FACTS OF THE CASE
- The
batch of writ petitions was filed by several contractors, led by M/s Sri
Sai Krishna Constructions, Harvin Construction Pvt. Ltd., Royal
Infraconstru Limited, Classic Engicon Pvt. Ltd., Larsen & Toubro
Limited, and others, against the State of Jharkhand and various government
departments/instrumentalities.
- The
petitioners were awarded works contracts by various State Government
departments (e.g., Water Resources Department, Road Construction
Department, Drinking Water & Sanitation Department) and State
Instrumentalities (e.g., Jharkhand Bijli Vitran Nigam Limited, JUIDCO)
prior to 1st July 2017 (the pre-GST regime).
- Execution
of these works and the subsequent payments/pending bills spanned into the
post-GST regime (on or after 01.07.2017).
- Under
the pre-GST regime, the contracts were structured around Value Added Tax
(VAT), Service Tax, Central Excise, and Entry Tax calculations. Following
the implementation of the GST regime on 01.07.2017, these indirect taxes
were subsumed, resulting in higher overall tax liabilities on the total
taxable value of the works contracts as a whole.
- The
contractors were compelled to bear the differential tax burden out of
pocket without receiving appropriate or uniform reimbursement from the
state authorities.
- An
earlier direction in M/s Bhardwaj Construction Company (P) Ltd. Vs.
State of Jharkhand (W.P.(T) No. 5045 of 2018) prompted an order dated
22nd April 2019 (Order No. 2086) by the Water Resources Department;
however, the petitioners contended that it failed to resolve the systemic
issue properly, leading to the instant batch of writ petitions.
ISSUES INVOLVED
- Reimbursement
Mechanism: Whether contractors executing pre-GST works
contracts, which continued post-01.07.2017, are entitled to reimbursement
of the differential GST liability caused by the transition from the
VAT/Service Tax regime to the GST regime.
- Lack
of Uniform Guidelines: Whether the State of Jharkhand was
obligated to establish a uniform Standard Operating Procedure (SOP) to
ensure consistent processing of pending post-GST bills across all
government departments and state instrumentalities.
- Expeditious
Disposal: How the individual differential tax
reimbursement claims should be adjudicated following the formulation and
gazette publication of the official State SOP.
PETITIONER’S ARGUMENTS
- Shift
in Tax Liability: The introduction of the GST regime
subsumed VAT, Central Excise, Service Tax, CST, and Entry Tax, resulting
in a significantly higher rate of tax leviable on the entire taxable value
of ongoing works contracts.
- Financial
Hardship: The petitioners were forced to pay the
increased differential tax amount upfront without corresponding mechanisms
or timely reimbursement from the respondent departments.
- Lack
of Uniform State Guidelines: While other State
Governments (such as Telangana and Andhra Pradesh), Indian Railways, and
various Public Sector Undertakings (PSUs) had framed guidelines to adjust
and reimburse differential tax liabilities, Jharkhand had failed to
provide a uniform mechanism.
- Ineffective
Initial Orders: Previous orders issued by individual
departments (such as Order No. 2086 dated 22.04.2019 by the Water
Resources Department) were inadequate and failed to address the systemic
issue across all departments.
- Need
for Time-Bound Resolution: Given that the claims had
been lingering since July 2017, the petitioners requested direct
instructions to the competent authorities to decide individual claims
within a strict, designated timeframe.
RESPONDENT’S ARGUMENTS
- SOP
Formulation: Pursuant to judicial directions dated
16.03.2021 and 04.05.2022, the Chief Secretary of Jharkhand conducted
inter-departmental deliberations and technical workshops, culminating in
the notification of a formal Standard Operating Procedure (SOP).
- Notification
S.O. No. 33: The Commercial Taxes Department officially
notified the SOP via Extraordinary Gazette Notification S.O. No. 33 dated
26th August 2022 to regulate post-GST payments of pending bills for
pre-GST work orders.
- Appropriate
Forum for Individual Claims: Since a comprehensive SOP
was officially in place and was not directly challenged in the writ
petitions, the individual petitioners ought to submit their claims
directly to the competent authorities of their respective Works
Departments/Instrumentalities for verification and settlement under the
new guidelines.
COURT ORDER / FINDINGS
- Role
of the Judiciary and SOP Establishment: The Division Bench
of Hon'ble Mr. Justice Aparesh Kumar Singh and Hon'ble Mr. Justice Deepak
Roshan observed that the framing of the SOP dated 26.08.2022 successfully
created an official framework to address post-GST pending bills for
pre-GST works contracts.
- No
Comments on SOP Clauses: As the validity of the SOP
was not under challenge in this batch of petitions, the High Court
refrained from expressing any opinion on its terms and clauses.
- Direction
for Expeditious Decision: The Court directed all
individual petitioners to press their claims before the respective
departments or state instrumentalities. The competent authorities were
directed to take an informed, fresh decision on the individual
representations strictly in accordance with law and the SOP dated
26.08.2022.
- Timeframe
Fixed: The Court ordered that all representations
and claims must be decided expeditiously, preferably within a period of
8 weeks from the date of receipt of a copy of the court order.
- Fresh
Cause of Action & Liberty to Challenge: The
Court clarified that if any contractor is aggrieved by a future decision
or rejection made under the SOP, or by any specific clause of the SOP
itself, it will give rise to a fresh cause of action that can be
challenged in an appropriate proceeding.
- Severance
of Specific Cases: W.P.(T) Nos. 989/2022 and 990/2022 were
ordered to be de-tagged from the batch and listed separately. The
remaining writ petitions were disposed of.
IMPORTANT CLARIFICATION
Key Judicial Observation:
The High Court clarified that any prior positions or stand
taken by the Respondent Departments regarding the correctness or rejection of
individual claims prior to the issuance of the SOP will not prevent or
impede the authorities from taking a fresh, independent decision based on the
application of the terms set out under the fresh SOP Notification dated
26.08.2022. Furthermore, contractors retain the explicit liberty to challenge
the SOP or any adverse order arising from it in fresh legal proceedings.
SECTIONS INVOLVED
- Section
15 of the Central Goods and Services Tax (CGST) Act, 2017 / Jharkhand
Goods and Services Tax (JGST) Act, 2017: Governs the
valuation of taxable supply.
- Section
142 of the Central Goods and Services Tax (CGST) Act, 2017 / JGST Act,
2017: Deals with transitional provisions, including price
revisions, supplementary contracts, and tax adjustments for
ongoing/subsisting contracts entered into during the pre-GST regime.
- Article
226 of the Constitution of India: Authorises High Courts to
issue writs for the enforcement of fundamental or legal rights.
- Jharkhand Commercial Taxes Department Notification S.O. No. 33 (Dated 26th August 2022): The official Standard Operating Procedure (SOP) framed for post-GST payments and reimbursement of differential tax on pending bills related to work orders issued during the pre-GST period.
Link to download the order - https://mytaxexpert.co.in/uploads/1784616502_1563compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content.The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment