Facts of the Case
The petitioner, M/s VPR Mining Infrastructure
Pvt. Ltd., was awarded a mining contract by The Singareni Collieries
Company Limited (SCCL) for drilling, excavation, transportation, dumping
and related overburden removal works pursuant to a Notice Inviting Tender (NIT)
dated 15.10.2018. The contract contemplated execution using Heavy Earth Moving
Machinery (HEMM) over a period of 72 months.
During execution, the petitioner alleged that the
respondents had failed to obtain necessary statutory permissions from the
Directorate General of Mines Safety (DGMS) for blasting operations within
restricted zones near high-tension transmission lines and the Godavari river
embankment before issuing the tender. According to the petitioner, this
resulted in controlled blasting instead of general blasting, substantially
altering the scope of work, reducing productivity, increasing operational
costs, and making performance commercially unviable.
The petitioner requested foreclosure of the contract under Clause 1.13.3 relating to unforeseen circumstances and sought settlement of its final dues. When SCCL declined, the petitioner invoked the writ jurisdiction of the Telangana High Court under Article 226 of the Constitution.
Issues Involved
- Whether the mining contract deserved foreclosure under Clause
1.13.3 due to alleged unforeseen circumstances.
- Whether failure to obtain statutory blasting permissions before
floating the tender constituted a material deviation from the contract.
- Whether the High Court could exercise jurisdiction under Article
226 in a contractual dispute involving disputed questions of fact.
- Whether the petitioner was entitled to a writ directing foreclosure of the contract and settlement of final bills.
Petitioner’s Arguments
- SCCL floated the tender without obtaining essential statutory
permissions for blasting operations in restricted zones.
- Controlled blasting imposed later fundamentally altered the
contractual scope and rendered the work commercially impracticable.
- The petitioner had mobilized substantial manpower, machinery, and
financial resources based on the original contractual assumptions
regarding general blasting.
- The respondents failed to disclose material facts concerning
blasting restrictions at the tender stage.
- The respondents also failed to provide sufficient working areas and
adequate blasting arrangements, causing significant financial losses and
prolonged idling of machinery.
- Since the contract had become impossible to perform as originally contemplated, Clause 1.13.3 regarding unforeseen circumstances was attracted, entitling the petitioner to foreclosure of the contract.
Respondent’s Arguments
- The writ petition was not maintainable because the contract itself
contained a comprehensive dispute resolution mechanism.
- Clause 1.13.3 was applicable only where work was stopped due to
changes in law, governmental action, court directions, or reasons beyond
SCCL's control, none of which existed in the present case.
- Controlled blasting had been followed from the beginning of the
project and the petitioner was fully aware of the site conditions.
- The petitioner had successfully achieved contractual targets during
the initial years, demonstrating that execution was feasible.
- Adequate work areas, blasting permissions, and explosives were made
available, and the petitioner itself intentionally slowed down work and
failed to deploy sufficient machinery.
- The dispute involved highly disputed questions of fact unsuitable for adjudication under Article 226.
Court Order / Findings
The Telangana High Court dismissed the writ
petition.
The Court observed that although writ jurisdiction
may be exercised in contractual matters in exceptional cases involving
arbitrariness by the State, such jurisdiction cannot be invoked where
adjudication requires examination of complex disputed questions of fact.
The Court found that:
- The dispute essentially arose from performance of contractual
obligations.
- The parties had seriously disputed the factual allegations
regarding blasting permissions, workability of the contract, availability
of work areas, productivity, and contractual deviations.
- The contract itself contained a dispute resolution mechanism.
- The question whether the contract had become impossible to perform
or whether foreclosure under Clause 1.13.3 was justified required detailed
factual adjudication, which could not appropriately be undertaken in writ
proceedings under Article 226.
Accordingly, the High Court declined to grant the relief of foreclosure and dismissed the writ petition without costs.
Important Clarification
This judgment reiterates that:
- Contractual disputes involving disputed facts ordinarily cannot be
resolved through writ proceedings under Article 226.
- Even where a State instrumentality is involved, the High Court will
ordinarily refuse to interfere if determination of rights requires
detailed examination of contractual evidence.
- Clauses permitting foreclosure of contracts must be interpreted
strictly according to their contractual language and cannot automatically
be invoked merely because execution becomes commercially difficult.
- Parties should ordinarily pursue contractual dispute resolution mechanisms or appropriate civil remedies before seeking constitutional relief.
Sections / Provisions Involved
- Article 226 of the Constitution of India
- Clause 1.13.3 (Foreclosure due to unforeseen circumstances)
- Clause 1.14 (Contractual dispute resolution mechanism)
- Coal Mines Regulations, 2017
- DGMS Blasting Permission Regulations
Link to Download the Order
https://mytaxexpert.co.in/uploads/1785321746_2227compressed.pdf
Disclaimer
This content is shared strictly for general information and knowledge purposes only. Readers should independently verify the information from reliable sources. It is not intended to provide legal, professional, or advisory guidance. The author and the organisation disclaim all liability arising from the use of this content. The material has been prepared with the assistance of AI tools.
0 Comments
Leave a Comment