Facts of the Case
- Tender
Notification and Agreement: Pursuant to a tender
notification dated June 14, 2017, for providing BT road, CC road, and side
drains in Yanamalakuduru Village, Penamaluru Mandal (estimated at ₹200.00
Lakhs), the petitioner participated and was declared the successful
bidder. Consequently, an agreement was executed between the petitioner and
the 3rd respondent on January 20, 2018.
- Work
Completion: The execution of the work was fully
completed by August 12, 2018. Following an inspection, the Quality Control
Agency submitted a favorable report on September 07, 2018.
- Directive
for Supplementary Agreement: Despite the satisfactory
completion of the work, the respondent authorities failed to release the
final bill amount. Subsequently, through a letter dated September 19,
2020, the 4th respondent directed the petitioner to give consent for
entering into a supplementary agreement to revise SOR/SSR rates pursuant
to G.O.Ms.No.58, Finance (WR.I) Department, dated May 08, 2018.
- Reduction
of Bill Amount: Pending the writ petition, the petitioner
executed a supplementary agreement under protest, explicitly stating that
its conditions were subject to the outcome of the writ petition.
Post-revision of SSR rates under the supplementary agreement, the bill amount
payable to the petitioner was reduced from ₹1,64,55,418/- to
₹1,54,23,312/-, creating a differential shortfall of ₹10,32,106/-.
Issues Involved
- Whether
the direction issued by the respondent authorities forcing the petitioner
to enter into a supplementary agreement to revise SOR/SSR rates post-work
completion based on G.O.Ms.No.58 dated May 08, 2018, is illegal,
arbitrary, and unconstitutional?
- Whether
the reduction of the admitted final bill amount from ₹1,64,55,418/- to
₹1,54,23,312/- and non-payment of the differential amount of ₹10,32,106/-
along with interest @ 18% p.a. for delayed payment is legally sustainable?
Petitioner’s Arguments
- Arbitrary
Action: The petitioner contended that the insistence
on entering into a supplementary agreement long after the satisfactory
completion of the assigned work was illegal, arbitrary, and contrary to
the terms of the original agreement dated January 20, 2018.
- Entitlement
to Original Agreed Value: It was argued that after
executing the main work and additional works entrusted via separate
agreements, the petitioner was lawfully entitled to the full gross amount
of ₹1,84,30,067/- (for CC-II Bill) and ₹1,72,74,109/- (for CC-III Bill)
including GST components.
- Conditional
Consent and Differential Claim: The petitioner asserted
that the supplementary agreement was executed under duress and explicitly
made subject to the result of the Writ Petition. Due to the unilateral
downward revision of SSR rates, the bill amount was arbitrarily reduced,
leaving an unpaid balance/differential amount of ₹10,32,106/-, which the
state is legally bound to disburse with interest.
Respondent’s Arguments
- Transition
to GST Regime: The 4th Respondent, in the counter
affidavit, contended that at the time of preparing estimates, the GST Act
had not come into force, and estimations were computed based on Value
Added Tax (VAT).
- Application
of G.O.Ms.No.58: Following the rollout of GST on July 01,
2017, the Government issued G.O.Ms.No.58 dated May 08, 2018, requiring all
public works contractors to enter into supplemental agreements to revise
unit rates (excluding tax elements) for works executed post-July 01, 2017,
and add applicable GST separately.
- No
Outstanding Liability: The respondents maintained that the
difference in calculations stemmed solely from tax adjustments under the
GST regime. Thus, the claimed amounts were appropriately adjusted toward
GST, leaving no further monetary liability on the state.
Court Order / Findings
- Order
of the Court: The Hon’ble High Court of Andhra Pradesh,
presided over by Hon'ble Sri Justice Venkateswarlu Nimmagadda, disposed of
the Writ Petition without delving into complex factual mathematical
calculations.
- Directions
Issued:
- The
Petitioner was directed to submit a detailed, comprehensive statement of
account, including GST payable as per the GST Act, to the authorities
within two (2) weeks from the date of receipt of the order.
- Upon
receipt of such statement of account, the 2nd Respondent was directed to
consider the same, provide an opportunity of hearing to the petitioner,
and determine the exact balance amount payable within three (3) months
thereafter.
- Pending
miscellaneous petitions were closed without any order as to costs.
Important Clarification
- Legal
Impact of G.O.Ms.No.58: The judgment underscores
that government circulars revising tax structures (such as transitioning
from VAT to GST via G.O.Ms.No.58) cannot be applied mechanically to reduce
the total contractual remuneration of contractors without giving them an
opportunity to present a reconciled statement of account.
- Conditional
Execution: Entering into a supplementary agreement
under protest or subject to the outcome of pending judicial proceedings
preserves the contractor's right to claim differential losses arising from
post-facto rate revisions.
Sections Involved
- Constitution
of India: Article 226 (Writ Jurisdiction for
enforcement of legal rights and challenging arbitrary state actions).
- Central
Goods and Services Tax Act, 2017 / Andhra Pradesh Goods and Services Tax
Act, 2017: Provisions applicable to works contracts
executed during the transitional period post-01.07.2017.
- Government Order: G.O.Ms.No.58, Finance (WR.I) Department, dated 08.05.2018 (Pertaining to revision of SoR/SSR rates and GST implementation in works contracts).
Link to download the order - https://mytaxexpert.co.in/uploads/1784626384_1863compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content.The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment