Facts of the
Case
Chemmanur Fashion Jewellers was the successful
bidder in a tender-cum-auction conducted by the Cochin Port Trust for allotment
of a Tourist Jetty with allied structures and nearby open area at Willingdon
Island on a licence basis for a period of five years.
The allotment order was issued to the petitioner on
19 October 2020. Before issuance of the allotment order, the petitioner
had paid:
- ₹9,90,000 as Security Deposit; and
- ₹1,65,000 plus GST as licence fee for the first month.
Under Clause 2.9 of the Bid Document, the
licensee was required to take over the licensed premises within 30 days of
allotment and commence payment of licence fee from the date of takeover.
According to the petitioner, immediate steps were
taken to commence construction. However, the Cochin Port Trust required the
petitioner to obtain all necessary clearances before beginning construction
activities.
The petitioner relied upon correspondence exchanged
between the parties to contend that it had acted in accordance with the
allotment conditions and that the delay was attributable to the Cochin Port
Trust.
The dispute became more serious when the CRZ
Authorities allegedly took the position that no construction was possible at
the allotted site. Faced with this obstacle, the petitioner issued Ext.
P10 letter dated 13 October 2021, terminating the contract.
Thereafter, the Cochin Port Trust issued Ext.
P11 letter, calling upon the petitioner to show cause why the licence
should not be terminated and the allotment cancelled. The proposed cancellation
was stated to be based on the petitioner’s alleged default in commencing
activities in accordance with the tender notice.
Aggrieved by this action and the dispute concerning
licence fee liability, the petitioner approached the Kerala High Court.
Issues Involved
The principal issues arising in the matter were:
- Whether the petitioner could be held liable to pay licence fee from
the date of takeover when the alleged delay in commencing activities was
claimed to be attributable to circumstances beyond the petitioner’s
control.
- Whether the delay in commencement of construction and project
activities was attributable to the petitioner or to the Cochin Port Trust
and regulatory clearance requirements.
- Whether the alleged stand of the CRZ Authorities that construction
was not possible at the allotted site materially affected the petitioner’s
contractual obligations.
- Whether the Cochin Port Trust was justified in insisting upon
strict compliance with the terms of allotment without granting relaxation.
- Whether the writ court could conclusively adjudicate the disputed
contractual and factual questions when their resolution required oral and
documentary evidence.
- Whether the impact of the COVID-19 pandemic and lockdown should be
considered while quantifying any claim for licence fee.
- Whether the petitioner should vacate the licensed premises
following termination of the licence and contract.
Petitioner’s
Arguments
The petitioner contended that it had acted in
accordance with the allotment and had taken immediate steps to commence
construction.
It was argued that the delay was not
attributable to the petitioner. According to the petitioner, the Cochin
Port Trust itself required necessary clearances to be obtained before
construction could commence.
The petitioner relied upon the correspondence
exchanged between the parties to demonstrate that it had acted pursuant to the
allotment and that the delay had occurred on the side of the Cochin Port Trust
or because of circumstances connected with necessary approvals.
The petitioner further relied on the alleged stand
of the CRZ Authorities that no construction was possible at the allotted
site, treating the same as an insurmountable hurdle to implementation of
the project.
Consequently, the petitioner issued the letter
dated 13 October 2021 terminating the contract.
On the issue of licence fee, the petitioner
specifically contended that it was not liable to pay licence fee from the
date of takeover, because the delay was not in any manner attributable to
it.
Regarding possession of the premises, the
petitioner submitted before the Court that it had expressed willingness to
vacate the premises long ago and, the licence having been terminated, it had no
intention of continuing in occupation.
Respondents’
Arguments
The Cochin Port Trust maintained that the
petitioner was bound by the terms of the allotment and that no
relaxation could be granted under any circumstances.
Its position was that the contractual and tender
conditions governed the parties’ obligations, including the petitioner’s
obligations concerning takeover, commencement of activities and payment of
licence fee.
The Port Trust’s show-cause action proceeded on the
allegation that the petitioner had defaulted in commencing activities in terms
of the tender notice.
The Cochin Port Trust also filed an interlocutory
application seeking a direction requiring the petitioner to immediately vacate
the licensed premises.
Court Order
/ Findings
The Kerala High Court observed that, from the
pleadings and arguments, it was evident that resolution of the dispute required
adduction of evidence, both oral and documentary.
The Court therefore did not undertake a final
adjudication of the disputed questions regarding responsibility for delay or
the ultimate licence fee liability in the writ proceedings.
Importantly, the Court expressed the opinion that
the Cochin Port Trust should adopt a practical approach, taking into
account the impact of the COVID-19 pandemic and lockdown.
However, the Court refrained from issuing any
specific direction because the parties had other efficacious remedies
available to them.
The Court further clarified that, while
quantifying the claim for licence fee, all relevant aspects should be taken
into account.
As regards possession, the Court recorded the
petitioner’s submission that:
- the petitioner had expressed willingness to vacate the premises
long ago;
- the licence had been terminated; and
- the petitioner had no intention to continue occupying the premises.
Accordingly, the writ petition was closed,
while reserving the right of the parties to resort to appropriate remedies
available to them.
Important
Clarification
This judgment does not declare that the
petitioner is automatically exempt from payment of the licence fee.
It also does not finally determine that the
Cochin Port Trust alone was responsible for the delay.
The Court’s crucial finding was that the dispute
involved contested factual questions requiring oral and documentary evidence,
making final resolution inappropriate in the writ proceedings.
At the same time, the Court made an important
observation that the Cochin Port Trust should take a practical approach
considering the impact of the COVID-19 pandemic and lockdown.
Further, while quantifying any licence fee claim, all
relevant aspects must be considered. This observation is significant
because it indicates that licence fee quantification should not be approached
mechanically without considering the surrounding circumstances relevant to the
dispute.
The Court ultimately left the parties free to
pursue their respective claims and defences through appropriate efficacious
remedies.
Section /
Clause Involved
Clause 2.9 of the Bid Document – The licensee was bound to take over the licensed premises within 30
days of allotment and was required to commence payment of licence fee from the
date of takeover.
Constitutional Writ Jurisdiction – The matter was instituted as a civil writ petition before the Kerala
High Court. The judgment’s central procedural significance lies in the Court
declining to conclusively determine disputed contractual questions requiring
oral and documentary evidence and reserving appropriate remedies to the
parties.
Tender and Licence Conditions – The dispute concerned contractual obligations arising from the
tender-cum-auction, allotment order, licence arrangement, commencement of
activities and liability for licence fee.
CRZ Clearance / Regulatory Restrictions – The petitioner relied upon the alleged position of CRZ Authorities that construction was not possible at the allotted site as a material circumstance affecting performance of the contract.
Link to
download the order -
https://mytaxexpert.co.in/uploads/1783334792_1141compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment