Facts of the Case
The petitioner, Marysadan Projects Pvt. Ltd.,
executed road construction works for the Public Works Department (PWD), Kerala,
including the Chalakudy–Vellikulangara Road and flood rectification works on
the Kulluthi–Kalavarakadavu Road. After completing the work, the petitioner
submitted part bills during July and August 2022.
Although the work measurements had been recorded
and the bills were prepared, the authorities failed to upload the bills through
the Price Software, allegedly because the software had become
non-functional while being updated following the revision in GST rates.
The petitioner contended that the delay in
uploading the bills would adversely affect its right to timely payment and
could also result in loss of seniority in the queue for bill clearance.
Consequently, the petitioner approached the Kerala High Court seeking
appropriate directions.
Issues Involved
- Whether the authorities could delay uploading the contractor's
bills due to malfunction or updating of the Price Software.
- Whether such administrative delay could adversely affect the
contractor's seniority in the processing and clearance of bills.
- Whether the Court should issue directions to protect the
contractor's entitlement pending restoration of the software.
Petitioner’s Arguments
- The petitioner had successfully completed the contractual work and
submitted the part bills within time.
- The measurements had already been taken and the bills had been
prepared by the departmental authorities.
- The only reason for non-uploading of the bills was the malfunction
of the Price Software.
- The delay was entirely attributable to the Government's internal
software issues and not to any fault of the petitioner.
- Continued delay would cause financial hardship and could deprive
the petitioner of seniority in the processing of bills, thereby affecting
timely payment.
Respondent’s Arguments
- The State submitted that the Price Software was undergoing updation
due to revision in GST and would become functional shortly.
- It was argued that since the work had already been measured and the
bills prepared, the petitioner would not lose seniority merely because
uploading had been delayed.
- The Government assured the Court that the software issue was
temporary and would be resolved without unnecessary delay.
Court Order / Findings
The Kerala High Court accepted the Government's
submission regarding the temporary software issue but recognised that the
petitioner should not suffer due to administrative or technical delays.
The Court disposed of the writ petition with
directions that:
- The competent authority shall upload the petitioner's part bills
immediately after the Price Software becomes functional.
- The delay in uploading shall not result in the petitioner losing
seniority in the matter of bill clearance.
- Payment shall be processed subject to the petitioner being
otherwise eligible to receive the amounts claimed under the bills.
The Court thereby ensured that contractors are not
prejudiced by delays arising from Government software or administrative issues.
Important Clarification
- Government contractors cannot be penalised for delays caused solely
by malfunctioning or updating of Government software.
- Administrative or technical issues within Government departments
cannot deprive contractors of their rightful position in the bill
processing queue.
- Once work measurements have been recorded and bills prepared,
subsequent software-related delays should not adversely affect the
contractor's entitlement.
- The Court protected both the petitioner's seniority and eligibility
for payment while recognising the temporary nature of the software issue.
Sections / Legal Provisions Involved
- Article 226 of the Constitution of India
- Administrative Law Principles relating to Fairness and
Non-Arbitrariness
- Public Works Department (PWD) Payment Procedures
- Government Contract Administration
- GST Revision affecting Government Billing Software
Sections Involved:
- Public Works Department (PWD) Contract Payments
- Upload of Running/Part Bills through Price Software
- GST Revision Impact on Government Payment Software
- Administrative Delay in Processing Bills
- Principles of Fair Administrative Action under Article 226 of the Constitution of India
Link to download the order - https://www.mytaxexpert.co.in/uploads/1783923957_2125compressed.pdf
Disclaimer
This content is shared strictly for general
information and knowledge purposes only. Readers should independently verify
the information from reliable sources. It is not intended to provide legal,
professional, or advisory guidance. The author and the organisation disclaim
all liability arising from the use of this content. The material has been
prepared with the assistance of AI tools.