Facts of the Case
The appellant, P. Shyam Raju, proprietor of Skilderz
Developers, participated in a tender floated by Kerala Minerals and Metals
Limited for work similar to an ongoing work already being executed by him.
According to the appellant, while submitting the
tender documents, he furnished a solvency certificate for Rs.1.50 crore
instead of the required amount of Rs.1.85 crore, allegedly due to an
inadvertent omission. The appellant subsequently furnished a solvency
certificate for Rs.2 crore after detecting the mistake and requested
that the same be considered.
The respondents declined to accept the subsequently
furnished certificate. The appellant alleged that this refusal effectively left
only one tenderer in the field and facilitated award of the work to the
remaining bidder.
The appellant asserted that his quoted rate was Rs.314
per MT plus GST, whereas M/s Deepthi Transport Service quoted Rs.369 per
MT plus GST. He also contended that his ongoing similar work was being
performed at Rs.324 per MT plus GST.
The appellant challenged the tender process through
W.P.(C) Nos. 27223 and 28351 of 2022, seeking, among other reliefs,
cancellation of the tender and a direction for re-tendering. The learned Single
Judge declined relief and dismissed the writ petitions. The appellant therefore
filed W.A. Nos. 1380 and 1396 of 2022.
Issues
Involved
The principal issues before the Division Bench
were:
- Whether the appellant’s belatedly submitted solvency certificate
could be accepted despite expiry of the deadline fixed under the tender
conditions.
- Whether the tender authority was justified in disqualifying the
appellant for failure to furnish the required solvency certificate within
the prescribed time.
- Whether the tender conditions could be relaxed or altered in favour
of the appellant.
- Whether the alleged higher financial quote of the remaining single
bidder justified cancellation and re-tendering under the CVC Guidelines.
- Whether the alleged financial loss to Kerala Minerals and Metals
Limited warranted judicial interference with the tender process.
- Whether the tender conditions, particularly the solvency
requirement, were illegal, arbitrary, unduly restrictive or liable to be
interfered with in writ jurisdiction.
- Whether the learned Single Judge erred in refusing to cancel the
tender and direct a re-tender.
Appellant / Petitioner’s
Arguments
The appellant contended that he had participated in
the tender floated by Kerala Minerals and Metals Limited and was already
executing similar ongoing work.
According to him, the furnishing of a solvency
certificate for Rs.1.50 crore instead of Rs.1.85 crore was merely an
inadvertent omission. After discovering the mistake, he furnished a fresh
solvency certificate for Rs.2 crore, but the respondents refused to
consider it.
The appellant alleged that the rejection was
intended to facilitate award of the tender to the remaining sole bidder.
Argument on
Comparative Rates
The appellant emphasized that:
- his quoted rate was Rs.314/MT + GST;
- the third respondent’s quoted rate was Rs.369/MT + GST; and
- his ongoing similar work was being executed at Rs.324/MT + GST.
According to the appellant, acceptance of the
higher bid would cause substantial financial loss to Kerala Minerals and Metals
Limited. He estimated a loss of approximately Rs.55 lakh, with the
possibility of the financial impact increasing if additional quantities were
involved.
Argument
Based on CVC Guidelines
The appellant relied on the CVC Guidelines relating
to a single bid. He contended that under Clause 5.6.7 of the guidelines, where
the price in a single-bid situation is unreasonable compared with market value,
the tender can be cancelled and the work re-tendered.
The appellant argued that re-tendering was
justified because:
- only a short period of seven days was allegedly granted for
submission of bids, whereas an earlier tender had allowed 21 days;
- the solvency condition was allegedly stringent and restrictive;
- despite reduction in the quantity of work, the solvency requirement
had allegedly been increased;
- acceptance of the remaining higher bid would cause substantial
financial loss; and
- the tender process allegedly violated the CVC Guidelines.
Argument on
Prior Tender Practice
The appellant further contended that in earlier
tenders, shortfall notices had been issued to tenderers for submission of
insufficient or defective documents, including solvency certificates.
According to him, refusal to follow a similar
procedure in the present tender demonstrated arbitrariness, mala fides and
bias.
Allegation
of Manipulation
The appellant alleged that the tender process had
been manipulated to exclude him and another bidder on technical grounds and to
accommodate the remaining bidder.
Respondents’
Arguments
On behalf of M/s Deepthi Transport Service, the
third respondent in W.A. No. 1380 of 2022, it was submitted that:
- the work had already commenced;
- a substantial portion of the sand had already been removed;
- the contract had been executed in accordance with the tender
conditions; and
- interference at that stage was therefore unwarranted.
It was also recorded during the proceedings that
the work had commenced from 06.09.2022.
The respondents’ position was effectively that the
appellant had failed to comply with the prescribed tender condition concerning
timely submission of the required solvency certificate and that the completed
tender process should not be disturbed.
Court Order
/ Findings
The Division Bench recorded a significant factual
admission by the learned Senior Counsel appearing for the appellant:
- the last date fixed for submission of the solvency certificate was 12.08.2022;
and
- the appellant submitted the certificate only on 17.08.2022.
Therefore, the central issue became whether a
solvency certificate submitted after the stipulated deadline was required to be
accepted.
The High Court found that the solvency certificate
required under the tender conditions had admittedly been submitted beyond
the prescribed period.
The Court held that:
Tender conditions cannot be altered unless and
until they are per se illegal.
The Division Bench further observed that, prima
facie, it found no reason to hold the relevant tender condition illegal.
Since the tender conditions required the solvency
certificate to be submitted before the last date fixed, and the appellant had
admittedly submitted it after the deadline, the Court sustained the decision
on disqualification.
Accordingly:
- W.A. No. 1396 of 2022 was dismissed; and
- W.A. No. 1380 of 2022 was also dismissed.
The Division Bench declined to interfere with the
judgments of the learned Single Judge.
Important
Clarification
The decisive basis of the judgment was the
appellant’s admitted failure to submit the required solvency certificate within
the time prescribed by the tender.
The High Court did not hold that every
tender condition is immune from judicial review. Instead, the Court expressly
stated that tender conditions cannot be altered unless and until they are
per se illegal.
Therefore, the judgment must be understood to mean
that:
- a bidder cannot ordinarily insist upon post-deadline relaxation of
a prescribed tender requirement;
- courts will not rewrite or alter tender conditions merely because
subsequent compliance is offered;
- where a condition is shown to be per se illegal, a different
question may arise; but
- in the present case, the Court found no prima facie reason to treat
the solvency requirement as illegal.
The Court also did not accept the appellant’s reliance on alleged financial loss, comparative lower pricing or the CVC single-bid guidelines as sufficient grounds to overcome the admitted belated submission of the mandatory solvency certificate.
Link to download the order -
https://mytaxexpert.co.in/uploads/1783334640_1140compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment