Facts of the Case
A large batch of writ petitions was filed before
the Jharkhand High Court by contractors and infrastructure entities executing
works for different departments of the State Government and other State
instrumentalities. The petitions raised a common issue concerning the
implementation of the GST regime in relation to works contracts that were
subsisting when GST came into force on 1 July 2017.
The petitioners’ case was that their contracts had
been awarded during the pre-GST / VAT regime. Under those contracts, tax had
been computed according to the then-existing VAT structure and contractual
provisions. With the introduction of GST from 01.07.2017, the tax framework
changed and, according to the petitioners, resulted in a higher or differential
tax burden in respect of works executed or payments received during the GST
period.
The petitioners contended that GST was not only
imposed at a changed rate but was also leviable on the taxable value of the
works contract as a whole under the new regime. Consequently, they claimed that
they were compelled to bear the differential GST burden without an appropriate
and uniform reimbursement mechanism.
The dispute had remained pending for a
considerable period. The petitioners pointed out that other State Governments
and public authorities, including Telangana, Andhra Pradesh, Railways and
certain public sector undertakings, had framed guidelines dealing with
comparable transitional issues.
The High Court had earlier addressed the subject
in M/s Bhardwaj Construction Company (P) Ltd. vs State of Jharkhand, W.P.(T)
No. 5045 of 2018, directing the State to take a decision. A subsequent
decision of the Water Resources Department dated 22 April 2019 bearing Order
No. 2086 was alleged by the petitioners to have failed to properly resolve
the issue.
During the proceedings, the High Court considered
that a uniform mechanism was necessary for implementing the GST reimbursement
framework. The Court referred to the MoRTH mechanism dated 19.12.2018
and the consequential letter dated 14.07.2021 bearing Letter No. 1421,
issued by the Secretary, Commercial Taxes Department, Government of Jharkhand.
The Court thereafter requested the Chief
Secretary, Jharkhand, to examine the matter and ensure that appropriate
guidelines were framed for resolving claims in a time-bound and coordinated
manner across different departments.
Following meetings with heads of concerned
departments and workshops for technical officers, the State Government framed a
Standard Operating Procedure dated 26.08.2022. The SOP was brought on
record through a supplementary counter affidavit filed by the Special
Secretary, Commercial Taxes Department on 02.09.2022.
Issues Involved
The principal issues before the High Court were:
- Whether
contractors executing subsisting works contracts awarded during the
pre-GST regime were entitled to seek reimbursement of the differential GST
burden arising after implementation of GST from 01.07.2017.
- Whether
the State of Jharkhand was required to provide a uniform mechanism for
dealing with differential GST reimbursement claims concerning pre-GST
works orders executed partly or wholly during the post-GST period.
- Whether
individual claims should be adjudicated by the concerned Government
departments or State instrumentalities under the newly framed SOP dated
26.08.2022.
- Whether
the High Court should examine the validity, deficiencies or individual
clauses of the SOP when the SOP itself had not been challenged in the
pending batch of writ petitions.
- Whether
earlier rejection or adverse consideration of individual claims would
prevent fresh determination under the subsequently issued SOP.
- What
time frame should govern the disposal of long-pending differential GST
reimbursement claims.
Petitioners’ Arguments
The petitioners contended that the works contracts
in question had been awarded under the pre-GST / VAT regime and contained
provisions for computation of tax according to the earlier tax structure.
According to them, the introduction of GST from 1
July 2017 created a higher and materially different tax burden. They argued
that they were required to bear differential tax liability without an effective
reimbursement mechanism.
The petitioners submitted that no uniform
guidelines had initially been framed by the State of Jharkhand, resulting in
inconsistent treatment across different Works Departments and State
instrumentalities.
They relied upon mechanisms and guidelines stated
to have been adopted by other State Governments, including Telangana and Andhra
Pradesh, as well as Railways and other public sector undertakings.
The petitioners also referred to judicial orders
passed by different High Courts, including the Madras High Court and Orissa
High Court, in relation to comparable transitional GST issues.
After the SOP dated 26.08.2022 was framed, counsel
for the petitioners attempted to point out certain alleged lacunae in its
clauses. However, they ultimately sought disposal of the writ petitions with a
direction requiring the competent authorities to decide their individual claims
within a strict time frame, since the issue had remained unresolved for a
considerable period.
Respondents’ Arguments
The respondents submitted that the State
Government had already framed the SOP dated 26.08.2022, which
established a mechanism for dealing with post-GST payments of pending bills
related to works orders issued during the pre-GST period.
The respondents argued that, after issuance of the
SOP, the individual petitioners should approach the competent authorities of
the respective departments or State instrumentalities for consideration of
their differential GST reimbursement claims.
It was further submitted that because the SOP
itself was not under challenge in the batch of writ petitions, the High Court
should not make observations regarding its individual clauses at that stage.
The respondents therefore supported resolution of
individual claims through the administrative mechanism created under the SOP.
Court Order / Findings
The High Court observed that the common
controversy concerned reimbursement of the differential GST amount paid by
contractors under subsisting contracts existing as on 01.07.2017.
The Court recorded that it was during the
proceedings and at the instance of the Court that the State Government
considered it appropriate to formulate a mechanism through a Standard
Operating Procedure for dealing with individual claims of aggrieved
contractors and petitioners.
The Court noted that the SOP had been framed and
published in the Extraordinary Gazette dated 26.08.2022 and was intended
to deal with post-GST payments of pending bills relating to works orders issued
during the pre-GST period.
Since the SOP was not under challenge in
the batch of writ petitions, the High Court held that it was not necessary or
appropriate to make observations on its terms and clauses at that stage.
The Court directed that the petitioners should
press their existing claims before the concerned departments or State
instrumentalities, or submit fresh claims, so that the competent authorities
could take an informed decision in accordance with law and the SOP dated
26.08.2022.
Considering that the claims had remained pending
for a long period following implementation of GST from 01.07.2017, the High
Court directed that individual representations or claims should be decided expeditiously,
preferably within eight weeks from the date of receipt of a copy of the Court’s
order.
The Court further clarified that any earlier stand
taken by the respondents regarding the correctness of an individual
petitioner’s claim would not prevent a fresh decision after application
of the guidelines and terms contained in the new SOP dated 26.08.2022.
The High Court also clarified that if any
petitioner was aggrieved by the fresh decision, such decision could give rise
to a fresh cause of action capable of being challenged in appropriate
proceedings.
Further, any petitioner aggrieved by a particular
clause of the SOP would remain free to challenge that clause separately.
The Court ordered that W.P.(T) Nos. 989 of 2022
and 990 of 2022 be de-tagged from the batch and listed separately after one
week. The remaining writ petitions were disposed of, all pending interlocutory
applications were closed, and the Court expressly stated that it had made no
comment on the individual merits of the petitioners’ cases.
Important Clarification
The judgment does not declare an automatic or
unconditional right to reimbursement of differential GST in favour of every
contractor holding a pre-GST works contract.
Instead, the High Court directed that each
individual claim must be examined by the competent department or State
instrumentality in accordance with law and the SOP dated 26.08.2022.
The Court also did not uphold or invalidate any
particular clause of the SOP, because the SOP itself was not under
challenge in the batch proceedings.
A significant clarification is that an earlier
rejection, adverse stand or previous departmental view concerning an individual
claim would not obstruct a fresh decision under the new SOP framework.
The judgment further preserves the right of an
aggrieved contractor to institute appropriate fresh proceedings against an
adverse decision and, where necessary, to separately challenge any clause of
the SOP causing prejudice.
Therefore, the legal effect of the order is
procedural and remedial: it establishes a route for time-bound reconsideration
and determination of individual differential GST reimbursement claims without
prejudging their merits.
Relevant Sections / Legal Framework Involved
- Goods
and Services Tax regime effective from 01.07.2017
— Central to the transitional dispute concerning ongoing and subsisting
works contracts.
- Pre-GST
VAT regime — Original tax framework under which
the relevant works contracts were awarded.
- SOP
/ Directive dated 26.08.2022 — Mechanism for
post-GST payments of pending bills relating to works orders issued during
the pre-GST period.
- S.O.
No. 33 dated 26 August 2022 — Notification of
the Commercial Taxes Department, Government of Jharkhand.
- MoRTH
Guidelines / Letter dated 19.12.2018 —
Mechanism considered during formulation and implementation of the
reimbursement framework.
- Commercial
Taxes Department Letter No. 1421 dated 14.07.2021
— Relevant State communication concerning implementation.
- Article
226 of the Constitution of India —
Constitutional writ jurisdiction under which the High Court addressed the
petitioners’ grievances and issued directions for administrative
consideration.
- GST transitional implementation concerning subsisting works contracts — Core legal and contractual framework governing the controversy.
Link to download the order -https://mytaxexpert.co.in/uploads/1783679033_1541compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes
only. Readers should independently verify the information from reliable
sources. It is not intended to provide legal, professional, or advisory
guidance. The author and the organisation disclaim all liability arising from
the use of this content. The material has been prepared with the assistance of
AI tools.
0 Comments
Leave a Comment