preserve that agreement and appoint an independent
arbitrator.
Further, at the Section 11 stage, a limitation
objection should ordinarily not prevent reference unless the claims are
demonstrably and ex facie dead or time-barred. Where limitation depends
on subsequent claims, continuing work, later causes of action, or disputed
facts, the arbitral tribunal may decide the issue.
Sections
Involved
Section 11 of the Arbitration and Conciliation Act,
1996 — Appointment of arbitrators.
Section 11(6) — Court
intervention where the agreed appointment procedure fails or becomes incapable
of lawful implementation.
Section 12 — Grounds
for challenge and mandatory disclosures concerning independence and
impartiality of arbitrators.
Section 12(5) — Statutory
ineligibility of persons falling within specified relationships and
circumstances, notwithstanding prior contractual agreement, subject to the
statutory waiver requirement.
Section 21 —
Commencement of arbitral proceedings.
Section 25 —
Consequences of default by a party in arbitral proceedings.
Fourth Schedule — Framework
concerning arbitrators’ fees.
Seventh Schedule — Categories relevant to arbitrator ineligibility under Section 12(5).
Link to download the order - https://mytaxexpert.co.in/uploads/1783330176_1124compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment