Facts of the Case
The petitioner, M/s. Bhanjadeo Constructions,
filed a writ petition before the Odisha High Court challenging the action of
the State Government in refusing to reimburse the differential tax liability
arising due to the transition from the Value Added Tax (VAT) regime to the
Goods and Services Tax (GST) regime with effect from 1 July 2017.
The petitioner contended that the works contract
had been awarded before the implementation of GST, whereas a substantial
portion of the work was executed after GST came into force. Consequently, the
petitioner was required to bear an additional tax burden that had not been
contemplated at the time of entering into the contract.
Issues Involved
- Whether a contractor executing a pre-GST works contract is entitled
to reimbursement of the additional GST liability arising after
implementation of GST.
- Whether the State Government is required to determine the
differential tax liability in accordance with the revised GST guidelines
issued by the Finance Department.
- Whether the authorities should consider the contractor's grievance
through a reasoned decision before taking coercive action.
Petitioner's Arguments
- The works contract was awarded before the introduction of GST.
- GST resulted in an additional tax burden which was never
contemplated while submitting the tender.
- The Government failed to reimburse the excess GST payable despite
the issuance of revised guidelines dealing with pre-GST works contracts.
- The petitioner sought reimbursement of the differential GST amount
incurred because of the statutory change in the indirect tax regime.
Respondent's Arguments
The State relied upon the Revised Guidelines
relating to Works Contract under GST issued by the Finance Department,
Government of Odisha through Office Memorandum dated 10 December 2018.
The revised guidelines prescribed the methodology
for determining the GST-inclusive value of works executed after 1 July 2017
where tenders had been invited prior to GST. The guidelines also provided for
reimbursement of the excess amount wherever the revised GST-inclusive value
exceeded the original contract value and reduction/recovery wherever the
revised value was lower.
Court Order / Findings
The Odisha High Court observed that identical
issues had already been considered in an earlier writ petition.
The Court directed the petitioner to submit a
comprehensive representation before the competent authority within four weeks.
The authority was directed to examine and dispose of the representation
strictly in accordance with the Finance Department's Revised Guidelines
dated 10 December 2018, preferably within three months.
The Court further held that:
- The petitioner would remain free to challenge the decision if
aggrieved.
- No coercive action should be taken against the petitioner until the
competent authority decides the representation.
Accordingly, the writ petition was disposed of with
the above directions.
Important Clarification
- Contractors executing works contracts awarded before 1 July 2017
but performed wholly or partly after GST implementation may seek
determination of the revised GST-inclusive contract value under the
Government's revised guidelines.
- The competent authority must examine such claims by following the
prescribed calculation methodology.
- Reimbursement is permissible where the revised GST-inclusive value
exceeds the original agreement value.
- If the revised value is lower, the excess amount already paid may
be recovered.
- The Court emphasized that authorities should first decide the
contractor's representation before initiating coercive action.
Key Takeaway
The Odisha High Court reaffirmed that disputes relating to additional GST liability on pre-GST government works contracts should be resolved in accordance with the Government's revised GST guidelines. Instead of granting direct reimbursement through a writ, the Court directed the competent authority to determine the contractor's entitlement by applying the statutory methodology prescribed under the revised guidelines.
Sections /
Subject Involved
- Goods and Services Tax (GST)
- Works Contract
- Transition from VAT to GST
- Reimbursement of Differential GST
- Government Contracts
- Article 226 of the Constitution of India (Writ Jurisdiction)
Link to Download the Order https://www.mytaxexpert.co.in/uploads/1784530633_1012compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.