Facts of the Case
The appellant, P. Shyam Raju, proprietor of
Skilderz Developers, participated in a tender floated by Kerala Minerals and
Metals Limited (“KMML”) for work similar to an ongoing work already being
executed by him. Under the tender conditions, the bidder was required to
satisfy the prescribed solvency requirement and submit the requisite solvency
certificate within the stipulated time.
According to the appellant, while submitting his
tender, he produced a solvency certificate for Rs. 1.50 crore instead of the
required amount, which he claimed occurred due to an inadvertent omission.
After detecting the mistake, he subsequently furnished a solvency
certificate for Rs. 2 crore through a separate letter. However, KMML
declined to consider the subsequently furnished certificate.
The appellant contended that his quoted rate was Rs.
314 per MT plus GST, whereas the competing bidder, M/s Deepthi Transport
Service, quoted Rs. 369 per MT plus GST. He alleged that rejection of
his bid and acceptance of the remaining bid would cause substantial financial
loss to KMML.
The appellant further challenged the tender process
on the basis of the CVC Guidelines relating to single bids, alleging
that the tender conditions were stringent and restrictive, that insufficient
time had been granted for submission of bids, and that acceptance of the higher
bid would cause substantial financial loss.
The writ petitions challenging the tender process
were dismissed by the learned Single Judge. Aggrieved by those judgments, the
appellant filed W.A. Nos. 1380 and 1396 of 2022 before the Division Bench.
Issues
Involved
The principal issues before the High Court were:
- Whether the appellant’s belated submission of the requisite
solvency certificate could be accepted after expiry of the deadline
prescribed under the tender conditions.
- Whether KMML was justified in disqualifying the appellant
for failure to submit the required solvency certificate within the
prescribed period.
- Whether the tender conditions could be relaxed or altered in favour
of the appellant when the prescribed eligibility document was submitted
late.
- Whether the alleged higher price of the remaining bid and the
appellant’s reliance on Clause 5.6.7 of the CVC Guidelines concerning
single bids justified cancellation and re-tendering.
- Whether the tender process was vitiated by alleged arbitrariness,
restrictive conditions, mala fides, bias, or violation of CVC Guidelines.
- Whether the Division Bench should interfere with the judgments of
the learned Single Judge dismissing the writ petitions.
Petitioner’s
/ Appellant’s Arguments
The appellant argued that the initial submission of
a lower-value solvency certificate was an inadvertent mistake and that,
immediately after discovering the error, he furnished a Rs. 2 crore solvency
certificate. According to him, KMML ought to have considered the
substituted certificate instead of rejecting his bid on a technical ground.
It was contended that the appellant had quoted Rs.
314/MT plus GST, whereas M/s Deepthi Transport Service had quoted Rs.
369/MT plus GST. The appellant asserted that acceptance of the higher bid
would result in an estimated loss of approximately Rs. 55 lakh to KMML
and that the loss could increase depending upon the additional quantity of
material to be removed.
The appellant relied upon the CVC Guidelines
concerning single bids, particularly the contention based on Clause 5.6.7,
to argue that where the price in a single bid is unreasonable compared with
market value, cancellation and re-tendering may be resorted to.
He further argued that:
- only 7 days were granted for submission of bids, whereas an
earlier tender had allegedly allowed 21 days;
- the solvency requirement was unduly stringent and restrictive;
- the higher solvency requirement had the effect of restricting
competition;
- in earlier tenders, shortfall notices had allegedly been issued to
bidders for submission of insufficient or defective documents, including
solvency certificates;
- refusal to provide a similar opportunity in the present tender
demonstrated alleged mala fides and bias;
- rejection of his lower bid on a technical ground and continuation
with the remaining higher bid violated the CVC Guidelines and caused
avoidable financial loss.
The appellant also alleged that the tender process
had been manipulated to accommodate the remaining bidder by excluding other
bidders on technical grounds.
Respondents’
Arguments
On behalf of the successful/remaining bidder, M/s
Deepthi Transport Service, it was submitted that the work had already commenced
and that a substantial portion of the sand had already been removed. It was
therefore contended that the contract had already been executed in accordance
with the tender conditions and performance had begun.
The respondents’ position, as reflected in the
proceedings and accepted by the Court, was that compliance with the prescribed
tender conditions was mandatory. The appellant’s own Senior Counsel fairly
acknowledged that the last date fixed for submission of the solvency
certificate was 12 August 2022, whereas the appellant submitted the
requisite certificate only on 17 August 2022.
Accordingly, the central question was whether a
solvency certificate submitted after the stipulated deadline could be accepted
despite the express tender conditions.
Court Order
/ Findings
The Division Bench found that the required solvency
certificate had admittedly been submitted beyond the period prescribed in
the tender.
The High Court laid down the crucial principle
that:
Tender conditions cannot be altered unless and
until they are per se illegal.
The Court observed that, prima facie, there was no
reason to hold the relevant tender condition illegal. Since the tender
conditions required the solvency certificate to be submitted before the last
date fixed, failure to comply with that requirement justified disqualification.
The Court therefore sustained the decision on
the aspect of disqualification.
Consequently:
- W.A. No. 1396 of 2022 was dismissed;
- W.A. No. 1380 of 2022 was also dismissed;
- the Division Bench declined to interfere with the impugned
judgments of the learned Single Judge.
Thus, despite the appellant’s arguments regarding a
lower quoted price, alleged financial loss, single-bid concerns, restrictive
conditions, and CVC Guidelines, the decisive factor remained the appellant’s
admitted failure to submit the prescribed solvency certificate within the
tender deadline.
Important
Clarification
The judgment is important because it distinguishes
between:
(a) a challenge to an allegedly illegal tender
condition, and
(b) a request to relax a valid tender condition after a bidder has failed to
comply with it.
The Court did not hold that tender
conditions can never be judicially examined. Rather, it held that tender
conditions cannot be altered unless they are shown to be per se illegal.
In the present case, the Court found no prima facie basis to invalidate the
requirement that the solvency certificate be submitted before the prescribed
last date.
Another important clarification is that a bidder’s lower
financial quotation does not automatically cure non-compliance with a mandatory
tender requirement. The appellant’s claim that his bid was financially more
advantageous did not override his admitted late submission of the requisite
solvency certificate.
Further, although the appellant relied upon the CVC
Guidelines on single bids and argued that acceptance of the remaining
higher bid would cause financial loss, the Court sustained the disqualification
because the appellant had failed to satisfy the tender requirement within time.
The judgment therefore reinforces that courts ordinarily
will not rewrite tender conditions merely to accommodate a bidder who submits a
mandatory eligibility document after the deadline, unless the condition itself
is shown to be legally unsustainable.
Sections /
Provisions / Clauses Involved
Article 226 of the Constitution of India — writ jurisdiction invoked in challenging the tender process and
seeking writs including mandamus and certiorari.
Clause 4.3 of the Tender Notice — prescribed the minimum solvency requirement and stipulated that the
solvency certificate must comply with the stated conditions, including its
validity/date and issuance requirements.
Clause 5.6.7 of the CVC Guidelines — relied upon by the appellant in relation to treatment of a single bid
and the contention that re-tendering could be considered where prices were
allegedly unreasonable compared with market value.
Central Vigilance Commission Guidelines / Central
Vigilance Manual — relied upon by the appellant to challenge
continuation of the tender process with the remaining bid.
General principles of judicial review in public tenders — particularly the principle that tender conditions should not be altered unless shown to be per se illegal and that compliance with prescribed tender requirements is material to bidder eligibility.
Link to download the order - https://mytaxexpert.co.in/uploads/1783333702_1134compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment