Facts of the Case
Ram Kripal Singh Construction Private Limited entered into an
agreement with the State of Jharkhand for widening and improvement of National
Highway NH-114(A). The project was awarded for approximately ₹69.70 crore with
a stipulated completion period of eighteen months.
Due to certain circumstances, the work could not be completed
within the original period, and an extension of time was granted. After
completion of the project, the petitioner received the completion certificate
and submitted the final bill along with claims for delayed payment interest,
royalty difference and GST reimbursement.
According to the petitioner, despite invoking the contractual arbitration clause and requesting appointment of a sole arbitrator, the respondents failed to act upon the request. Consequently, the petitioner approached the Jharkhand High Court under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of an arbitrator.
Issues Involved
- Whether
the High Court should appoint an arbitrator under Section 11(6) of the
Arbitration and Conciliation Act, 1996.
- Whether
the existence of disputes relating to delayed payment, GST reimbursement,
royalty and interest could be examined by the Court at the stage of
appointment of an arbitrator.
- Whether
objections raised by the State regarding absence of dispute prevented
appointment of an arbitrator.
Petitioner's Arguments
- The
petitioner submitted that genuine disputes existed regarding delayed
payment of the final bill, GST reimbursement, royalty adjustment and
interest.
- The
contractual arbitration mechanism had already been invoked under Clause 25
of the agreement.
- Despite
the request, the respondents failed to appoint an arbitrator within the
prescribed period.
- Since
the arbitration agreement existed and disputes had arisen between the
parties, appointment of an arbitrator under Section 11(6) became
necessary.
- The merits of the disputes were required to be decided by the arbitral tribunal and not by the Court while considering an application under Section 11(6).
Respondent's Arguments
The State opposed the application by contending that:
- No
arbitrable dispute actually existed.
- The
contractor had delayed completion of the work.
- Extension
of time had already been granted.
- The
final bill had been paid.
- Claims
relating to interest, royalty difference and GST reimbursement were not
payable.
- Since there were no outstanding dues, appointment of an arbitrator was unnecessary.
Court Order / Findings
The Jharkhand High Court observed that the State had not
disputed the existence of the arbitration clause contained in Clause 25 of the
agreement. The Court held that while exercising jurisdiction under Section
11(6), it is not required to examine the merits of the disputes or determine
whether the claims are ultimately sustainable.
The Court clarified that issues regarding delayed payment,
entitlement to GST reimbursement, royalty difference, interest or alleged
absence of liability are matters to be adjudicated by the arbitrator.
Since the arbitration agreement existed and the respondents
had failed to appoint an arbitrator after invocation of the arbitration clause,
the statutory requirements under Section 11(6) stood satisfied.
Accordingly, the Court appointed Hon'ble Mr. Justice (Retd.) Tapen Sen, Former Judge of the Jharkhand High Court, as the Sole Arbitrator to adjudicate the disputes between the parties. The arbitrator was directed to furnish the disclosure required under Section 12 of the Arbitration and Conciliation Act, 1996 and conduct the proceedings in accordance with law.
Important Clarification
This judgment reiterates the settled principle that while
exercising powers under Section 11(6) of the Arbitration and Conciliation Act,
1996, the Court primarily examines the existence of a valid arbitration
agreement and whether the appointment procedure has failed.
The Court does not decide disputed questions relating to entitlement, liability, delayed payments, GST reimbursement, royalty adjustments or interest claims at the stage of appointment of an arbitrator. Such issues fall exclusively within the jurisdiction of the arbitral tribunal.
Link to Download the Order
https://mytaxexpert.co.in/uploads/1785561347_2452compressed.pdf
Disclaimer
This content is shared strictly for general information and
knowledge purposes only. Readers should independently verify the information
from reliable sources. It is not intended to provide legal, professional, or
advisory guidance. The author and the organisation disclaim all liability
arising from the use of this content. The material has been prepared with the
assistance of AI tools.
0 Comments
Leave a Comment