Facts of the Case
The petitioner, Unicon Builders and Contractors,
participated in the tendering process for two works bearing Package Nos.
UDRP/PWD/07/RD/118 and UDRP/PWD/07/RD/119. Since both writ petitions arose in
similar circumstances, the High Court treated Writ Petition (M/S) No. 3067 of
2018 as the lead matter.
In relation to Package No. UDRP/PWD/07/RD/119, the
estimated cost of the work was ₹1,528.53 lakh. The petitioner submitted a bid
of ₹15,24,91,267.15, which was only about ₹4 lakh below the estimated cost.
The respondents issued a Letter of Acceptance dated
23 September 2017 and required the petitioner to furnish Additional Performance
Security of ₹2,88,69,664.72 on the ground that the bid was “unbalanced” in
terms of ITB Clause 40. However, the communication did not disclose how or on
what objective basis the petitioner’s bid had been treated as unbalanced.
The petitioner declined to furnish the Additional
Performance Security, contending that such demand was contrary to the
contractual terms. The respondents thereafter sought to forfeit the
petitioner’s bid security.
The petitioner had earlier approached the High
Court through Writ Petition (M/S) No. 2798 of 2017, contending that no basis
had been disclosed for requiring Additional Performance Security under ITB
Clause 40.1. The learned Single Judge disposed of that petition with directions
to the respondents to consider the petitioner’s case in terms of Clause 40.1,
consider its explanation, and pass an order in accordance with law.
Pursuant to that direction, the petitioner
submitted its explanation on 2 July 2018. The respondents subsequently passed
the impugned order dated 31 August 2018. They stated, inter alia, that rates
quoted for 42 items of work were substantially low in comparison with
departmental sanctioned estimates and that Additional Performance Security had
been assessed in accordance with the applicable Government Order. The
petitioner challenged that decision.
Issues
Involved
- Whether the respondents could invoke ITB Clause 40.1 and demand
Additional Performance Security merely by stating that the petitioner’s
rates were “substantially low”.
- Whether the employer was required to undertake an objective
analysis and disclose the specific basis on which the bid or individual
item rates were considered seriously unbalanced, front-loaded, or
substantially below updated estimates.
- Whether the impugned order dated 31 August 2018 complied with the
earlier High Court direction dated 25 June 2018 in Writ Petition (M/S) No.
2798 of 2017.
- Whether the respondents had properly considered the petitioner’s
rate analysis submitted on 2 July 2018 before reaching the conclusion that
the quoted rates were substantially low.
- Whether the demand for Additional Performance Security could be
sustained in the absence of a reasoned and objectively supported
determination under ITB Clause 40.1.
Petitioner’s
Arguments
The petitioner contended that the demand for
Additional Performance Security was contrary to the terms governing the tender
and that the respondents had failed to disclose any proper basis for treating
the bid as unbalanced or substantially low.
It was emphasized that the petitioner’s total bid
was only about ₹4 lakh below the estimated cost of the work. Therefore, a bare
assertion that the bid or rates were substantially low could not justify
invocation of ITB Clause 40.1.
The petitioner further maintained that adequate
contractual safeguards already existed, including the performance bank
guarantee and deductions from running bills. It assured the authorities that
the work would be completed within the stipulated time and to the required
satisfaction.
The petitioner also relied upon the detailed rate
analysis furnished on 2 July 2018 pursuant to the earlier order of the High
Court and contended that the respondents had not objectively evaluated that
explanation before maintaining the demand for Additional Performance Security.
Respondents’
Arguments
The respondents maintained that the petitioner had
quoted substantially low rates in respect of 42 items of work when compared
with the departmental sanctioned estimates.
They relied upon ITB Clause 40.1 and the
Uttarakhand Government Order dated 12 June 2017 to justify the assessment and
demand of Additional Performance Security amounting to ₹2,88,69,664.72.
The respondents further stated that the Letter of
Acceptance had been issued after treating the petitioner as competent, but the
petitioner failed to deposit the assessed Additional Performance Security
within the stipulated period. Consequently, action was taken under ITB Clauses
45.1 and 45.2, including cancellation of the Letter of Acceptance and the bid.
The respondents also referred to the time-bound
nature of the UDRP project and the limited period remaining for completion of
the works.
Court Order
/ Findings
The High Court found that the respondents had
failed to undertake the exercise expected of them. The impugned order did not
clearly identify the specific items in respect of which the rates quoted by the
petitioner were found to be unbalanced or substantially low, nor did it
objectively disclose the basis for such a conclusion.
The Court held that a mere statement that the
petitioner’s rates were substantially low was insufficient. This was
particularly significant because the petitioner claimed that its total bid was
only about ₹4 lakh below the estimated cost.
The High Court observed that invocation of ITB
Clause 40 required the respondents to arrive at an objective conclusion that
the bid submitted by the bidder was substantially low.
The Court further held that the impugned order did
not comply, either in letter or in spirit, with the earlier order dated 25 June
2018 passed by the learned Single Judge in Writ Petition (M/S) No. 2798 of
2017.
Accordingly, the High Court:
- quashed the impugned order dated 31 August 2018;
- remanded the matter to the respondents;
- directed the respondents to clearly state the basis on which the
bids or rates submitted by the petitioner were claimed to be substantially
low;
- directed consideration of the rate analysis furnished by the
petitioner on 2 July 2018;
- directed that a personal hearing be granted to the petitioner;
- directed the respondents to pass a reasoned order; and
- required completion of the entire exercise within four weeks.
Both writ petitions were disposed of in these
terms.
Important
Clarification
The High Court expressly clarified that it had not
itself examined or decided whether the rates or quotations submitted by the
petitioner were, in fact, substantially low.
That question was left for determination by the
respondents. However, the respondents were required to reach such determination
objectively, disclose the basis of their conclusion, consider the petitioner’s
rate analysis, provide a personal hearing, and pass a reasoned order.
Therefore, the judgment should not be understood as
holding that the petitioner’s bid was not substantially low. The decisive
finding was that the respondents could not sustain such a conclusion merely
through an unsupported assertion without objective analysis and disclosed
reasons.
Sections /
Clauses Involved
ITB Clause 40.1: Relating to
seriously unbalanced, front-loaded, or substantially below-estimate bids;
detailed price analysis; evaluation of internal consistency and justification
of prices; and possible enhancement of performance security to protect the
employer against financial loss in the event of default.
ITB Clause 45.1: Referred to
by the respondents in connection with action following failure to furnish the
required security.
ITB Clause 45.2: Referred to
by the respondents in connection with cancellation-related consequences arising
from non-submission of the demanded Additional Performance Security.
Uttarakhand Government Order dated 12 June 2017: Relied upon by the respondents for assessment of Additional Performance Security.
Link to download the order - https://www.mytaxexpert.co.in/uploads/1783504067_2101compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment